MONTHYEARPNO-III-12-013, Planned Shutdown and Decommissioning of Kewaunee Power Station2012-10-23023 October 2012 PNO-III-12-013: Planned Shutdown and Decommissioning of Kewaunee Power Station PNO-III-09-002, Kewaunee Unplanned Shutdown Due to Main Steam Pressure Instruments Not Calibrated as Required2009-04-20020 April 2009 PNO-III-09-002 - Kewaunee Unplanned Shutdown Due to Main Steam Pressure Instruments Not Calibrated as Required PNO-III-07-004, A - Kewaunee Reactor Shutdown (Update)2007-03-12012 March 2007 PNO-III-07-004A - Kewaunee Reactor Shutdown (Update) ML0706004812007-03-0101 March 2007 PNO-III-07-004: Kewaunee Reactor Shutdown PNO-III-06-022, Kewaunee Reactor Shutdown and Startup2006-11-14014 November 2006 PNO-III-06-022: Kewaunee Reactor Shutdown and Startup PNO-III-06-019, Kewaunee: Tritium Detected in Groundwater Beneath Plant Buildings2006-08-14014 August 2006 PNO-III-06-019 Kewaunee: Tritium Detected in Groundwater Beneath Plant Buildings PNO-III-06-014, Kewaunee, Procedure Adherence Problems During Reactor Startup2006-05-23023 May 2006 PNO-III-06-014, Kewaunee, Procedure Adherence Problems During Reactor Startup PNO-III-06-012, A: Kewaunee: Manual Reactor Shutdown Following Feedwater Pump Trip (Update)2006-05-17017 May 2006 PNO-III-06-012A: Kewaunee: Manual Reactor Shutdown Following Feedwater Pump Trip (Update) ML0611803492006-04-28028 April 2006 PNO-III-06-012: Kewaunee, Manual Reactor Shutdown Following Feedwater Pump Trip PNO-III-05-003, Kewaunee Shutdown in Excess of 72 Hours Due to Auxiliary Feedwater System Declared Inoperable Due to High Energy Line Break Concerns2005-02-23023 February 2005 PNO-III-05-003: Kewaunee Shutdown in Excess of 72 Hours Due to Auxiliary Feedwater System Declared Inoperable Due to High Energy Line Break Concerns PNO-III-04-001, Kewaunee: Plant Shutdown Greater than 72 Hours and Initiation of NRC Special Inspection to Look Into Plant Shutdown Due to Both Trains of Safety Injection System Declared Inoperable2004-01-20020 January 2004 PNO-III-04-001 Kewaunee: Plant Shutdown Greater than 72 Hours and Initiation of NRC Special Inspection to Look Into Plant Shutdown Due to Both Trains of Safety Injection System Declared Inoperable PNO-III-02-022, Shutdown to Repair Component Cooling Heat Exchanger2002-05-0707 May 2002 PNO-III-02-022 - Shutdown to Repair Component Cooling Heat Exchanger 2012-10-23
[Table view] |
May 7, 2002 PRELIMINARY NOTIFICATION OF EVENT OR UNUSUAL OCCURRENCE -- PNO-III-02-022 This preliminary notification constitutes EARLY notice of events of POSSIBLE safety or public interest significance. The information is as initially received without verification or evaluation, and is basically all that is known by the Region III staff on this date.
Facility Licensee Emergency Classification Kewaunee Nuclear Power Plant Notification of Unusual Event Nuclear Management Company Alert Kewaunee, Wisconsin Site Area Emergency Docket: 050-00305 General Emergency x Not Applicable
SUBJECT:
SHUTDOWN TO REPAIR COMPONENT COOLING HEAT EXCHANGER DESCRIPTION:
At 11:43 a.m. CDT on May 5, 2002, the licensee began a reactor shutdown to repair the A heat exchanger in the safety-related Component Cooling Water system. The heat exchanger was declared inoperable when it was removed from service to investigate tube leakage within the heat exchanger of approximately 0.37 gallons per minute.
The leakage entered the service water system which discharges to Lake Michigan. There was no measurable radioactivity in the water discharged to the lake.
The licensee is developing its repair plans, including possible sleeving and/or plugging of the heat exchanger tubes found to be leaking.
The resident inspectors are monitoring the licensees investigation and repair efforts.
The State of Wisconsin will be informed. The information in this preliminary notification has been reviewed with licensee management.
The licensee notified the NRC Operations Center of the shutdown at 12:53 p.m. CDT on May 5, 2002. This information is current as of 1 p.m. CDT on May 7, 2002.
CONTACTS:
Julio Lara Roger Lanksbury 920/388-3156 630/829-9631