UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555

March 11, 1980

APPLICANTS FOR CONSTRUCTION PERMITS, AND LICENSEES OF PLANTS UNDER CONSTRUCTION

Gentlemen:

Subject: CHANGE OF SUBMITTAL DATE FOR EVACUATION TIME ESTIMATES

The submittal date for the evacuation time estimates requested by my letter of December 26, 1979 (March 31, 1980) is postponed until the General Accounting Office completes its review of this request for information and grants clearance under the Federal Reports Act. GAO clearance normally takes about 45 days.

Sincerely,

Brian K. Grimes, Director Emergency Preparedness Task Group Office of Nuclear Reactor Regulation