PNP 2013-092, Schedule for Generic Safety Issue - 191 Resolution

From kanterella
(Redirected from ML13353A567)
Jump to navigation Jump to search
Schedule for Generic Safety Issue - 191 Resolution
ML13353A567
Person / Time
Site: Palisades Entergy icon.png
Issue date: 12/18/2013
From: Gustafson O
Entergy Nuclear Operations
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PNP 2013-092
Download: ML13353A567 (5)


Text

Entergy Nuclear Operations, Inc.

Palisades Nuclear Plant 27780 Blue Star Memorial Highway Covert, MI 49043-9530 Tel 269 764 2000 Otto W. Gustafson Regulatory Assurance Manager PNP 2013-092 December 18, 2013 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001

SUBJECT:

Schedule for Generic Safety Issue - 191 Resolution Palisades Nuclear Plant Docket 50-255 License No. DPR-20

REFERENCES:

1. Entergy Nuclear Operations, Inc. letter, PNP 2013-041, "Generic Safety Issue-191 Closure Option," dated May 15, 2013 (ADAMS Accession No. ML13136A006)
2. NRC Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors," dated September 13, 2004 (ADAMS Accession No. ML042360586)
3. NRC SECY-12-0093, "Closure Options for Generic Safety Issue

- 191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance," dated July 9, 2012 (ADAMS Accession No. ML121310648)

Dear Sit or Madam:

By letter dated May 15, 2013 (Reference 1), Entergy Nuclear Operations, Inc. (ENO) notified the Nuclear Regulatory Commission (NRC) that it had selected the Risk-Informed version of Option 2 for resolution of Generic Safety Issue (GSI)-191 (Reference 2) for the Palisades Nuclear Plant (PNP), in accordance with closure options specified in Commission Paper SECY-12-0093 (Reference 3). In Reference 1, ENO committed to submit a schedule for completion of risk-informed resolution path activities.

The PNP schedule for completion of risk-informed resolution path activities is provided in the enclosure.

PNP 2013-092 Page 2 Summary of Commitments This letter contains no new commitments. This letter completes the following commitment:

"ENO will submit a schedule for completion of the risk-informed resolution path activities that provides for submittal of a licensing action following issuance of a safety evaluation (SE) for the South Texas Project (STP) license amendment request (LAR)."

This was a one-time action, with a scheduled completion date of December 31,2013.

owgljse

Enclosure:

Palisades Nuclear Plant Schedule for Generic Safety Issue-191 Resolution cc: Administrator, Region III, USNRC Project Manager, Palisades, USNRC Resident Inspector, Palisades, USNRC

Enclosure Palisades Nuclear Plant Schedule for Generic Safety Issue-191 Resolution

Palisades Nuclear Plant Schedule for Generic Safety Issue-191 Resolution Introduction By letter dated May 15, 2013 (Reference 1), Entergy Nuclear Operations, Inc. (ENO) notified the Nuclear Regulatory Commission (NRC) that it had selected the Risk-Informed version of Option 2 for resolution of Generic Safety Issue (GSI)-191 (Reference 2) for the Palisades Nuclear Plant (PNP), in accordance with closure options specified in Commission Paper SECY-12-0093 (Reference 3). Option 2 includes a risk-informed approach. In Reference 1, ENO committed to submit a schedule for completion of risk-informed resolution path activities. The PNP schedule for completion of risk-informed resolution path activities is provided below.

Milestone Schedule The schedule provided below contains the major milestones for completion of risk-informed resolution path activities at PNP.

Schedule for Palisades Nuclear Plant Risk-Informed Resolution Milestone Milestone Date l Conduct Meeting with NRC staff Completed August 2013 Establish Break Frequencies August 2014 Modify Plant PRA Model December 2014 Assemble Base Inputs for Analysis Software March 2015 Thermal Hydraulics Modeling June 2015 Strainer Head Loss/Bypass Testing January 2016 Chemical Effects Testing January 2016 Finalize Analysis Software Inputs March 2016 Perform Sensitivity Analysis June 2016 Determine ~CDF and ~LERF September 2016 Submit LAR for Risk-Informed Approach March 2017 Modification Package Prepared December 2017 Modifications Installed December 2018 Receive SE for Risk-Informed Approach March 2019 Supplemental Modification Package Prepared June 2019 Supplemental Modifications Installed May 2020 Licensing Basis Updated June 2020 1 Milestone dates are subject to change as implementation details are developed.

Page 1 of 2

References

1. Entergy Nuclear Operations, Inc. letter, PNP 2013-041, "Generic Safety Issue-191 Closure Option," dated May 15, 2013 (ADAMS Accession No. ML13136A006)
2. NRC Generic Letter 2004-02, "Potential Impact of Debris Blockage on Emergency Recirculation During Design Basis Accidents at Pressurized-Water Reactors," dated September 13, 2004 (ADAMS Accession No. ML042360586)
3. NRC SECY-12-0093, "Closure Options for Generic Safety Issue - 191, Assessment of Debris Accumulation on Pressurized-Water Reactor Sump Performance," dated July 9,2012 (ADAMS Accession No. ML121310648)