MONTHYEARML22153A1302022-05-24024 May 2022 News Release-III-22-013: NRC to Hold Public Meeting to Discuss 2021 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-21-016, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Donald C. Cook Nuclear Power Plant2021-07-0606 July 2021 Press Release-III-21-016: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-20-007, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Donald C. Cook Nuclear Power Plant2020-07-14014 July 2020 Press Release-III-20-007: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-20-001, NRC Names New Senior Resident Inspector at Donald C. Cook Nuclear Power Plant2020-01-29029 January 2020 Press Release-III-20-001: NRC Names New Senior Resident Inspector at Donald C. Cook Nuclear Power Plant Press Release-III-19-019, NRC to Hold Open House to Discuss 2018 Performance of Donald C. Cook Nuclear Power Plant2019-07-15015 July 2019 Press Release-III-19-019: NRC to Hold Open House to Discuss 2018 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-18-027, NRC to Hold Open House to Discuss 2017 Performance of Donald C. Cook Nuclear Power Plant2018-08-13013 August 2018 Press Release-III-18-027: NRC to Hold Open House to Discuss 2017 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-17-023, NRC to Conduct Open House to Discuss 2016 Performance of Donald C. Cook Nuclear Power Plant2017-07-20020 July 2017 Press Release-III-17-023: NRC to Conduct Open House to Discuss 2016 Performance of Donald C. Cook Nuclear Power Plant Press Release-III-16-021, NRC to Hold Open House to Discuss Agency'S Assessment of D.C. Cook Nuclear Power Plant2016-08-17017 August 2016 Press Release-III-16-021: NRC to Hold Open House to Discuss Agency'S Assessment of D.C. Cook Nuclear Power Plant Press Release-III-16-018, NRC Evaluates Unusual Event at DC Cook Nuclear Plant2016-07-0606 July 2016 Press Release-III-16-018: NRC Evaluates Unusual Event at DC Cook Nuclear Plant Press Release-15-068, NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors2015-10-27027 October 2015 Press Release-15-068: NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors Press Release-III-15-021, NRC Schedules Open House Aug. 31 to Discuss Performance of DC Cook Nuclear Power Plant2015-08-24024 August 2015 Press Release-III-15-021: NRC Schedules Open House Aug. 31 to Discuss Performance of DC Cook Nuclear Power Plant ML14184B2762014-07-0303 July 2014 Press Release No. III-14-024: NRC Schedules Public Meeting July 8 to Discuss Performance of D.C. Cook Nuclear Power Plant Press Release-III-14-017, NRC Names New Resident Inspector at D.C. Cook Nuclear Station2014-05-12012 May 2014 Press Release-III-14-017: NRC Names New Resident Inspector at D.C. Cook Nuclear Station Press Release-III-13-020, NRC Will Hold an Open House on 2012 D.C. Cook Nuclear Power Plant Performance on May 302013-05-23023 May 2013 Press Release-III-13-020: NRC Will Hold an Open House on 2012 D.C. Cook Nuclear Power Plant Performance on May 30 Press Release-III-12-026, NRC Issues Confirmatory Order to D.C. Cook Nuclear Power Plant2012-06-28028 June 2012 Press Release-III-12-026: NRC Issues Confirmatory Order to D.C. Cook Nuclear Power Plant Press Release-III-12-019, NRC Schedules Open House for May 31 to Discuss D. C. Cook Nuclear Power Plant Performance and NRC Oversight2012-05-24024 May 2012 Press Release-III-12-019: NRC Schedules Open House for May 31 to Discuss D. C. Cook Nuclear Power Plant Performance and NRC Oversight Press Release-III-11-021, NRC Schedules Open House for June 16 to Discuss D. C. Cook Nuclear Power Plant Performance and NRC Oversight2011-06-0303 June 2011 Press Release-III-11-021: NRC Schedules Open House for June 16 to Discuss D. C. Cook Nuclear Power Plant Performance and NRC Oversight Press Release-III-10-018, NRC Schedules Open House to Discuss Nuclear Issues and 2009 Performance of D.C. Cook Nuclear Plant2010-05-18018 May 2010 Press Release-III-10-018: NRC Schedules Open House to Discuss Nuclear Issues and 2009 Performance of D.C. Cook Nuclear Plant Press Release-III-09-019, NRC Schedules Open House to Discuss Nuclear Power Plant Issues and 2008 Performance of D.C. Cook Nuclear Power Plant2009-05-20020 May 2009 Press Release-III-09-019: NRC Schedules Open House to Discuss Nuclear Power Plant Issues and 2008 Performance of D.C. Cook Nuclear Power Plant Press