PNO-III-11-013, A, Prairie Island Unit 2 Unplanned Shutdown for Greater than 72 Hours (Update)

From kanterella
(Redirected from PNO-III-11-013)
Jump to navigation Jump to search
PNO-III-11-013A, Prairie Island Unit 2 Unplanned Shutdown for Greater than 72 Hours (Update)
ML11293A090
Person / Time
Site: Prairie Island Xcel Energy icon.png
Issue date: 10/20/2011
From: Kenneth Riemer, Karla Stoedter
NRC/RGN-III
To:
References
PNO-III-013A
Download: ML11293A090 (1)


PRELIMINARY NOTIFICATION - REGION III October 20, 2011 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE - PNO-III-11-013A This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. Some of the information may not yet be fully verified or evaluated by the Region III staff.

Facility Licensee Emergency Classification Prairie Island Nuclear Generating Plant, Unit 2 Notification of Unusual Event Northern States Power Company, Minnesota Alert Welch, Minnesota Site Area Emergency Docket No: 50-306 General Emergency License No: DPR-60 x Not Applicable

SUBJECT:

PRAIRIE ISLAND UNIT 2 UNPLANNED SHUTDOWN FOR GREATER THAN 72 HOURS (UPDATE)

==

Description:==

On October 20, 2011, at approximately 03:43 a.m. CDT, Prairie Island Unit 2 was restarted after a forced outage. The outage began on October 4, 2011, after one of two reactor coolant pumps (RCP) experienced seal cooling water flow that was below procedural limits. The purpose of the seal is to keep water in the reactor coolant system. In order to keep the seal intact, a continuous flow of water is required. The rate at which flow comes out of a seal has to fall within a specified range in order to keep the RCP running. The licensee proceeded to shut down, as specified by their procedures, to replace the affected seal.

The licensee replaced the seals on both the RCPs during the forced shutdown. The NRC resident inspectors monitored the plant operator response during the shutdown and the reactor coolant pump seal replacement activities. Before the reactor start-up, the NRC inspectors reviewed the evaluations and tests performed to assure the adequacy of the plant repairs.

The inspectors were present in the control room to observe the Unit 2 restart.

Minnesota State officials have been informed of the plant restart. The information presented herein has been discussed with the licensee, and is current as of October 20, 2011, at 09:00 a.m. (CDT). This preliminary notification is issued for information only and no further action by the staff is anticipated.

ADAMS Accession Number ML11293A090 CONTACTS: Karla Stoedter Kenneth Riemer 651/388-8209 630/829-9628 Karla.Stoedter@nrc.gov Kenneth.Riemer@nrc.gov