PLA-2504, Provides Final Response to IE Bulletin 83-03.Insps of Check Valves Planned for Unit 1 Refueling Outages.Initial Valve Insps Determined One Valve to Be Partially Disassembled. Valve Reassembled & Disc Nut Pin Properly Peened

From kanterella
(Redirected from PLA-2504)
Jump to navigation Jump to search
Provides Final Response to IE Bulletin 83-03.Insps of Check Valves Planned for Unit 1 Refueling Outages.Initial Valve Insps Determined One Valve to Be Partially Disassembled. Valve Reassembled & Disc Nut Pin Properly Peened
ML20133D659
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 07/16/1985
From: Keiser H
PENNSYLVANIA POWER & LIGHT CO.
To: Murley T
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION I)
References
IEB-83-03, IEB-83-3, PLA-2504, NUDOCS 8507220266
Download: ML20133D659 (3)


Text

o 7

PP&L Pennsylvania Power & Light Company Two North Ninth Street

  • Allentown, PA 18101
  • 215 / 770 5151 Hanald \\M. Kelser Vice President-Nuclear Operations 215/770-7502 JtAL 161985 Dr. Thomas E. Murley Regional Administrator, Region i U.S. Nuclear Regulatory Commission 631 Park Avenue King of Prussia, PA 19406 SUSQUEHANNA STEAM ELECTRIC STATION FINAL RESPONSE TO IE BULLETIN 83-03 ER 100450/100508 FILE 842-3 Docket Nos. 50-387 PLA-2504 and 50-388

Dear Dr. ' Murley:

PP&L initially responded to IE Bulletin 83-03 on June 9, 1983 (PLA-1697).

This letter serves to provide the final report of inspections conducted pursuant to the bulletin and to provide the status of other commitments made in our original response.

Inservice Inspection Program Revision 2 to the Susquehanna SES Unit 1 Pump and Valve ISI program was submitted on June 30, 1983 (PLA-1731). This revision included new ISI requirements for the twelve check valves in the ESW system flowpati for supplying cooling water to the diesels. The Unit 2 Pump and Valve ISI Program was submitted December 31, 1984 (PLA-2319). It did not include these valves since they are all common valves and the Unit 2 Program was established to cover only those valves not included in the Unit 1 Program.

Inspections of these valves are planned only for Unit I refueling outages with half the valves to be inspected during each outage.

Initial Valve Inspections All twelve check valves were disassembled and inspected prior to or during the Unit i first refueling outage to confirm the integrity of the valve internals.

This included eight Pacific check valves at the Diesel Generator bays and four Anchor Darlina check valves at the ESW pump discharges. The inspections were completed on May 10, 1985. All valves were determined to be satisfactory except 0-11-039 which was discovered to be partially disassembled. Upon disassembly, the check valve disc was found to be not seating properly. The disc nut was found to be loose caused by the disc nut pin being partially out of the nut. The cause of the pin coming out was due to the pin not being peened over sufficiently when the valve was initially assembled. Over time, b

8507220266 850716 di PDR ADOCK 05000387 y

1 l }l G

P1Hi

c:

O v

Page 2 SSES PLA-2504 in i s 1985 ER 100450/100508 File 842-3 Dr. Thomas E. Murley.

vibration had caused the pin to vibrate out of the disc stud allowing the disc nut to loosen. The valve was reassembled and the disc nut pin was properly peened.

This completes PP&L's actions in response to IE Bulletin 83-03.

Very truly yours, H. W. Keiser

- Vice President-Nuclear Operations Affidavit ec:. U.S. Nuclear Regulatory Commission Document Control Desk Washington, D.C.

20555 Mr. R. H. Jacobs - USNRC Ms. M. J. Campagnone - USNRC i,

i

, -,.. -. ~, -. -., - - - - -, -.. - _ _ - = -..... - _. - _.. ~ _ _ _ _ _, -, -. _ - -..

AFFIDAVIT COMMONWEALTH OF PENNSYLVANIA) ss COUNTY OF LEHIGH

)

1, HAROLD W. KEISER, being duly sworn according to law, state that I am Vice President, Nuclear Operations of Pennsylvania Power & Light Company and that the facts set forth on the attached response to IE Bulletin 83-03 rire true and correct to the best of my knowledge, information and belief.

l Harold W. Keiser Vice President, Nuclear Operations