PLA-7406, Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425

From kanterella
(Redirected from PLA-7406)
Jump to navigation Jump to search
Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425
ML15315A045
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 11/11/2015
From: Franke J
Susquehanna, Talen Energy
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
PLA-7406
Download: ML15315A045 (6)


Text

NOV 1 1 2015 Jon A. Franke Site Vice President U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Susquehanna Nuclear, LLC 769 Salem Boulevard Berwick, PA 18603 Tel. 570.542.2904 Fax 570.542.1504 jon.franke@talenenergy.com SUSQUEHANNA STEAM ELECTRIC STATION RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ON TECHNICAL SPECIFICATION CHANGES TO ADOPT TRAVELER TSTF-425 PLA-7406 TALEN ~

ENERGY Docket Nos. 50-387 and 50-388

References:

1.

Letter PLA-7119, [Proposed Amendments to License NPF-14 and NPF-22] Adoption ofTechnical Specification TaskForce Traveler TSTF-425, Revision 3, "Relocate Surveillance Frequencies to Licensee Control-Risk Informed Technical Task Force (RITSTF) Initiative 5, "dated October 27, 2014 (AccessionML14317A052).

2.

Letter PLA-7334, "Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425, "dated July 2, 2015 (Accession ML15183A248).

3. Letter PLA-7381, "Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425, "dated September 21, 2015 (Accession ML15265A347).
4.

NRC Summmy of October 21, 2015, Meeting with Susquehanna Nuclear, LLC on the TSTF-425 License Amendment Request, dated October 29, 2015, (TAC Nos. MF5151 and MF5152), (Accession ML15295A202).

The purpose of this letter is for Susquehanna Nuclear, LLC to provide the requested additional information (RAI). By Reference 1, and as supplemented by additional information in References 2 and 3, Susquehanna Nuclear, LLC submitted a license amendment request (LAR) to modify Susquehanna Steam Electric Station, Units 1 and 2 (SSES) Technical Specifications (TS) by relocating specific surveillance frequencies to a licensee-controlled program. The program will implement Nuclear Energy Institute (NEI) 04-10, "Risk-Informed Technical Specifications Initiative 5B, Risk-Informed Method for Control of Surveillance Frequencies," (Accession ML071360456). The changes adopt an NRC approved Technical Specification Task Force (TSTF) traveler, TSTF-425, Revision 3, (Accession ML080280275).

The NRC RAI is in the October 21 Public Meeting Summary, dated October 29, 2015, (Reference 4). Attachment 1 re-states both the issue and the RAI 10, and provides the SSES response.

Document Control Desk PLA-7406 Susquehanna Nuclear, LLC has reviewed the information supporting a finding of no significant hazards consideration and the environmental consideration provided to the NRC in Reference 1. The additional information provided by this submittal does not affect the bases for concluding that the proposed license amendment does not involve a significant hazards consideration. Furthermore, the additional information also does not affect the bases for concluding that neither an environmental impact statement nor an environmental assessment needs to be prepared in connection with the proposed amendment.

There are no new regulatory commitments associated with this response.

If you have any questions or require additional information, please contact Mr. JefferyN. Grisewood (570) 542-1330.

I declare under penalty of perjury that the foregoing is true and conect.

Executed on:

J. /

  • anke : Response to Requested Additional Information Copy:

NRC Region I Mr. J. E. Greives, NRC Sr. Resident Inspector Mr. J. A. Whited, NRC Project Manager Mr. T. E. Hood, NRC Project Manager Mr. M. Shields, P A DEP/BRP to PLA-7406 Response to Requested Additional Information to PLA-7406 Page 1 of3 Response to Requested Additional Information By letter dated October 27, 2014,<1) and as supplemented by additional information in a letter dated July 2, 2015(2) and September 21, 2015,<3) Susquehanna Nuclear, LLC submitted a license amendment request (LAR) for the Susquehanna Steam Electric Station (SSES), Units 1 and 2. The proposed amendment would modify the SSES Technical Specifications by relocating specific frequencies to a licensee-controlled program with the implementation of Nuclear Energy Institute (NEI) 04-10, "Risk-Informed Technical Specifications Initiative 5b, Risk-Informed Method for Control of Surveillance Frequencies. "(4) The NRC requested additional information (RAI) is in the October 21 Public Meeting Summary, dated October 29, 2015.<5) This Attachment re-states both the issue and the RAI 10 below, and provides the SSES response.

ISSUE

[Supporting Requirement] SR HR-A3 describes a mechanism or process and clarifies it by the examples. The examples are not exhaustive. Common cause failure events may occur due to either single or multiple activities. An example of pre-initiator multiple actions which could result in a common failure is the use of an incorrect procedure, which may be used at different times. Therefore, pre-initiator multiple activity human failure events which could be a common mode failure, whether or not the activities occur in an outage, cannot be screened out considering SR HR-A3. This may be relevant to equipment which follows staggered testing.

RAJ 10:

Based on the above, address how you will consider the potential for multiple actions which could be a common mode failure (such as the use of a procedure) consistent with SR HR-A3, for the probabilistic risk assessment (PRA) model.

(1)

Letter (PLA-7119), [Proposed Amendments to License NPF-14 and NPF-22] Adoption of Technical Specification Task Force Traveler TSTF-425, Revision 3, "Relocate Surveillance Frequencies to Licensee Control-Risk Informed Technical Specification Task Force (RITSTF)

Initiative 5, " dated October 27, 2014 (Accession :ML14317A052).

(2)

Letter (PLA-7334), "Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425, "dated July 2, 2015 (Accession :ML15183A248).

(3)

Letter (PLA-7381), "Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425," dated September 21,2015 (Accession :ML15265A347).

(4)

Nuclear Energy Institute (NEI) 04-10, Revision 1, "Risk-Informed Technical Specifications Initiative 5B, Risk-Informed Method for Control of Surveillance Frequencies," dated April30, 2007 (Accession :ML071360456).

(5)

NRC Summary of October 21,2015, Meeting with Susquehanna Nuclear LLC on the TSTF-425 License Amendment Request, dated October 29,2015 (TAC Nos. MF5151 and MF5152),

(Accession :ML15295A202).

SSES Response to RAJ 10: to PLA-7406 Page 2 of3 Consistent with SR HR-A3, the Human Reliability Analysis (HRA) pre-initiator development process considers the potential for multiple actions which could be a common mode failure (such as the use of a procedure).

The Susquehanna HRA pre-initiator process includes the following attributes to identify possible pre-initiator actions where redundant or multiple diverse equipment can be affected by a single action or through a common failure with similar multiple actions:

  • Perform a component/system review. System trains explicitly modeled in the PRA are potential candidates for pre-initiator (Human Error Probabilities) HEPs.

For example, instruments/logic used for initiation and control of PRA components are considered for event generation, including multiple, separate instruments in different divisions that could be failed by a common cause.

  • Review station procedures to identify potential pre-initiator events.
  • Review operating experience to identify potential pre-initiator events.

Work practices, including procedures, that simultaneously affect equipment in different trains of a redundant system have been included in the development of Susquehanna HRA pre-initiator basic events. Any mechanism that simultaneously affects multiple equipment in either different trains of a redundant system or diverse system is not screened. Specifically, staggered testing is not used to screen common mode failures.

This practice aligns with NUREG-1792/6) Sections 4.1.3.4, "Good Practice #4: Identify Actions Affecting Redundant and Multiple Diverse Equipment, " and 4.2.3.2, "Good Practice #2: Do Not Screen Actions Affecting Redundant or Multiple Diverse Equipment. "

As a result of this process, the Susquehanna PRA HRA pre-initiators include cross-train and cross-division common cause pre-initiators. For example, common cause pre-initiators were developed for drywell pressure switches, Reactor Pressure Vessel (RPV) pressure switches, and reactor level switches. Examples of these common cause pre-initiator basic events included in the Susquehanna PRA model are:

BASIC EVENT BASIC EVENT DESCRIPTION TRAINS/DIVISIONS 151PSE111N011 CCF MISCALIBRA TION OF DW PRESSURE Trains A and B AB-H SWITCHES PSElllNOllA/B Divisions I and II 151PSE111N011 CCF MISCALIBRATION OF DW PRESSURE Trains A and D AD-H SWITCHES PSElllNOllA/D Divisions I and II

( 6) NUREG-1792, "Good Practices for Implementing Human Reliability Analysis (HRA), "Final Report, April2005.

BASIC EVENT 151PSE111N011 BC-H 151PSE111N011 CD-H 180-B211N021 AB-H 180-B211N021 AD-H 180-B211N021 BC-H 180-B211N021 CD-H 180-B211N031 AB-H 180-B211N031 AD-H 180-B211N031 BC-H 180-B211N031 CD-H 180-B211N042 AB-H 183-PSE111N010 AB-H 183-PSE111N010 AD-H 183-PSE111N010 BC-H 183-PSE111N010 CD-H BASIC EVENT DESCRIPTION CCF MISCALIBRA TION OF DW PRESSURE SWITCHES PSE111N011B/C CCF MISCALIBRATION OF DW PRESSURE SWITCHES PSE111N011C/D CCF MISCALIBRATION OF RPV PRESSURE SWITCHES PISB211N021A/B CCF MISCALIBRATION OF RPV PRESSURE SWITCHES PISB211N021A/D CCF MISCALIBRATION OF RPV PRESSURE SWITCHES PISB211 N021 B/C CCF MISCALIBRATION OF RPV PRESSURE SWITCHES PISB211N021C/D COMMON MISCALIBRATION OF RX LVL SWITCHES LISB211 N031 AlB COMMON MISCALIBRA TION OF RX LVL SWITCHES LISB211N031A/D COMMON MISCALIBRA TION OF RX LVL SWITCHES LISB211N031B/C COMMON MISCALIBRATION OF RX LVL SWITCHES LISB211 N031 C/D COMMON MISCALIBRA TION OF RX LVL SWITCHES LISB211N042A/B (ADS divisional permissive)

COMMON MISCAL OF DRYWELL PRS SWITCHES PSE111N010A/B COMMON MISCAL OF DRYWELL PRS SWITCHES PSE 111 NO 1 OA/D COMMON MISCAL OF DRYWELL PRS SWITCHES PSE111N010B/C COMMON MISCAL OF DRYWELL PRS SWITCHES PSE111N010C/D to PLA-7406 Page 3 of3 TRAINS/DNISIONS Trains B and C Divisions I and II Trains C and D Divisions I and II Trains A and B Divisions I and II Trains A and D Divisions I and II Trains B and C Divisions I and II Trains C and D Divisions I and II Trains A and B Divisions I and II Trains A and D Divisions I and II Trains B and C Divisions I and II Trains C and D Divisions I and II Divisions I and II Trains A and B Divisions I and II Trains A and D Divisions I and II Trains B and C Divisions I and II Trains C and D Divisions I and II Therefore, work practices, including procedures, that simultaneously affect equipment in different trains of a redundant system have been included in the development of Susquehanna HRA pre-initiator common cause basic events.

NOV 1 1 2015 Jon A. Franke Site Vice President U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Susquehanna Nuclear, LLC 769 Salem Boulevard Berwick, PA 18603 Tel. 570.542.2904 Fax 570.542.1504 jon.franke@talenenergy.com SUSQUEHANNA STEAM ELECTRIC STATION RESPONSE TO REQUEST FOR ADDITIONAL INFORMATION ON TECHNICAL SPECIFICATION CHANGES TO ADOPT TRAVELER TSTF-425 PLA-7406 TALEN ~

ENERGY Docket Nos. 50-387 and 50-388

References:

1.

Letter PLA-7119, [Proposed Amendments to License NPF-14 and NPF-22] Adoption ofTechnical Specification TaskForce Traveler TSTF-425, Revision 3, "Relocate Surveillance Frequencies to Licensee Control-Risk Informed Technical Task Force (RITSTF) Initiative 5, "dated October 27, 2014 (AccessionML14317A052).

2.

Letter PLA-7334, "Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425, "dated July 2, 2015 (Accession ML15183A248).

3. Letter PLA-7381, "Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425, "dated September 21, 2015 (Accession ML15265A347).
4.

NRC Summmy of October 21, 2015, Meeting with Susquehanna Nuclear, LLC on the TSTF-425 License Amendment Request, dated October 29, 2015, (TAC Nos. MF5151 and MF5152), (Accession ML15295A202).

The purpose of this letter is for Susquehanna Nuclear, LLC to provide the requested additional information (RAI). By Reference 1, and as supplemented by additional information in References 2 and 3, Susquehanna Nuclear, LLC submitted a license amendment request (LAR) to modify Susquehanna Steam Electric Station, Units 1 and 2 (SSES) Technical Specifications (TS) by relocating specific surveillance frequencies to a licensee-controlled program. The program will implement Nuclear Energy Institute (NEI) 04-10, "Risk-Informed Technical Specifications Initiative 5B, Risk-Informed Method for Control of Surveillance Frequencies," (Accession ML071360456). The changes adopt an NRC approved Technical Specification Task Force (TSTF) traveler, TSTF-425, Revision 3, (Accession ML080280275).

The NRC RAI is in the October 21 Public Meeting Summary, dated October 29, 2015, (Reference 4). Attachment 1 re-states both the issue and the RAI 10, and provides the SSES response.

Document Control Desk PLA-7406 Susquehanna Nuclear, LLC has reviewed the information supporting a finding of no significant hazards consideration and the environmental consideration provided to the NRC in Reference 1. The additional information provided by this submittal does not affect the bases for concluding that the proposed license amendment does not involve a significant hazards consideration. Furthermore, the additional information also does not affect the bases for concluding that neither an environmental impact statement nor an environmental assessment needs to be prepared in connection with the proposed amendment.

There are no new regulatory commitments associated with this response.

If you have any questions or require additional information, please contact Mr. JefferyN. Grisewood (570) 542-1330.

I declare under penalty of perjury that the foregoing is true and conect.

Executed on:

J. /

  • anke : Response to Requested Additional Information Copy:

NRC Region I Mr. J. E. Greives, NRC Sr. Resident Inspector Mr. J. A. Whited, NRC Project Manager Mr. T. E. Hood, NRC Project Manager Mr. M. Shields, P A DEP/BRP to PLA-7406 Response to Requested Additional Information to PLA-7406 Page 1 of3 Response to Requested Additional Information By letter dated October 27, 2014,<1) and as supplemented by additional information in a letter dated July 2, 2015(2) and September 21, 2015,<3) Susquehanna Nuclear, LLC submitted a license amendment request (LAR) for the Susquehanna Steam Electric Station (SSES), Units 1 and 2. The proposed amendment would modify the SSES Technical Specifications by relocating specific frequencies to a licensee-controlled program with the implementation of Nuclear Energy Institute (NEI) 04-10, "Risk-Informed Technical Specifications Initiative 5b, Risk-Informed Method for Control of Surveillance Frequencies. "(4) The NRC requested additional information (RAI) is in the October 21 Public Meeting Summary, dated October 29, 2015.<5) This Attachment re-states both the issue and the RAI 10 below, and provides the SSES response.

ISSUE

[Supporting Requirement] SR HR-A3 describes a mechanism or process and clarifies it by the examples. The examples are not exhaustive. Common cause failure events may occur due to either single or multiple activities. An example of pre-initiator multiple actions which could result in a common failure is the use of an incorrect procedure, which may be used at different times. Therefore, pre-initiator multiple activity human failure events which could be a common mode failure, whether or not the activities occur in an outage, cannot be screened out considering SR HR-A3. This may be relevant to equipment which follows staggered testing.

RAJ 10:

Based on the above, address how you will consider the potential for multiple actions which could be a common mode failure (such as the use of a procedure) consistent with SR HR-A3, for the probabilistic risk assessment (PRA) model.

(1)

Letter (PLA-7119), [Proposed Amendments to License NPF-14 and NPF-22] Adoption of Technical Specification Task Force Traveler TSTF-425, Revision 3, "Relocate Surveillance Frequencies to Licensee Control-Risk Informed Technical Specification Task Force (RITSTF)

Initiative 5, " dated October 27, 2014 (Accession :ML14317A052).

(2)

Letter (PLA-7334), "Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425, "dated July 2, 2015 (Accession :ML15183A248).

(3)

Letter (PLA-7381), "Response to Request for Additional Information on Technical Specification Changes to Adopt Traveler TSTF-425," dated September 21,2015 (Accession :ML15265A347).

(4)

Nuclear Energy Institute (NEI) 04-10, Revision 1, "Risk-Informed Technical Specifications Initiative 5B, Risk-Informed Method for Control of Surveillance Frequencies," dated April30, 2007 (Accession :ML071360456).

(5)

NRC Summary of October 21,2015, Meeting with Susquehanna Nuclear LLC on the TSTF-425 License Amendment Request, dated October 29,2015 (TAC Nos. MF5151 and MF5152),

(Accession :ML15295A202).

SSES Response to RAJ 10: to PLA-7406 Page 2 of3 Consistent with SR HR-A3, the Human Reliability Analysis (HRA) pre-initiator development process considers the potential for multiple actions which could be a common mode failure (such as the use of a procedure).

The Susquehanna HRA pre-initiator process includes the following attributes to identify possible pre-initiator actions where redundant or multiple diverse equipment can be affected by a single action or through a common failure with similar multiple actions:

  • Perform a component/system review. System trains explicitly modeled in the PRA are potential candidates for pre-initiator (Human Error Probabilities) HEPs.

For example, instruments/logic used for initiation and control of PRA components are considered for event generation, including multiple, separate instruments in different divisions that could be failed by a common cause.

  • Review station procedures to identify potential pre-initiator events.
  • Review operating experience to identify potential pre-initiator events.

Work practices, including procedures, that simultaneously affect equipment in different trains of a redundant system have been included in the development of Susquehanna HRA pre-initiator basic events. Any mechanism that simultaneously affects multiple equipment in either different trains of a redundant system or diverse system is not screened. Specifically, staggered testing is not used to screen common mode failures.

This practice aligns with NUREG-1792/6) Sections 4.1.3.4, "Good Practice #4: Identify Actions Affecting Redundant and Multiple Diverse Equipment, " and 4.2.3.2, "Good Practice #2: Do Not Screen Actions Affecting Redundant or Multiple Diverse Equipment. "

As a result of this process, the Susquehanna PRA HRA pre-initiators include cross-train and cross-division common cause pre-initiators. For example, common cause pre-initiators were developed for drywell pressure switches, Reactor Pressure Vessel (RPV) pressure switches, and reactor level switches. Examples of these common cause pre-initiator basic events included in the Susquehanna PRA model are:

BASIC EVENT BASIC EVENT DESCRIPTION TRAINS/DIVISIONS 151PSE111N011 CCF MISCALIBRA TION OF DW PRESSURE Trains A and B AB-H SWITCHES PSElllNOllA/B Divisions I and II 151PSE111N011 CCF MISCALIBRATION OF DW PRESSURE Trains A and D AD-H SWITCHES PSElllNOllA/D Divisions I and II

( 6) NUREG-1792, "Good Practices for Implementing Human Reliability Analysis (HRA), "Final Report, April2005.

BASIC EVENT 151PSE111N011 BC-H 151PSE111N011 CD-H 180-B211N021 AB-H 180-B211N021 AD-H 180-B211N021 BC-H 180-B211N021 CD-H 180-B211N031 AB-H 180-B211N031 AD-H 180-B211N031 BC-H 180-B211N031 CD-H 180-B211N042 AB-H 183-PSE111N010 AB-H 183-PSE111N010 AD-H 183-PSE111N010 BC-H 183-PSE111N010 CD-H BASIC EVENT DESCRIPTION CCF MISCALIBRA TION OF DW PRESSURE SWITCHES PSE111N011B/C CCF MISCALIBRATION OF DW PRESSURE SWITCHES PSE111N011C/D CCF MISCALIBRATION OF RPV PRESSURE SWITCHES PISB211N021A/B CCF MISCALIBRATION OF RPV PRESSURE SWITCHES PISB211N021A/D CCF MISCALIBRATION OF RPV PRESSURE SWITCHES PISB211 N021 B/C CCF MISCALIBRATION OF RPV PRESSURE SWITCHES PISB211N021C/D COMMON MISCALIBRATION OF RX LVL SWITCHES LISB211 N031 AlB COMMON MISCALIBRA TION OF RX LVL SWITCHES LISB211N031A/D COMMON MISCALIBRA TION OF RX LVL SWITCHES LISB211N031B/C COMMON MISCALIBRATION OF RX LVL SWITCHES LISB211 N031 C/D COMMON MISCALIBRA TION OF RX LVL SWITCHES LISB211N042A/B (ADS divisional permissive)

COMMON MISCAL OF DRYWELL PRS SWITCHES PSE111N010A/B COMMON MISCAL OF DRYWELL PRS SWITCHES PSE 111 NO 1 OA/D COMMON MISCAL OF DRYWELL PRS SWITCHES PSE111N010B/C COMMON MISCAL OF DRYWELL PRS SWITCHES PSE111N010C/D to PLA-7406 Page 3 of3 TRAINS/DNISIONS Trains B and C Divisions I and II Trains C and D Divisions I and II Trains A and B Divisions I and II Trains A and D Divisions I and II Trains B and C Divisions I and II Trains C and D Divisions I and II Trains A and B Divisions I and II Trains A and D Divisions I and II Trains B and C Divisions I and II Trains C and D Divisions I and II Divisions I and II Trains A and B Divisions I and II Trains A and D Divisions I and II Trains B and C Divisions I and II Trains C and D Divisions I and II Therefore, work practices, including procedures, that simultaneously affect equipment in different trains of a redundant system have been included in the development of Susquehanna HRA pre-initiator common cause basic events.