Letter Sequence Response to RAI |
---|
EPID:L-2024-LLR-0028, Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-8112 (Open) |
|
|
|
---|
Category:Letter type:PLA
MONTHYEARPLA-8145, Biennial 10 CFR 50.59 and 72.48 Summary Report and Changes to Regulatory Commitments - PLA-81452024-10-21021 October 2024 Biennial 10 CFR 50.59 and 72.48 Summary Report and Changes to Regulatory Commitments - PLA-8145 PLA-8148, Registration for the Use of Spent Fuel Storage Casks 311, 308, and 3102024-10-15015 October 2024 Registration for the Use of Spent Fuel Storage Casks 311, 308, and 310 PLA-8141, Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-81412024-09-18018 September 2024 Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-8141 PLA-8142, Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-81422024-09-18018 September 2024 Registration for the Use of Spent Fuel Storage Casks 306, 309, and 307 - PLA-8142 PLA-8117, 23rd Refueling Outage Owners Activity Report (PLA-8117)2024-07-23023 July 2024 23rd Refueling Outage Owners Activity Report (PLA-8117) PLA-8126, Response to Request for Confirmation of Information Regarding Relief Request 1RR062024-05-29029 May 2024 Response to Request for Confirmation of Information Regarding Relief Request 1RR06 PLA-8122, Annual Radiological Environmental Operating Report (PLA-8122)2024-05-28028 May 2024 Annual Radiological Environmental Operating Report (PLA-8122) PLA-8115, Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115)2024-05-23023 May 2024 Relief Request IRR06 One Time Extension to the Fourth 10-Year Inservice Testing Program Interval (PLA-8115) PLA-8101, Re 2023 Annual Report of Radiation Exposure2024-04-22022 April 2024 Re 2023 Annual Report of Radiation Exposure PLA-8095, 2023 Annual Radiological Environmental Operating Report (PLA-8095)2024-04-22022 April 2024 2023 Annual Radiological Environmental Operating Report (PLA-8095) PLA-8094, Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-80942024-04-22022 April 2024 Radioactive Effluent Release Report and Offsite Dose Calculation Manual PLA-8094 PLA-8113, Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113)2024-04-11011 April 2024 Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113) PLA-8102, Annual Environmental Operating Report (Nonradiological) PLA-81022024-04-11011 April 2024 Annual Environmental Operating Report (Nonradiological) PLA-8102 PLA-8112, Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-81122024-04-0909 April 2024 Relief Request 4RR-11 Relief from End of Interval Boundary Leakage Test PLA-8112 PLA-8110, Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110)2024-04-0404 April 2024 Submittal of Unit 1 Cycle 24 Core Operating License Report (Pla 8110) PLA-8100, Property Insurance Program (PLA-8100)2024-04-0101 April 2024 Property Insurance Program (PLA-8100) PLA-8109, Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109)2024-03-21021 March 2024 Supplement to Request for Exemption from Certain Requirements of 10 CR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance (PLA-8109) PLA-8107, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance2024-03-19019 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 Resulting from Fuel Basket Design Control Compliance PLA-8099, Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099)2024-02-13013 February 2024 Proof of Financial Protection and Guarantee of Payment of Deferred Premiums (PLA-8099) PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8077, Emergency Plan Revision 67 (PLA-8077)2023-12-27027 December 2023 Emergency Plan Revision 67 (PLA-8077) PLA-8088, Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation (PLA-8088)2023-12-0505 December 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks and Security Event Notifications Implementation (PLA-8088) PLA-8089, Submittal of Revision to Inservice Testing Program Plan2023-12-0505 December 2023 Submittal of Revision to Inservice Testing Program Plan PLA-8084, Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.22023-11-29029 November 2023 Application to Revise Technical Specifications to Adopt TSTF-568, Revise Applicability of BWR TS 3.6.2.5 and TS 3.6.3.2 PLA-8091, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091)2023-11-0808 November 2023 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091) PLA-8082, Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program2023-11-0202 