A E .,.

Entergy Nuclear Operations, Inc.

c:->> n"ergx Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530 Tel 269 764 2000 Jeffery A. Hardy Regulatory Assurance Manager PNP 2018-017 March 29, 2018 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Milestone Schedule for Generic Safety Issue - 191 Resolution Palisades Nuclear Plant Docket 50-255 Renewed Facility Operating License No. DPR-20

REFERENCES:

1. Entergy Nuclear Operations, Inc. letter to NRC, PNP 2013-041, "Generic Safety Issue - 191 Closure Option," dated May 15, 2013 (ADAMS Accession No. ML13136A0063)
2. Entergy Nuclear Operations, Inc. letter to NRC, PNP 2013-092, "Schedule for Generic Safety Issue - 191 Resolution," dated December 18, 2013 (ADAMS Accession No. ML13353A567)
3. NRC letter to Entergy Nuclear Operations, Inc, "Summary of September 28, 2016, Public Meeting with Entergy Nuclear Operations, Inc.

Regarding the Proposed Closure Plan for Generic Safety Issue 191,

'Assessment of Debris Accumulation on Pressurized Water Reactor (PWR) Sump Performance,'" dated October 11, 2016 (ADAMS Accession No. ML16277A677) ,

4. Entergy Nuclear Operations, Inc. letter to NRC, PNP 2017-001, "Certification of Permanent Cessation of Power Operations," dated January 4, 2017 (ADAMS Accession No. ML17004A062)
5. NRC letter to Entergy Nuclear Operations, Inc, "Palisades Nuclear Plant

- Closure of NRC Generic Letter 2004-02 (CAC No. MC4701 )," dated February 22,2017 (ADAMS Accession No. ML17030A014)

6. Entergy Nuclear Operations, Inc. letter to NRC, PNP 2017-058, "Certification of Permanent Cessation of Power Operations," dated September 28, 2017 (ADAMS Accession No. ML17271A233)
7. Entergy Nuclear Operations, Inc. letter to NRC, PNP 2017-065, "Supplement to Certification of Permanent Cessation of Power Operations," dated October 19, 2017 (ADAMS Accession No. ML17292A032)

PNP 2018-017 Page 2 of 2

Dear Sir or Madam:

In Reference 1, Entergy Nuclear Operations, Inc. (ENO) notified the NRC that, for resolution of Generic Safety Issue -191 (GSI-191) at Palisades Nuclear Plant (PNP), it had selected for the risk-informed version of Option 2 in Commission Paper SECY-12-0093, "Closure Options for Generic Safety Issue - 191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance," dated September 13, 2004.

In Reference 2, ENO submitted a schedule for GSI-191 resolution. In Reference 3, a public meeting notice was issued to summarize a meeting ENO held with NRC to discuss the status of the PNP GSI-191 project.

. In Reference 4, ENO submitted a certification of permanent cessation of power operations with a shutdown date of October 1, 2018. In Reference 5, NRC issued a closure letter for GSI-191 citing the planned shutdown date of October 1, 2018 for PNP. In Reference 6, ENO notified the NRC that PNP would continue operation and changed the date that PNP will permanently cease power operation from October 1, 2018 to the spring of 2022. This notification was supplemented in Reference 7, which notified the NRC that PNP will permanently cease power operation no later than May 31,2022.

Due to the postponed shutdown date for PNP, ENO is providing a revised schedule for GSI-191 risk-informed resolution at PNP in Attachment 1.

Summary of Commitments This letter contains no new commitments and no revisions to existing commitments.

94k\C Sincerely, JAH/ach Attachments: 1. Milestone Schedule for Generic Safety Issue-191 Resolution cc: Administrator, Region III, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC

Attachment 1 Palisades Nuclear Plant Milestone Schedule for Generic Safety Issue -191 Resolution Milestone Schedule The schedule provided below contains the major milestones for completion of the GSI-191 resolution path activities at PNP.

Schedule for Palisades Nuclear Plant Risk-Informed Resolution Milestone Milestone Completion Date 1 Restart Project Post-Shutdown Announcement ComJ21ete Plant Engineering Studies October 2018 (Refueling Outage 1R26) (Fall 2018)

Proposed NRC Meeting on Test Plan December 2018 Strainer Test March 2019 Proposed NRC Meeting to Witness Strainer Test May 2019 Analyze Strainer Test Results 2 July 2019 Determine Necessary Modifications Al!gust 2019 Corrosion and Autoclave Test and Analysis October 2019 (Refueling Outage 1R27) (Summer 2020)

Prepare Licensing_ Amendment Request (LAR) December 2020 NRC Presubmittal Meeting January 2021 Submit LAR February 2021 LAR Approval February 2022 JDefuelinjl Outage 1R28) (May 2022) 1 Milestone dates are subject to change as Implementation details are developed.

20etermine if the risk-informed option is necessary or if a deterministic resolution is viable.

Page 1 of 1