NLS2008083, Revision to Commitment Referenced in Amendment 231 Safety Evaluation
| ML082700454 | |
| Person / Time | |
|---|---|
| Site: | Cooper |
| Issue date: | 09/22/2008 |
| From: | Minahan S Nebraska Public Power District (NPPD) |
| To: | Document Control Desk, Office of Nuclear Reactor Regulation |
| References | |
| NLS2008083, TAC MD7385 | |
| Download: ML082700454 (3) | |
Text
N Nebraska Public Power District "Always there when you need us" NLS2008083 September 22, 2008 U.S. Nuclear Regulatory Commission Attention: Document Control Desk Washington, D.C. 20555-0001
Subject:
Revision to Commitment Referenced in Amendment 231 Safety Evaluation Cooper Nuclear Station, Docket No. 50-298, DPR-46
References:
- 1.
Letter from Stewart B. Minahan, Nebraska Public Power District, to the U.S. Nuclear Regulatory Commission, dated November 19, 2007, "License Amendment Request to Revise Technical Specifications -
Appendix K Measurement Uncertainty Recapture Power Uprate"
- 2.
Letter from Carl F. Lyon, U.S. Nuclear Regulatory Commission, to Stewart B. Minahan, Nebraska Public Power District, dated June 30, 2008, "Cooper Nuclear Station - Issuance of Amendment Re: Measurement Uncertainty Recapture Power Uprate (TAC No. MD73 85)"
Dear Sir or Madam:
The purpose of this letter is to communicate the revision of a commitment made in Reference 1.
In that letter, the Nebraska Public Power District committed to the submittal of a Startup Test Report within 90 days following resumption of power operation following Refueling Outage 24 (RE-24). The Nuclear Regulatory Commission (NRC) reflected this commitment in the issuance of Amendment 231 in Reference 2. This commitment has been revised to submit a Startup Test Report to the NRC within 90 days following completion of the power uprate special test.
At the time the original commitment was made, the measurement uncertainty power uprate license amendment was anticipated prior to the conclusion of RE-24. The special test for power uprate would have been accomplished during power ascension. However, Amendment 231 was not granted until June 30, 2008, which delayed the completion of the special test. The intent of the original commitment was to provide the Startup Test Report 90 days or sooner from the completion of the special test. Based on the completion date of the special test, the revised commitment due date is October 23, 2008.
The due date of the original commitment was August 15, 2008. The missed due date and the need to revise the commitment has been discussed with the NRC Project Manager for Cooper Nuclear Station (CNS), and has been entered into the CNS corrective action program.
COOPER NUCLEAR STATION A
P.O. Box 98 / Brownville, NE 68321-0098 Telephone: (402) 825-3811 / Fax: (402) 825-5211 wwwv.nppd.com
NLS2008083 Page 2 of 2 If you have questions concerning this matter, please contact David Van Der Kamp, Licensing Manager at (402) 825-2904.
Sincerely, Stewart B. Minahan Vice President-Nuclear and Chief Nuclear Officer
/dm cc:
Regional Administrator USNRC - Region IV Cooper Project Manager USNRC - NRR Project Directorate IV-1 Senior Resident Inspector USNRC - CNS NPG Distribution CNS Records
ATTACHMENT 3 LIST OF REGULATORY COMMITMENTS@
ATTACHMENT 3 LIST OF REGULATORY COMMITMENTS0 Correspondence Number: NLS2008083 The following table identifies those actions committed to by Nebraska Public Power District (NPPD) in this document. Any other actions discussed in the submittal represent intended or planned actions by NPPD. They are described for information only and are not regulatory commitments. Please notify the Licensing Manager at Cooper Nuclear Station of any questions regarding this document or any associated regulatory commitments.
COMMITMENT COMMITTED DATE COMMITMENT NUMBER OR OUTAGE Submit Startup Test Report to NRC NLS2007069-11 Within 90 days following completion of Power Uprate special test
-I.
+
+
+
- 1--