November 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Application to Revise Technical Specifications to Adopt TSTF-563, Revise Instrument Testing Definitions to Incorporate the Surveillance Frequency Control Program PLA-8080, Proposed Relief for Valve 251130 (PLA-8080)2023-08-14014 August 2023 Proposed Relief for Valve 251130 (PLA-8080) PLA-8074, Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2023-08-0303 August 2023 Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8076, Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076)2023-07-20020 July 2023 Unit 2 - 21st Refueling Outage Owner'S Activity Report (PLA-8076) PLA-8078, Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-80782023-07-0505 July 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report, Revision 1, PLA-8078 PLA-8054, Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence2023-06-0808 June 2023 Proposed Amendment to Licenses NPF-14 and NPF-22: Remove Control Rod Operability Separation Criteria and Replace Reference to Banked Position Withdrawal Sequence with the Analyzed Rod Position Sequence PLA-8073, Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval2023-06-0101 June 2023 Proposed Relief Request for the Fifth 10-Year Inservice Inspection Interval PLA-8067, Notification of Completion of Emergence from Bankruptcy (PLA-8067)2023-05-17017 May 2023 Notification of Completion of Emergence from Bankruptcy (PLA-8067) PLA-8064, Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064)2023-05-17017 May 2023 Response to NRC Regulatory Issue Summary 2023-01 (PLA-8064) PLA-8066, Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-80662023-05-0808 May 2023 Notification of Planned Closing Date and Information Identified in March 30, 2023 Order, PLA-8066 PLA-8053, Radiation Exposure Information and Reporting System2023-04-27027 April 2023 Radiation Exposure Information and Reporting System PLA-8058, Annual Radiological Environmental Operating Report (PLA-8058)2023-04-26026 April 2023 Annual Radiological Environmental Operating Report (PLA-8058) PLA-8041, Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041)2023-04-25025 April 2023 Radioactive Effluent Release Report and Offsite Dose Calculation Manual (PLA-8041) PLA-8047, 2022 Annual Environmental Operating Report (Nonradiological), PLA-80472023-04-19019 April 2023 2022 Annual Environmental Operating Report (Nonradiological), PLA-8047 PLA-8062, Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-80622023-04-11011 April 2023 Supplement to Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 252F007B, PLA-8062 PLA-8061, Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-80612023-04-10010 April 2023 Relief Request 4RR-10 Relief from Code Seal Weld Requirement for Valve 25F007B, PLA-8061 PLA-8060, Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060)2023-03-30030 March 2023 Submittal of Unit 2 Cycle 22 Core Operating Limits Report (PLA-8060) PLA-8057, Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-80572023-03-15015 March 2023 Application for Order Approving Indirect Transfer of Control of Licenses and Approving Conforming License Amendments- Supplemental Information, PLA-8057 PLA-8052, (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums2023-02-13013 February 2023 (Sses), Proof of Financial Protection and Guarantee of Payment of Deferred Premiums PLA-8048, Response to Request for Additional Information Regarding License Amendment Requesting Temporary Addition of Analyzed Rod Position Sequence2023-01-14014 January 2023 Response to Request for Additional Information Regarding License Amendment Requesting Temporary Addition of Analyzed Rod Position Sequence PLA-8042, Proposed Emergency Amendment to License NPF-22: Temporary Addition of Analyzed Rod Position Sequence2023-01-10010 January 2023 Proposed Emergency Amendment to License NPF-22: Temporary Addition of Analyzed Rod Position Sequence PLA-8039, Application for Order Approving Indirect Transfer of Control of License Amendments - Supplemental Information2022-12-22022 December 2022 Application for Order Approving Indirect Transfer of Control of License Amendments - Supplemental Information PLA-8038, Notification of Petition for Bankruptcy (PLA-8038)2022-12-14014 December 2022 Notification of Petition for Bankruptcy (PLA-8038) PLA-8036, Registration for the Use of Spent Fuel Storage Casks 203, 202, and 204, PLA-80362022-11-30030 November 2022 Registration for the Use of Spent Fuel Storage Casks 203, 202, and 204, PLA-8036 PLA-8035, Registration for the Use of Spent Fuel Storage Casks 205, 200, and 201, PLA-80352022-11-0808 November 2022 Registration for the Use of Spent Fuel Storage Casks 205, 200, and 201, PLA-8035 2024-09-18
