Letter Sequence Approval |
|---|
|
|
MONTHYEARML0906301322009-03-0303 March 2009 Request for Exemption from 10 CFR 50, Appendix R, Section Iii.G., Fire Protection of Safe Shutdown Capability (Phase 1) Project stage: Request ML0906402252009-03-0404 March 2009 Request for Exemption from 10 CFR 50, Appendix R, Section Iii.G, Fire Protection of Safe Shutdown Capability (Phase 2) Project stage: Request ML1106911302009-03-13013 March 2009 E-mail from D. Frumkin, NRR to E. Miller, NRR on Acceptance Review for ME0756 Project stage: Acceptance Review ML0907710512009-03-18018 March 2009 E-mail, Miller, NRR, to Stewart, Exelon, Acceptance Review for ME0756 Project stage: Acceptance Review ML0911102032009-07-14014 July 2009 Environmental Assessment and Finding of No Significant Impact Project stage: Other ML1107000842009-10-0101 October 2009 E-mail from D. Frumkin, NRR to B. Metzger, NRR Fw: RAI 1 OCNGS (Draft Ks) Project stage: Draft RAI ML1107000852009-10-0202 October 2009 E-mail from K. Sullivan, BNL to B. Metzger, NRR RAIs Project stage: Other ML1106911362009-10-28028 October 2009 E-mail from D. Frumkin, NRR to E. Miller, Fire Protection RAIs Project stage: Other ML0929311432009-12-0101 December 2009 Request for Additional Information on Request for Exception from 10 CFR 50, Appendix R, Section Iii. G, Fire Protection of Safe Shutdown Capability (Phase 1 & 2) at Oyster Creek Nuclear Generating Station Project stage: RAI ML0933805322009-12-0404 December 2009 Electronic Transmission, Draft Request for Additional Information Regarding Requested Exemptions to Fire Protection Requirements in 10 CFR 50, Appendix R Project stage: Draft RAI ML0935705722010-01-0707 January 2010 Request for Additional Information Regarding Requested Exemptions to Fire Protection Requirements in 10 CFR 50, Appendix R Project stage: RAI ML1107001502010-07-22022 July 2010 E-mail from K. Sullivan, Bn: to D. Frumkin, NRR Et Al. on Revised Oc TERs Project stage: Other ML1107001512010-08-11011 August 2010 E-mail from B. Grenier, NRR to K. Sullivan, BNL J-4242A Period of Performance Project stage: Other ML1035703292011-01-28028 January 2011 OMA Exemption, Fire Protection Input for Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R, Section Iii.G, Fire Protection of Safe Shutdown Capability (Phase 1) Project stage: Approval ML1107004512011-03-30030 March 2011 Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval NRC-2010-0320, Oyster Creek, Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements2011-03-30030 March 2011 Oyster Creek, Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML1107004712011-03-30030 March 2011 Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval NRC-2009-0320, Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements2012-10-15015 October 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML12250A8002012-10-15015 October 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML12250A7252012-10-16016 October 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval 2009-03-04
[Table View] |
Text
[7590-01-P]
NUCLEAR REGULATORY COMMISSION
[Docket No. 50-219; NRC-2009-0320] Exelon Generation Company, LLC Oyster Creek Nuclear Generating Station Exemption AGENCY: Nuclear Regulatory Commission.
ACTION: Notice of issuance; correction.
SUMMARY
- This document corrects a notice appearing in the Federal Register on April 8, 2011 (76 FR 19795), that incorrectly described Sections 3.9.2 and 3.18.2, "Detection, Control, and Extinguishment." This action is necessary to correct erroneous information.
FOR FURTHER INFORMATION CONTACT: John G. Lamb, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone:
301-415-3100, e-mail: John.Lamb@nrc.gov. SUPPLEMENTARY INFORMATION: On page 19805, in the first column, in the third complete paragraph, it is corrected to read from, "The licensee stated that RB-FZ-1E has an area-wide smoke detection system and an automatic fixed deluge water spray system installed over cable trays and open hatches. The deluge suppression system protecting safety-related cable trays is automatically activated by a cross-zoned detection system consisting of linear heat detection wire located on top of the cables in each original safety-related cable trays and smoke detectors are located in each beam pocket at the ceiling," to "The licensee stated that RB-FZ-1E has a smoke detection system and an automatic fixed deluge water spray system installed over cable trays and open hatches. The deluge suppression system protecting safety-related cable trays is automatically activated by a cross-zoned detection system." On page 19812, in the first column, in the second complete paragraph, it is corrected to read from, "The licensee stated that a closed head automatic sprinkler and spray systems protect the south end basement area and the hydrogen seal oil unit," to "The closed head automatic sprinkler system in the condenser bay area was designed, installed and tested in accordance with NFPA 13, 1976 Edition, which was the latest edition of this code at the time of design."
Dated in Rockville, Maryland, this 15th day of October 2012.
FOR THE NUCLEAR REGULATORY COMMISSION
/RA/
Michele G. Evans, Director Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation