Category:License-Operator
MONTHYEARML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20072L2192020-03-12012 March 2020 Response to Regulatory Issue Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19211C7742019-07-30030 July 2019 Requalification Program Inspection ML19135A6642019-05-15015 May 2019 Units 2 & 3; River Bend, and Waterford 3 - Response to RIS 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19044A6012019-02-0404 February 2019 Operator Licensing Written Exam Approval ML19029B3192019-01-28028 January 2019 Operator Licensing Operating Test Approval ML18159A3512018-06-0505 June 2018 Final Operating Test (Sections a, B, and C) - JPM C, D, K Corrected (Folder 3) ML18047A1692018-01-0303 January 2018 Final Qa/Related Forms (Folder 1) ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18047A1702017-11-0707 November 2017 Handouts to Applicants (Folder 3) ML17297A6432017-10-24024 October 2017 Initial Operator Licensing Written Examination Approval - Indian Point Energy Center, Unit 3 ML17297A0132017-10-23023 October 2017 Initial Operator Licensing Operating Test Approval - Indian Point Energy Center, Unit 3 ML17234A5902017-08-22022 August 2017 Requalification Program Inspection - Indian Point Nuclear Generating, Unit 3 NL-17-080, Operator Licensing Examination Data2017-06-28028 June 2017 Operator Licensing Examination Data ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML17206A4422016-10-31031 October 2016 Final Qa/Related Forms - Form ES-401-6 (Folder 1) ML16365A0432016-10-31031 October 2016 Handouts to Applicants (Folder 3) ML17069A2842016-10-31031 October 2016 Final Outlines Update ES-401-2, ES-401-3 ML16365A0412016-10-31031 October 2016 Final Outlines (Folder 3) ML17206A4452016-10-31031 October 2016 Final Qa/Related Forms (Folder 1) ML16365A0442016-10-31031 October 2016 Final Operating Test (Sections a, B, and C) (Folder 3) ML16365A0422016-10-31031 October 2016 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML16301A2882016-10-27027 October 2016 Initial Operator Licensing Written Examination Approval - Indian Point Energy Center, Unit 2 ML16298A0162016-10-20020 October 2016 Initial Operator Licensing Operating Test Approval - Indian Point Energy Center, Unit 2 ML17047A5982016-10-0303 October 2016 NRC Comments on Draft Facility-Developed Operating Test (Folder 2) ML17047A5972016-10-0303 October 2016 NRC Comments on Draft Facility-Developed Written Exam (Folder 2) ML17047A6012016-09-0101 September 2016 Draft Operating Exam (Section a, B, and C) (Folder 2) ML17047A6002016-09-0101 September 2016 Draft Written Exam (Folder 2) ML17047A5992016-07-18018 July 2016 Draft - Outlines (Folder 2) (Facility Letter Dtd - 07/18/2016) NL-16-073, Operator Licensing Examination Data2016-07-0707 July 2016 Operator Licensing Examination Data ML16189A0832016-07-0606 July 2016 Requalification Program Inspection - Indian Point Energy Center, Unit 2 ML16119A0012016-04-27027 April 2016 Senior Reactor and Reactor Operator Initial License Examinations-Indian Point Energy Center, Unit 2 ML15223A0162015-08-10010 August 2015 Requalification Program Inspection-Indian Point Energy Ctr, Unit 3 IR 05000286/20153012015-06-24024 June 2015 Er 05000286/2015301; 5/11/2015 to 6/18/2015; Indian Point Energy Center, Unit 3: Initial Operator Licensing Examination Report ML15163A2302015-06-0404 June 2015 Draft - Outlines (Folder 2) ML15163A2322015-06-0404 June 2015 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML15163A2312015-06-0404 June 2015 Draft Written Exam (Folder 2) ML15163A2292015-06-0404 June 2015 All Comments on Draft NRC-Developed Exam (Operating) (Folder 2) ML15160A4702015-06-0404 June 2015 Final Outlines (Folder 3) ML15160A4642015-06-0404 June 2015 Final Operating Exam (Sections a, B, and C) (Folder 3) ML15160A4562015-06-0404 June 2015 Handouts to Applicants (Folder 3) ML15160A4092015-06-0404 June 2015 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML15282A3072015-06-0101 June 2015 Final Qa/Related Forms (Folder 1) ML14308A0522014-10-29029 October 2014 Final Outlines (Folder 3) ML14307B5652014-10-29029 October 2014 Draft Operating Exam (Section a) (Folder 2) ML14307B5212014-10-29029 October 2014 Draft-Outlines (Folder 2) ML14307B3852014-10-29029 October 2014 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML14308A2512014-10-29029 October 2014 Final Operating Exam (Section a) (Folder 3) ML14251A2402014-09-0808 September 2014 Operator Licensing Retake Operating Examination Approval-Indian Point Unit 2 2021-01-12