[Table view] Category:Response to Request for Additional Information (RAI)
MONTHYEARPLA-8141, Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-81412024-09-18018 September 2024 Response to Request for Additional Information Regarding Relief Request 1RR06, PLA-8141 PLA-8113, Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113)2024-04-11011 April 2024 Response to Request for Additional Information Regarding Relief Request 4RR-11 (PLA-8113) PLA-8096, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval2024-01-0404 January 2024 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inservice Test Program Interval PLA-8091, Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091)2023-11-0808 November 2023 Response to Request for Additional Information Regarding Proposed Relief Request for the Fifth 10-Year Inseervice Inspection Interval (PLA-8091) PLA-8048, Response to Request for Additional Information Regarding License Amendment Requesting Temporary Addition of Analyzed Rod Position Sequence2023-01-14014 January 2023 Response to Request for Additional Information Regarding License Amendment Requesting Temporary Addition of Analyzed Rod Position Sequence PLA-8013, Response to Request for Additional Information Regarding License Amendment Requesting Adoption of TSTF-505, Revision 2 PLA-80132022-06-27027 June 2022 Response to Request for Additional Information Regarding License Amendment Requesting Adoption of TSTF-505, Revision 2 PLA-8013 PLA-8005, Response to Request for Additional Information Regarding License Amendment to Revise Reactor Steam Dome Pressure - Low Instrumentation Function Allowable Value (PLA-8005)2022-05-23023 May 2022 Response to Request for Additional Information Regarding License Amendment to Revise Reactor Steam Dome Pressure - Low Instrumentation Function Allowable Value (PLA-8005) PLA-7984, Supplement to License Amendment Requesting Adoption of TSTF-505, Revision 22022-03-0808 March 2022 Supplement to License Amendment Requesting Adoption of TSTF-505, Revision 2 PLA-7865, Response to Request for Additional Information Regarding Proposed License Amendment Requesting Revision to the Dose Consequence Analysis for a Loss of Coolant Accident (PLA-7865) Loss of Coolant Accident2020-06-0202 June 2020 Response to Request for Additional Information Regarding Proposed License Amendment Requesting Revision to the Dose Consequence Analysis for a Loss of Coolant Accident (PLA-7865) Loss of Coolant Accident PLA-7853, Ninety-Day Response to Request for Additional Information Regarding Proposed License Amendment Requesting Application of Advanced Framatome Methodologies PLA-78532020-04-0101 April 2020 Ninety-Day Response to Request for Additional Information Regarding Proposed License Amendment Requesting Application of Advanced Framatome Methodologies PLA-7853 PLA-7841, Thirty-Day Response to Request for Additional Information Regarding Proposed License Amendment Requesting Application of Advanced Framatome Methodologies2020-02-0606 February 2020 Thirty-Day Response to Request for Additional Information Regarding Proposed License Amendment Requesting Application of Advanced Framatome Methodologies PLA-7830, Response to Second Request for Additional Information Regarding Proposed License Amendment Requesting a Temporary Change to the Technical Specifications to Allow Replacement of Emergency Service Water System Piping2019-12-0909 December 2019 Response to Second Request for Additional Information Regarding Proposed License Amendment Requesting a Temporary Change to the Technical Specifications to Allow Replacement of Emergency Service Water System Piping PLA-7793, Response to Request for Additional Information Regarding Proposed License Amendment Requesting a Temporary Change to the Technical Specifications to Allow Replacement of Emergency Service Water System Piping2019-06-0303 June 2019 Response to Request for Additional