MONTHYEARML0906301322009-03-0303 March 2009 Request for Exemption from 10 CFR 50, Appendix R, Section Iii.G., Fire Protection of Safe Shutdown Capability (Phase 1) Project stage: Request ML0906402252009-03-0404 March 2009 Request for Exemption from 10 CFR 50, Appendix R, Section Iii.G, Fire Protection of Safe Shutdown Capability (Phase 2) Project stage: Request ML1106911302009-03-13013 March 2009 E-mail from D. Frumkin, NRR to E. Miller, NRR on Acceptance Review for ME0756 Project stage: Acceptance Review ML0907710532009-03-18018 March 2009 E-mail, Miller, NRR, to Stewart, Exelon, Acceptance Review for ME0780 Project stage: Acceptance Review ML0907710512009-03-18018 March 2009 E-mail, Miller, NRR, to Stewart, Exelon, Acceptance Review for ME0756 Project stage: Acceptance Review ML0911102032009-07-14014 July 2009 Environmental Assessment and Finding of No Significant Impact Project stage: Other ML1107000842009-10-0101 October 2009 E-mail from D. Frumkin, NRR to B. Metzger, NRR Fw: RAI 1 OCNGS (Draft Ks) Project stage: Draft RAI ML1107000852009-10-0202 October 2009 E-mail from K. Sullivan, BNL to B. Metzger, NRR RAIs Project stage: Other ML1107000862009-10-20020 October 2009 E-mail from K. Sullivan, BNL to D. Frumkin, NRR Et Al. Draft RAI OCNGS Ph2 10209 Project stage: Draft Other ML1106911362009-10-28028 October 2009 E-mail from D. Frumkin, NRR to E. Miller, Fire Protection RAIs Project stage: Other ML0929311432009-12-0101 December 2009 Request for Additional Information on Request for Exception from 10 CFR 50, Appendix R, Section Iii. G, Fire Protection of Safe Shutdown Capability (Phase 1 & 2) at Oyster Creek Nuclear Generating Station Project stage: RAI ML0933805322009-12-0404 December 2009 Electronic Transmission, Draft Request for Additional Information Regarding Requested Exemptions to Fire Protection Requirements in 10 CFR 50, Appendix R Project stage: Draft RAI ML0935705722010-01-0707 January 2010 Request for Additional Information Regarding Requested Exemptions to Fire Protection Requirements in 10 CFR 50, Appendix R Project stage: RAI RA-10-026, Response to Request for Additional Information, Request for Exemption from 10 CFR 50, Appendix R, Section Iil.G, Fire Protection of Safe Shutdown Capability2010-04-0202 April 2010 Response to Request for Additional Information, Request for Exemption from 10 CFR 50, Appendix R, Section Iil.G, Fire Protection of Safe Shutdown Capability Project stage: Response to RAI ML1012505802010-06-0707 June 2010 Environmental Assessment and Finding of No Significant Impact Project stage: Other ML1012505742010-06-0707 June 2010 FRN: General Notice. Oyster Creek Nuclear Generating Station - Environmental Assessment and Finding of No Significant Impact Project stage: Other ML1107001502010-07-22022 July 2010 E-mail from K. Sullivan, Bn: to D. Frumkin, NRR Et Al. on Revised Oc TERs Project stage: Other ML1107001512010-08-11011 August 2010 E-mail from B. Grenier, NRR to K. Sullivan, BNL J-4242A Period of Performance Project stage: Other ML1035703292011-01-28028 January 2011 OMA Exemption, Fire Protection Input for Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R, Section Iii.G, Fire Protection of Safe Shutdown Capability (Phase 1) Project stage: Approval ML1107004712011-03-30030 March 2011 Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval NRC-2010-0320, Oyster Creek, Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements2011-03-30030 March 2011 Oyster Creek, Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML1108206262011-03-30030 March 2011 Exemption Project stage: Other ML1107002672011-03-30030 March 2011 Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML1107004512011-03-30030 March 2011 Request for Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval NRC-2009-0320, Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements2012-10-15015 October 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML12250A8002012-10-15015 October 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML12250A7252012-10-16016 October 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML12250A8462012-11-0909 November 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval NRC-2010-0200, Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements2012-11-0909 November 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval ML12250A8352012-11-13013 November 2012 Correction to Exemption from Title 10 of the Code of Federal Regulations Part 50, Appendix R Requirements Project stage: Approval 2009-07-14
[Table View] |
Text
From:
Grenier Bernard I To:
Sullivan. Kenneth Cc:
Higgins. ames C; Frumkin. Daniel
Subject:
RE: J-4242A Period of Performance Date:
Wednesday, August 11, 2010 11:18:42 AM Greetings, Ken!
Not a problem on the extension, Ken. I'll check with Dan on the extension.
As for funds, my records show that you have spent $53.4K out of FY-10 available funds of
$80.3K, as of May. Based on what you know is left to be done, do you have sufficient funding; or, if not how much more do you need?
Bernie From: Sullivan, Kenneth [1] t Sent: Wednesday, August 11, 2010 9:22 AM To: Grenier, Bernard Cc: Higgins, James C
Subject:
J-4242A Period of Performance Hi Bernie-The period of performance on J-4242A (Technical Assistance in Support of Fire Protection Licensing Actions; Task order 1, Project Number 15446) will expire on September 30, 2010.
Since I expect the work to continue past September 30 I request a no-cost extension of the period of performance to December 30, 2010.
J-4242A Task 1 Status
- 1. Oyster Creek -
ME 0756 and ME0780 Task Complete.
TER submitted July 22.
- 2.
Wolf Creek -
ME0798 and ME0799 Draft TER submitted for review and comment.
- 3.
Indian Point 2 and 3 -
Awaiting receipt of responses to RAIS submitted on July 8, 2010 (second set).
I apologize in advance for any inconvenience this request may have caused.
Thanks!
Ken Sullivan Energy sciences and Technology Department
Brookhaven National Laboratory (631) 344-7915 mailto:ks@bnl.gov