Release-III-08-039, NRC Begins Special Inspection at the DC Cook Nuclear Plant2008-09-24024 September 2008 Press Release-III-08-039: NRC Begins Special Inspection at the DC Cook Nuclear Plant Press Release-III-08-027, NRC Names New Resident Inspector at D.C. Cook Nuclear Power Plant2008-07-11011 July 2008 Press Release-III-08-027: NRC Names New Resident Inspector at D.C. Cook Nuclear Power Plant Press Release-III-08-014, NRC to Discuss 2007 Performance Assessment for D.C. Cook Nuclear Power Plant2008-04-11011 April 2008 Press Release-III-08-014: NRC to Discuss 2007 Performance Assessment for D.C. Cook Nuclear Power Plant Press Release-III-07-013, - NRC to Discuss 2006 Performance Assessment for D.C. Cook Nuclear Power Plant2007-04-0606 April 2007 Press Release-III-07-013 - NRC to Discuss 2006 Performance Assessment for D.C. Cook Nuclear Power Plant Press Release-III-06-030, NRC Proposes $60,000 Fine Against Indiana Michigan Power for Emergency Plan Violation at D. C. Cook Nuclear Plant2006-10-11011 October 2006 Press Release-III-06-030: NRC Proposes $60,000 Fine Against Indiana Michigan Power for Emergency Plan Violation at D. C. Cook Nuclear Plant Press Release-III-06-028, NRC to Discuss 2005 Performance Assessment for D. C. Cook Nuclear Power Plant2006-07-0303 July 2006 Press Release-III-06-028: NRC to Discuss 2005 Performance Assessment for D. C. Cook Nuclear Power Plant Press Release-III-05-044, NRC Proposes $60,000 Fine Against D.C. Cook for Failure to Provide Complete and Accurate Information2005-11-28028 November 2005 Press Release-III-05-044: NRC Proposes $60,000 Fine Against D.C. Cook for Failure to Provide Complete and Accurate Information Press Release-III-05-043, NRC Begins Special Inspection of Electrical Problems in Shutdown at D.C. Cook Nuclear Power Plant2005-11-10010 November 2005 Press Release-III-05-043: NRC Begins Special Inspection of Electrical Problems in Shutdown at D.C. Cook Nuclear Power Plant Press Release-05-119, NRC Renews Operating Licenses for Donald C. Cook Nuclear Plant for an Additional 20 Years2005-08-30030 August 2005 Press Release-05-119: NRC Renews Operating Licenses for Donald C. Cook Nuclear Plant for an Additional 20 Years Press Release-05-075, NRC Finds No Significant Environmental Impacts from Extended Operation of Cook Nuclear Plant, Units 1 and 22005-05-0303 May 2005 Press Release-05-075: NRC Finds No Significant Environmental Impacts from Extended Operation of Cook Nuclear Plant, Units 1 and 2 Press Release-III-05-019, NRC to Discuss 2004 Performance Assessment for D.C. Cook Nuclear Power Plant2005-04-15015 April 2005 Press Release-III-05-019: NRC to Discuss 2004 Performance Assessment for D.C. Cook Nuclear Power Plant Press Release-III-04-031, Meeting to Discuss Results of a Special Inspection at D.C. Cook2004-05-0606 May 2004 Press Release-III-04-031: Meeting to Discuss Results of a Special Inspection at D.C. Cook Press Release-03-161, NRC Announces Opportunity for Hearing on Application to Renew D.C. Cook, Units 1 and 2, Operating Licenses2003-12-11011 December 2003 Press Release-03-161: NRC Announces Opportunity for Hearing on Application to Renew D.C. Cook, Units 1 and 2, Operating Licenses Press Release-03-055, NRC Approves Power Uprate for D.C. Cook Unit 22003-05-0505 May 2003 Press Release-03-055: NRC Approves Power Uprate for D.C. Cook Unit 2 Press Release-III-03-036, NRC Dispatches Inspectors to Review Cook Nuclear Plant Shutdown2003-04-24024 April 2003 Press Release-III-03-036: NRC Dispatches Inspectors to Review Cook Nuclear Plant Shutdown Press Release-III-03-030, NRC to Meet with Officials from American Electric Power Company to Discuss Safety Performance at D.C. Cook2003-04-0808 April 2003 Press Release-III-03-030: NRC to Meet with Officials from American Electric Power Company to Discuss Safety Performance at D.C. Cook Press Release-02-146, NRC Approves Power Uprate for D.C. Cook Nuclear Plant2002-12-24024 December 2002 Press Release-02-146: NRC Approves Power Uprate for D.C. Cook Nuclear Plant Press Release-III-02-057, NRC Cites D.C. Cook Nuclear Power Station for Violation of Low to Moderate Safety Significance2002-10-0808 October 2002 Press Release-III-02-057: NRC Cites D.C. Cook Nuclear Power Station for Violation of Low to Moderate Safety Significance Press Release-III-02-044, NRC Staff to Meet with American Electric Power Co. to Discuss Safety Significance of Equipment Cooling Issue at D.C. Cook Plant2002-07-22022 July 2002 Press Release-III-02-044: NRC Staff to Meet with American Electric Power Co. to Discuss Safety Significance of Equipment Cooling Issue at D.C. Cook Plant Press Release-III-02-029, NRC Cites D.C. Cook Nuclear Power Station for Violation of Low to Moderate Safety Significance2002-05-20020 May 2002 Press Release-III-02-029: NRC Cites D.C. Cook Nuclear Power Station for Violation of Low to Moderate Safety Significance Press Release-III-02-016, NRC to Meet with American Electric Power April 12 to Discuss D.C. Cook Nuclear Power Station Safety Performance2002-04-0303 April 2002 Press Release-III-02-016: NRC to Meet with American Electric Power April 12 to Discuss D.C. Cook Nuclear Power Station Safety Performance Press Release-III-00-063, NRC Prohibits Former Clerical Worker at D.C. Cook Plant from Working in NRC-Licensed Activities2000-11-24024 November 2000 Press Release-III-00-063: NRC Prohibits Former Clerical Worker at D.C. Cook Plant from Working in NRC-Licensed Activities 2022-05-24
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION 801 Warrenville Road Lisle IL 60532 Web Site: http://www.nrc.gov E-mail: opa3@nrc.gov No. III-02-057 October 8, 2002 CONTACT: Jan Strasma (630) 829-9663 Viktoria Mitlyng (630) 829-9662 NRC CITES D.C. COOK NUCLEAR POWER STATION FOR VIOLATION OF LOW TO MODERATE SAFETY SIGNIFICANCE The Nuclear Regulatory Commission staff has determined that a violation of NRC safety regulations at the D. C. Cook Nuclear Power station near Bridgman, Michigan, should be characterized as white, meaning that it is an issue of low to moderate importance to safety. The two-reactor facility is operated by American Electric Power Company.
During an inspection conducted between August 2001 and May of this year, NRC inspectors determined that an essential service water (ESW) strainer was improperly installed. This resulted in lake sediment and debris being drawn into the water system on August 29 of last year.
When debris entered the system, which provides cooling for the emergency diesel generators and other plant safety equipment, the water flow to various heat exchangers was reduced.
The plants four emergency diesel generators were not operating nor needed at the time; however, if they had been needed to supply power to plant safety systems, their function might have been impaired.
NRC inspection findings are evaluated using a four-level scale of safety significance, ranging from "green" for a finding of minor significance, through "white" and "yellow" to "red," for a finding of high safety significance.
The debris problem at D. C. Cook was initially characterized as a "yellow" finding in an inspection report available for viewing in the NRC's electronic reading room at http://www.nrc.gov/reading-rm/adams.html. Help in using this on-line system is available by contacting the NRC Public Document Room at 301/415-4737 or 1/800/397-4209.
On July 25, the NRC held a regulatory conference with the utility to further discuss the companys views on this issue.
The NRC staff used the information presented by the utility in the regulatory conference and correspondence, along with its inspection findings, to issue the final safety significance determination of the problem as white. The final determination is posted on the NRC's web site at:
http://www.nrc.gov/reading-rm/doc-collections/enforcement/actions/reactors.
In addition to the white determination, the NRC issued a Notice of Violation to American Electric Power for violation of the NRC requirement that activities affecting quality must be prescribed by documented instructions, procedures, and drawings. The licensee had taken corrective action to preclude recurrence of the problem addressed in the Notice of Violation.
Because this is the utilitys second white finding in the Mitigating Systems Cornerstone in the Reactor Safety and Strategic Performance Area, the NRC will increase its oversight activities for the utility.
The previous white finding involved the failure of the Unit 2 Turbine-Driven Auxiliary Feedwater Pump to start. It is described in NRC News Release III-02-029 issued on May 20. The news release is posted on the NRCs web site at:
http://www.nrc.gov/reading-rm/doc-collections/news/2002/.