MONTHYEARML22153A1302022-05-24024 May 2022 News Release-III-22-013: NRC to Hold Public Meeting to Discuss 2021 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-21-016, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Donald C. Cook Nuclear Power Plant2021-07-0606 July 2021 Press Release-III-21-016: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-20-007, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Donald C. Cook Nuclear Power Plant2020-07-14014 July 2020 Press Release-III-20-007: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-20-001, NRC Names New Senior Resident Inspector at Donald C. Cook Nuclear Power Plant2020-01-29029 January 2020 Press Release-III-20-001: NRC Names New Senior Resident Inspector at Donald C. Cook Nuclear Power Plant Press Release-III-19-019, NRC to Hold Open House to Discuss 2018 Performance of Donald C. Cook Nuclear Power Plant2019-07-15015 July 2019 Press Release-III-19-019: NRC to Hold Open House to Discuss 2018 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-18-027, NRC to Hold Open House to Discuss 2017 Performance of Donald C. Cook Nuclear Power Plant2018-08-13013 August 2018 Press Release-III-18-027: NRC to Hold Open House to Discuss 2017 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-17-023, NRC to Conduct Open House to Discuss 2016 Performance of Donald C. Cook Nuclear Power Plant2017-07-20020 July 2017 Press Release-III-17-023: NRC to Conduct Open House to Discuss 2016 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-16-021, NRC to Hold Open House to Discuss Agency'S Assessment of D.C. Cook Nuclear Power Plant2016-08-17017 August 2016 Press Release-III-16-021: NRC to Hold Open House to Discuss Agency'S Assessment of D.C. Cook Nuclear Power Plant Press Release-III-16-018, NRC Evaluates Unusual Event at DC Cook Nuclear Plant2016-07-0606 July 2016 Press Release-III-16-018: NRC Evaluates Unusual Event at DC Cook Nuclear Plant Press Release-15-068, NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors2015-10-27027 October 2015 Press Release-15-068: NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors Press Release-III-15-021, NRC Schedules Open House Aug. 31 to Discuss Performance of DC Cook Nuclear Power Plant2015-08-24024 August 2015 Press Release-III-15-021: NRC Schedules Open House Aug. 31 to Discuss Performance of DC Cook Nuclear Power Plant ML14184B2762014-07-0303 July 2014 Press Release No. III-14-024: NRC Schedules Public Meeting July 8 to Discuss Performance of D.C. Cook Nuclear Power Plant Press Release-III-14-017, NRC Names New Resident Inspector at D.C. Cook Nuclear Station2014-05-12012 May 2014 Press Release-III-14-017: NRC Names New Resident Inspector at D.C. Cook Nuclear Station Press Release-III-13-020, NRC Will Hold an Open House on 2012 D.C. Cook Nuclear Power Plant Performance on May 302013-05-23023 May 2013 Press Release-III-13-020: NRC Will Hold an Open House on 2012 D.C. Cook Nuclear Power Plant Performance on May 30 Press Release-III-12-026, NRC Issues Confirmatory Order to D.C. Cook Nuclear Power Plant2012-06-28028 June 2012 Press Release-III-12-026: NRC Issues Confirmatory Order to D.C. Cook Nuclear Power Plant Press Release-III-12-019, NRC Schedules Open House for May 31 to Discuss D. C. Cook Nuclear Power Plant Performance and NRC Oversight2012-05-24024 May 2012 Press Release-III-12-019: NRC Schedules Open House for May 31 to Discuss D. C. Cook Nuclear Power Plant Performance and NRC Oversight Press Release-III-11-021, NRC Schedules Open House for June 16 to Discuss D. C. Cook Nuclear Power Plant Performance and NRC Oversight2011-06-0303 June 2011 Press Release-III-11-021: NRC Schedules Open House for June 16 to Discuss D. C. Cook Nuclear Power Plant Performance and NRC Oversight Press Release-III-10-018, NRC Schedules Open House to Discuss Nuclear Issues and 2009 Performance of D.C. Cook Nuclear Plant2010-05-18018 May 2010 Press Release-III-10-018: NRC Schedules Open House to Discuss Nuclear Issues and 2009 Performance of D.C. Cook Nuclear Plant Press Release-III-09-019, NRC Schedules Open House to Discuss Nuclear Power Plant Issues and 2008 Performance of D.C. Cook Nuclear Power Plant2009-05-20020 May 2009 Press Release-III-09-019: NRC Schedules Open House to Discuss Nuclear Power Plant Issues and 2008 Performance of D.C. Cook Nuclear Power Plant Press Release-III-08-039, NRC Begins Special Inspection at the DC Cook Nuclear Plant2008-09-24024 September 2008 Press Release-III-08-039: NRC Begins Special Inspection at the DC Cook Nuclear Plant Press Release-III-08-027, NRC Names New Resident Inspector at D.C. Cook Nuclear Power Plant2008-07-11011 July 2008 Press Release-III-08-027: NRC Names New Resident Inspector at D.C. Cook Nuclear Power Plant Press Release-III-08-014, NRC to Discuss 2007 Performance Assessment for D.C. Cook Nuclear Power Plant2008-04-11011 April 2008 Press Release-III-08-014: NRC to Discuss 2007 Performance Assessment for D.C. Cook Nuclear Power Plant Press Release-III-07-013, - NRC to Discuss 2006 Performance Assessment for D.C. Cook Nuclear Power Plant2007-04-0606 April 2007 Press Release-III-07-013 - NRC to Discuss 2006 Performance Assessment for D.C. Cook Nuclear Power Plant Press Release-III-06-030, NRC Proposes $60,000 Fine Against Indiana Michigan Power for Emergency Plan Violation at D. C. Cook Nuclear Plant2006-10-11011 October 2006 Press Release-III-06-030: NRC Proposes $60,000 Fine Against Indiana Michigan Power for Emergency Plan Violation at D. C. Cook Nuclear Plant Press Release-III-06-028, NRC to Discuss 2005 Performance Assessment for D. C. Cook Nuclear Power Plant2006-07-0303 July 2006 Press Release-III-06-028: NRC to Discuss 2005 Performance Assessment for D. C. Cook Nuclear Power Plant Press Release-III-05-044, NRC Proposes $60,000 Fine Against D.C. Cook for Failure to Provide Complete and Accurate Information2005-11-28028 November 2005 Press Release-III-05-044: NRC Proposes $60,000 Fine Against D.C. Cook for Failure to Provide Complete and Accurate Information Press Release-III-05-043, NRC Begins Special Inspection of Electrical Problems in Shutdown at D.C. Cook Nuclear Power Plant2005-11-10010 November 2005 Press Release-III-05-043: NRC Begins Special Inspection of Electrical Problems in Shutdown at D.C. Cook Nuclear Power Plant Press Release-05-119, NRC Renews Operating Licenses for Donald C. Cook Nuclear Plant for an Additional 20 Years2005-08-30030 August 2005 Press Release-05-119: NRC Renews Operating Licenses for Donald C. Cook Nuclear Plant for an Additional 20 Years Press Release-05-075, NRC Finds No Significant Environmental Impacts from Extended Operation of Cook Nuclear Plant, Units 1 and 22005-05-0303 May 2005 Press Release-05-075: NRC Finds No Significant Environmental Impacts from Extended Operation of Cook Nuclear Plant, Units 1 and 2 Press Release-III-05-019, NRC to Discuss 2004 Performance Assessment for D.C. Cook Nuclear Power Plant2005-04-15015 April 2005 Press Release-III-05-019: NRC to Discuss 2004 Performance Assessment for D.C. Cook Nuclear Power Plant Press Release-III-04-031, Meeting to Discuss Results of a Special Inspection at D.C. Cook2004-05-0606 May 2004 Press Release-III-04-031: Meeting to Discuss Results of a Special Inspection at D.C. Cook Press Release-03-161, NRC Announces Opportunity for Hearing on Application to Renew D.C. Cook, Units 1 and 2, Operating Licenses2003-12-11011 December 2003 Press Release-03-161: NRC Announces Opportunity for Hearing on Application to Renew D.C. Cook, Units 1 and 2, Operating Licenses Press Release-03-055, NRC Approves Power Uprate for D.C. Cook Unit 22003-05-0505 May 2003 Press Release-03-055: NRC Approves Power Uprate for D.C. Cook Unit 2 Press Release-III-03-036, NRC Dispatches Inspectors to Review Cook Nuclear Plant Shutdown2003-04-24024 April 2003 Press Release-III-03-036: NRC Dispatches Inspectors to Review Cook Nuclear Plant Shutdown Press Release-III-03-030, NRC to Meet with Officials from American Electric Power Company to Discuss Safety Performance at D.C. Cook2003-04-0808 April 2003 Press Release-III-03-030: NRC to Meet with Officials from American Electric Power Company to Discuss Safety Performance at D.C. Cook Press Release-02-146, NRC Approves Power Uprate for D.C. Cook Nuclear Plant2002-12-24024 December 2002 Press Release-02-146: NRC Approves Power Uprate for D.C. Cook Nuclear Plant Press Release-III-02-057, NRC Cites D.C. Cook Nuclear Power Station for Violation of Low to Moderate Safety Significance2002-10-0808 October 2002 Press Release-III-02-057: NRC Cites D.C. Cook Nuclear Power Station for Violation of Low to Moderate Safety Significance Press Release-III-02-044, NRC Staff to Meet with American Electric Power Co. to Discuss Safety Significance of Equipment Cooling Issue at D.C. Cook Plant2002-07-22022 July 2002 Press Release-III-02-044: NRC Staff to Meet with American Electric Power Co. to Discuss Safety Significance of Equipment Cooling Issue at D.C. Cook Plant Press Release-III-02-029, NRC Cites D.C. Cook Nuclear Power Station for Violation of Low to Moderate Safety Significance2002-05-20020 May 2002 Press Release-III-02-029: NRC Cites D.C. Cook Nuclear Power Station for Violation of Low to Moderate Safety Significance Press Release-III-02-016, NRC to Meet with American Electric Power April 12 to Discuss D.C. Cook Nuclear Power Station Safety Performance2002-04-0303 April 2002 Press Release-III-02-016: NRC to Meet with American Electric Power April 12 to Discuss D.C. Cook Nuclear Power Station Safety Performance Press Release-III-00-063, NRC Prohibits Former Clerical Worker at D.C. Cook Plant from Working in NRC-Licensed Activities2000-11-24024 November 2000 Press Release-III-00-063: NRC Prohibits Former Clerical Worker at D.C. Cook Plant from Working in NRC-Licensed Activities 2022-05-24
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION 801 Warrenville Road Lisle IL 60532 Web Site: http://www.nrc.gov No. III-03-030 April 8, 2003 CONTACT: Jan Strasma (630) 829-9663 E-mail: opa3@nrc.gov Viktoria Mitlyng (630) 829-9662 NRC TO MEET WITH OFFICIALS FROM AMERICAN ELECTRIC POWER COMPANY TO DISCUSS SAFETY PERFORMANCE AT D. C. COOK The U.S. Nuclear Regulatory Commission staff will meet with officials from the American Electric Power Company on Thursday, April 10, to discuss the results of NRCs annual assessment of the D. C. Cook nuclear power plant, located in Stevensville, Michigan.
The meeting will be held at 5:30 p.m. at the Park Inn Conference Center, 4290 Red Arrow Highway, in Stevensville. The public is invited to observe the meeting, and NRC officials will be available before the conclusion of the meeting for questions and comments from the public.
A March 4 letter from the NRC to the American Electric Power Company addresses plant safety performance during the previous year and forms the basis for the meeting discussions. The letter indicates that, overall, D. C. Cook operated safely.
The NRC uses a performance-based regulatory safety inspection program, which utilizes a color-coded scale of increasing levels of safety significance, beginning with "green" and progressing to "white," "yellow" and "red." The oversight process uses performance indicators submitted by nuclear power plants and findings from NRCs inspections to evaluate each plants safety performance. These findings fall into seven specific areas, or "cornerstones," which are key indicators of the safety of a plants operations. When the regulatory process identifies two "white" issues in the same cornerstone, this cornerstone is considered "degraded." Having a "degraded" cornerstone is not an indication that the plant is unsafe, but it does result in heightened regulatory attention.
The letter indicates that two findings of low to moderate safety significance were identified by the NRC and resulted in degraded performance in the Unit 2 Mitigating Systems cornerstone. The first finding was associated with failures of the Unit 2 auxiliary feedwater pump to start. (This finding is described in an NRC press release dated May 20, 2002). Details on this finding can be accessed on the NRC web site at: http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/REPORTS/cook_2002005.pdf.
The second finding was associated with improper installation of an essential service water system strainer, which affected both units. (This finding is described in an NRC press release dated October 8, 2002). Details on this finding can be accessed on the NRC web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/REPORTS/cook_2001017.pdf.
The March 4 letter also addresses a substantive cross-cutting issue in the area of problem identification and resolution. The NRC conducted a problem identification and resolution inspection, which "identified several issues with the adequacy of apparent cause evaluations and with the implementation of corrective actions." The letter further states, "Based on the continued identification of findings associated with poor corrective actions, the NRC is concerned that your performance in this area is on a declining trend. You are requested to specifically address the actions that you are taking to improve performance in this cross cutting area at the end of cycle public meeting."
The letter is available from Region III Public Affairs Office and on the NRC web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/cook_2002q4.pdf.
In addition, the letter notes: "As you are aware, since the terrorist attacks of September 11, 2001, the NRC has issued several Orders and threat advisories to enhance security capabilities and improve guard force readiness. We have conducted inspections to review your implementation of these requirements and have monitored your actions in response to changing threat advisories. For calendar year 2003, we plan to continue these inspections and conduct portions of the security baseline inspection program, as well as perform additional inspections to evaluate your compliance with new requirements that may be ordered."
Current performance information for D. C. Cook is available on the NRC web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/COOK1/cook1_chart.html.
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/COOK2/cook2_chart.html.