Information Regarding Proposed License Amendment Requesting a Temporary Change to the Technical Specifications to Allow Replacement of Emergency Service Water System Piping PLA-7704, Response to Generic Letter 2016-01, Request for Supplemental Information2018-05-24024 May 2018 Response to Generic Letter 2016-01, Request for Supplemental Information PLA-7701, Response to NRC Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examination.2018-04-11011 April 2018 Response to NRC Issue Summary 2018-02, Preparation and Scheduling of Operator Licensing Examination. PLA-7673, Proposed Amendment to Licenses NPF-14 and NPF-22: Response to Request for Additional Information and Supplement to Application to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control PLA-76732018-02-16016 February 2018 Proposed Amendment to Licenses NPF-14 and NPF-22: Response to Request for Additional Information and Supplement to Application to Adopt TSTF-542, Reactor Pressure Vessel Water Inventory Control PLA-7673 PLA-7655, Response to Request for Additional Information, (CAC Nos. MF9131 and MF9132) PLA-76552017-12-0404 December 2017 Response to Request for Additional Information, (CAC Nos. MF9131 and MF9132) PLA-7655 PLA-7619, Response to Request for Additional Information Regarding License Amendment Request to Revise Diesel Generator Surveillance Requirements with New Steady State Voltage and Frequency Limits2017-08-0404 August 2017 Response to Request for Additional Information Regarding License Amendment Request to Revise Diesel Generator Surveillance Requirements with New Steady State Voltage and Frequency Limits PLA-7583, Response to NRC Request for Supplemental Information for License Amendment Request to Revise Diesel Generator Surveillance Requirements with New Steady State Voltage and Frequency Limits (PLA-7583)2017-03-21021 March 2017 Response to NRC Request for Supplemental Information for License Amendment Request to Revise Diesel Generator Surveillance Requirements with New Steady State Voltage and Frequency Limits (PLA-7583) PLA-7518, Response to Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools.2016-10-31031 October 2016 Response to Generic Letter 2016-01, Monitoring of Neutron-Absorbing Materials in Spent Fuel Pools. PLA-7537, Response to Request for Additional Information License Amendment Request Extending Completion Times in Support of 480V Ess Load Center Transformer Replacements2016-10-10010 October 2016 Response to Request for Additional Information License Amendment Request Extending Completion Times in Support of 480V Ess Load Center Transformer Replacements ML16097A4872016-04-0606 April 2016 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request for Temporary Change of Technical Specifications 3.7.1 and 3.8.7, Applicable Drawings PLA-7418, Response to Request for Additional Information for the Third Interval Relief Requests 3RR-19, 3RR-20 and 3RR-212015-12-10010 December 2015 Response to Request for Additional Information for the Third Interval Relief Requests 3RR-19, 3RR-20 and 3RR-21 PLA-7406, Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-4252015-11-11011 November 2015 Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425 ML15296A0602015-10-16016 October 2015 Enclosure 3, Revised (Clean) Copy of the SSES EAL Basis Document Which Includes the Changes Made in Enclosure 2 ML15296A0592015-10-16016 October 2015 Enclosure 1, Response to NRC Request for Additional Information Regarding License Amendment Request to Adopt Nuclear Energy Institute 99-0 1, Revision 6 and Enclosure 2, Mark-up of the Changes Made to the SSES EAL Basis.. ML15296A0532015-10-15015 October 2015 Enclosure 4 to PLA-7399 Revised (Clean) Copy of the SSES EAL Basis Document ML15296A0522015-10-15015 October 2015 Attachments 1 Through 9 - EP-RM-004 to Enclosure 3 to PLA-7399 Mark-up of Proposed Additional Changes Made to the SSES EAL Basis Document ML15296A0502015-10-15015 October 2015 Enclosures 1 and 2 to PLA-7399 - List of Proposed Additional Changes to the Susquehanna Steam Electric Station Emergency Action Level Basis Document and Mark-up of Proposed Additional Changes Made to the SSES EAL Comparison Matrix (Revision PLA-7399, Proposed Additional Changes to the SSES Emergency Plan Basis Document Since Submittal of Response to NRC Request for Additional Information PLA-73992015-10-15015 October 2015 Proposed Additional Changes to the SSES Emergency Plan Basis Document Since Submittal of Response to NRC Request for Additional Information PLA-7399 PLA-7389, Flood Hazards Reevaluation Report, Information to Support Audit2015-09-24024 September 2015 Flood Hazards Reevaluation Report, Information to Support Audit PLA-7381, Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-4252015-09-21021 September 2015 Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425 PLA-7371, Response to Request for Supplemental Information for the Third Interval Relief Requests 3RR-19, 3RR-20, and 3RR-212015-08-0606 August 2015 Response to Request for Supplemental Information for the Third Interval Relief Requests 3RR-19, 3RR-20, and 3RR-21 PLA-7334, Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-4252015-07-0202 July 2015 Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425 ML18024A1091978-09-0808 September 1978 Letter Attaching a Schedule for Responses to NRC Question List of June 5, 1978 ML18026A1161978-08-31031 August 1978 Letter Responding to the Letter of May 17, 1978 Enclosing Information for Antitrust Review of Operating License. ML18025A5151978-08-31031 August 1978 Letter Regarding Information for Antitrust Review of Operating License Application ML18024A0921978-04-14014 April 1978 Letter Responding to the Commission Request for Additional Information with a Schedule for Response on Containment ML18024A0891978-03-31031 March 1978 Letter Replying to the Questionnaire Contained in the December 6, 1977 Letter and Attaching an Updated Response for Unit 1 and a Complete Response for Unit 2 ML18024A0851978-03-0707 March 1978 Letter Regarding the Commission Letter of February 15, 1978 Containing the Staff Position on the Use of Austenitic Stainless Steel and Advising That PP&L Will Provide a Response by September 1, 1978 ML18025A2481977-06-14014 June 1977 Letter Submitting Additional Information Relative to the Commission'S Previous Request to Establish a Cold Weather Concrete Freeze-Protection Period of Three Days ML18025A2611977-01-19019 January 1977 Letter Documenting Responses to Questions Given to Mr. Singh Bawa of the NRC from Pp&L'S Mr. E.D. Testa in Telephone Conversations on 1/17/1977 and 01/18/1977 ML18025A2641976-12-30030 December 1976 Letter Responding to Letters Requesting That Certain Information Be Submitted to Address Anticipated Transients Without Scram (ATWS) for SSES Including Analysis and Justification of the GE Analysis Model ... ML18023A9051976-11-18018 November 1976 Response to Four Questions on the Susquehanna-Siegfried 500 Kv Line ML18023B4951976-11-18018 November 1976 Letter Responding the November 3, 1976 Letter with Answer to Four Questions on the Susquehanna-Siegfried 500 Kv Line as Indicated in Amendment 5 and Attaching PA Dept. of Environmental Resources Approval for the Crossing ... ML18025A4871976-10-15015 October 1976 Responses to Questions with Attached Drawings and Maps ML18023B4961976-10-15015 October 1976 Letter Responding to the October 6, 1976 Letter Requesting Additional Information on SSES Transmission Lines ML18025A2741976-09-0909 September 1976 Letter Responding to the Commission Letter of August 9, 1976 Relating to Annulus Pressurization and Cracks in the Feedwater Nozzle Blend Radii ML18025A4951975-06-0505 June 1975 Letter Responding to the April 17, 1975 Letter Requesting Additional Information Relative to the Design of the Containment for SSES and Attaching the Mark II Containment Program and Schedule ML18023A7651975-05-13013 May 1975 Letter Responding to NRC Letters Dated February 18, 1975 and March 14, 1975 Containing NRC Staff Positions 2024-09-18
[Table view] |
Text
Edward Casulli Susquehanna Nuclear, LLC Site Vice President 769 Salem Boulevard Berwick, PA 18603 TALEN~
Tel. 570.542.3795 Fax 570.542.1504 Edward.Casulli@TalenEnergy.com ENERGY
April 11, 2024
Attn: Document Control Desk 10 CFR 50.55a U. S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUSQUEHANNA STEAM ELECTRIC STATION RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION REGARDING RELIEF REQUEST 4RR-11 PLA-8113 Docket No. 50-387
References:
- 1) Susquehanna letter to NRC, "Relief Request 4RR-11 Relief Request from End of Interval Boundary Leakage Test (PLA-8112)," dated April 09, 2024 (ADAMS Accession No. ML24100A832).
- 2) NRC email to Susquehanna, "Request for Additional Information for Susquehanna Unit 1 Alternative Request 4RR-ll," dated April 10, 2024.
In accordance with 10 CFR 50.55a(z), Susquehanna Nuclear, LLC (Susquehanna), in Reference 1, requested NRC approval of relief request 4RR-l 1 associated with the fourth and fifth 10-year Inservice Inspection intervals for the Susquehanna Steam Electric Station, Unit 1.
Relief request 4RR-11 requested authorization of alternative requirements for the American Society of Mechanical Engineers Boiler and Pressure Vessel Code,Section XI, IWB-5222(b) pressure boundary test for the volume between the inboard (IB) and outboard (OB) main steam isolation valves (MSIVs) on the 'D' main steam line (MSL). This request would defer the pressure test between the IB and OB MSIVs on the 'D' MSL until the next Unit 1 refuel and inspection outage (projected for spring 2026).
The NRC provided a Request for Additional Information (RAI) in Reference 2. The enclosure provides Susquehanna's response to the RAI.
Susquehanna requests authorization of the proposed alternative by April 12, 2024.
There are no new or revised regulatory commitments contained in this submittal.
- 2 - Document Control Desk PLA-8113
Should you have any questions regarding this submittal, please contact Ms. Melisa Krick, Manager-Nuclear Regulatory Affairs, at (570) 542-1818.
E. Casulli
Enclosure:
Response to Request for Additional Information
Copy: NRC Region I Ms. J. England, NRC Senior Resident Inspector Ms. A. Klett, NRC Project Manager Mr. M. Shields, PA DEP/BRP Enclosure to PLA-8 113
Response to Request for Additional Information
Enclosure to PLA-8113 Page 1 of 3
Response to Request for Additional Information
On April 09, 2024, Susquehanna Nuclear, LLC (Susquehanna), submitted a relief request, 4RR-11, associated with the Class 1 boundary leakage test required by American Society of Mechanical Engineers (ASME) Boiler and Pressure Vessel Code (Code),Section XI, IWB-5222(b). Specifically, 4RR-11 requested authorization of alternative requirements for the IWB-5222(b) pressure boundary test for the volume between the inboard (IB) and outboard (OB) main steam isolation valves (MSIVs) on the D main steam line (MSL). This request would defer the pressure test between the IB and OB MSIVs on the D MSL until the next Unit 1 refuel and inspection outage (RIO) (projected for spring 2026). Subsequently, the NRC provided a Request for Additional Information (RAI) in Reference 2. The response to this RAI is provided below.
RAI-1
Section 3, Applicable Code Requirement, of [Reference 1] states, ASME Code,Section XI, Section XI, IWB-5222(b) requires the system leakage test pressure retaining boundary to extend to all Class 1 components. However, the alternative is taking exception to the specific ASME Code requirement that system leakage test be performed at or near the end of the interval per IWB-5222(b). Therefore, the staff requests the licensee to discuss the specific requirement to which the alternative is taking exception, in this section of the submittal.
Susquehanna Response
Section 3 below replaces Section 3 of Reference 1 in its entirety. This replacement does not alter the remaining content of Reference 1.
- 3. Applicable Code Requirement
The ASME Code,Section XI, IWB-5222(b) requires the system leakage test pressure retaining boundary to extend to all Class 1 components within the system boundary.
Specifically, IWB-5222(b) states,
The Class 1 pressure retaining boundary which is not pressurized when the system valves are in the position required for normal reactor startup shall be pressurized and examined at or near the end of the inspection interval. This boundary may be tested in its entirety or in portions and testing may be performed during the testing of the boundary of IWB-5222(a).
The ASME Code,Section XI, Table IWB-2500 -1, Item No. B15.20 requires that pressure retaining components subject to IWB-5222(b) must be tested once per interval, at or near the Enclosure to PLA-8113 Page 2 of 3
end of the interval. As shown in Reference 1, Table 5.1, Susquehanna did test the subject piping between the IB and OB MSIV of the D MSL multiple times during the fourth 10-year Inservice Inspection interval, most recently in April 2020. However, none of these tests are considered at or near the end of the interval. Therefore, Susquehanna is requesting to take exception to the at or near the end of the interval scheduling requirement of ASME Code,Section XI, IWB-5222(b) and Table IWB-2500 -1 for the subject piping between the IB and OB MSIV of the D MSL.
RAI-2
Section 5 of [Reference 1], states:
... the proposed alternative is to perform a partial IWB-5222(b) pressure boundary test during the 2024 RIO, including all piping applicable to the IWB-5222(b) pressure boundary and the Main Steam system MSL D to the IB MSIV, subsequently test the remainder of the boundary (all piping applicable to the IWB-5222(a) pressure boundary and the Main Steam system MSL D to the OB MSIV) during the next Unit 1 RIO (projected for spring 2026).
Confirm that the above means the following:
The IWB-5222(b) pressure boundary inspection performed during the 2024 RIO will include all required piping systems, including the Main Steam System, except for Main Steam system MSL D IB [MSIV] to OB [MSIV]. The Main Steam system MSL D IB [MSIV] to OB [MSIV]
will be deferred this RIO and be performed during the next RIO (projected for spring 2026) during the IWB-5222(a) pressure boundary inspection. Hence, all the inspections required under IWB-5222 will be completed at least once during the 2024 and/or 2026 RIO.
Susquehanna Response
Yes, Susquehanna concurs that the provided statement aligns with the intent of Reference 1, Section 5.
RAI-3
[Reference 1] states that when these tests are considered in the aggregate, the entire Class 1 pressure boundary is shown to be pressure tested to requirements of IWB-5222(b) within the fourth 10-year ISI interval. The NRC staff notes that the alternative is only asking an exception to the requirement that the testing was not performed at or near the end of the interval (2014-2024). Testing was performed during this interval in 2016, 2018 and 2020, but the timing of these inspections was not at the end of the interval (2024). To meet the intent of the ASME Code of ensuring the inspection interval does not exceed 10 years, the alternative is proposing to Enclosure to PLA-8113 Page 3 of 3
perform the deferred inspection in 2026, thereby making the time between inspections less than 10 years. Based on the understanding above, confirm whether the licensee would conclude that the information provided in the proposed alternative, including the previous inspections performed, would justify that the proposed alternative provides for an acceptable level of quality and safety as set forth in 10 CFR 50.55a(z)(1).
Susquehanna Response
Yes, Susquehanna agrees that the information provided in Reference 1 would justify that the proposed alternative provides for an acceptable level of quality and safety as set forth in 10 CFR 50.55a(z)(1).
Note, Susquehanna continues to request authorization of the proposed alternative by April 12, 2024.
References
- 1. Susquehanna letter to NRC, Relief Request 4RR-11 Relief Request from End of Interval Boundary Leakage Test (PLA-8112), dated April 09, 2024 (ADAMS Accession No. ML24100A832).
- 2. NRC email to Susquehanna, Request for Additional Information for Susquehanna Unit 1 Alternative Request 4RR-11, dated April 10, 2024.