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML21012A2692021-01-12012 January 2021 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2021 ML20072L2192020-03-12012 March 2020 Response to Regulatory Issue Summary 2020-01, Preparation and Scheduling of Operator Licensing Examinations ML19352D6572019-12-16016 December 2019 Announcement 0f Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2020 ML19211C7742019-07-30030 July 2019 Requalification Program Inspection ML19135A6642019-05-15015 May 2019 Units 2 & 3; River Bend, and Waterford 3 - Response to RIS 2019-02, Preparation and Scheduling of Operator Licensing Examinations ML19029B3192019-01-28028 January 2019 Operator Licensing Operating Test Approval ML18159A3512018-06-0505 June 2018 Final Operating Test (Sections a, B, and C) - JPM C, D, K Corrected (Folder 3) ML18047A1692018-01-0303 January 2018 Final Qa/Related Forms (Folder 1) ML18005A4202018-01-0303 January 2018 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2018 ML18047A1702017-11-0707 November 2017 Handouts to Applicants (Folder 3) ML17297A6432017-10-24024 October 2017 Initial Operator Licensing Written Examination Approval - Indian Point Energy Center, Unit 3 ML17297A0132017-10-23023 October 2017 Initial Operator Licensing Operating Test Approval - Indian Point Energy Center, Unit 3 NL-17-080, Operator Licensing Examination Data2017-06-28028 June 2017 Operator Licensing Examination Data ML17018A2822017-01-17017 January 2017 Announcement of Generic Fundamentals Examination Section of the Written Operator Licensing Examination for 2017 ML16365A0442016-10-31031 October 2016 Final Operating Test (Sections a, B, and C) (Folder 3) ML17206A4422016-10-31031 October 2016 Final Qa/Related Forms - Form ES-401-6 (Folder 1) ML17206A4452016-10-31031 October 2016 Final Qa/Related Forms (Folder 1) ML17069A2842016-10-31031 October 2016 Final Outlines Update ES-401-2, ES-401-3 ML16365A0422016-10-31031 October 2016 Final Written Examination with Answer Key (401-5 Format) (Folder 3) ML16365A0412016-10-31031 October 2016 Final Outlines (Folder 3) ML16365A0432016-10-31031 October 2016 Handouts to Applicants (Folder 3) ML16301A2882016-10-27027 October 2016 Initial Operator Licensing Written Examination Approval - Indian Point Energy Center, Unit 2 ML16298A0162016-10-20020 October 2016 Initial Operator Licensing Operating Test Approval - Indian Point Energy Center, Unit 2 ML17047A5972016-10-0303 October 2016 NRC Comments on Draft Facility-Developed Written Exam (Folder 2) ML17047A5982016-10-0303 October 2016 NRC Comments on Draft Facility-Developed Operating Test (Folder 2) ML17047A6002016-09-0101 September 2016 Draft Written Exam (Folder 2) ML17047A6012016-09-0101 September 2016 Draft Operating Exam (Section a, B, and C) (Folder 2) ML17047A5992016-07-18018 July 2016 Draft - Outlines (Folder 2) (Facility Letter Dtd - 07/18/2016) NL-16-073, Operator Licensing Examination Data2016-07-0707 July 2016 Operator Licensing Examination Data ML16119A0012016-04-27027 April 2016 Senior Reactor and Reactor Operator Initial License Examinations-Indian Point Energy Center, Unit 2 ML15223A0162015-08-10010 August 2015 Requalification Program Inspection-Indian Point Energy Ctr, Unit 3 IR 05000286/20153012015-06-24024 June 2015 Er 05000286/2015301; 5/11/2015 to 6/18/2015; Indian Point Energy Center, Unit 3: Initial Operator Licensing Examination Report ML15163A2312015-06-0404 June 2015 Draft Written Exam (Folder 2) ML15163A2322015-06-0404 June 2015 Draft Operating Exam (Sections a, B, and C) (Folder 2) ML15160A4562015-06-0404 June 2015 Handouts to Applicants (Folder 3) ML15163A2302015-06-0404 June 2015 Draft - Outlines (Folder 2) ML15163A2292015-06-0404 June 2015 All Comments on Draft NRC-Developed Exam (Operating) (Folder 2) ML15160A4092015-06-0404 June 2015 Final Written Examination with Answer Key (401-5 Format) (Folder 2) ML15160A4702015-06-0404 June 2015 Final Outlines (Folder 3) ML15160A4642015-06-0404 June 2015 Final Operating Exam (Sections a, B, and C) (Folder 3) ML15282A3072015-06-0101 June 2015 Final Qa/Related Forms (Folder 1) ML14308A0522014-10-29029 October 2014 Final Outlines (Folder 3) ML14307B5652014-10-29029 October 2014 Draft Operating Exam (Section a) (Folder 2) ML14307B5212014-10-29029 October 2014 Draft-Outlines (Folder 2) ML14307B3852014-10-29029 October 2014 NRC Comments on Draft Licensee-Developed Exam (Operating) (Folder 2) ML14308A2512014-10-29029 October 2014 Final Operating Exam (Section a) (Folder 3) ML14251A2402014-09-0808 September 2014 Operator Licensing Retake Operating Examination Approval-Indian Point Unit 2 ML14195A0902014-07-14014 July 2014 Requalification Program Inspection-Indian Point Station, Unit 2 IR 05000247/20143012014-03-31031 March 2014 Er 05000247-14-301; 2/10/2014 to 2/19/2014; Indian Point, Units 2; Initial Operator Licensing Examination Report ML14091A6922014-03-31031 March 2014 Er 05000247-14-301; 2/10/2014 to 2/19/2014; Indian Point, Units 2; Initial Operator Licensing Examination Report 2021-01-12
[Table view] |
Text
Entergy Nuclear Northeast Entergy Nuclear Operations, Inc.
Indian Point Energy Center 295 Broadway, Suite 1 P.O. Box 249 Buchanan, NY 1051 1 -0249 I!4 ;fJG -2 ..
D 1 :37 July 30, 2004 Indian Point Unit Nos. 2 and 3 Docket Nos. 50-247 and 50-286 NL-04-093 Mr. Richard J. Conte Chief, Operational Safety Branch Division of Reactor Safety - Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415
Subject:
Justification of Six-Month On-site Experiencefor Licensed Operator Qualificationfor Indian Point Energy Center
References:
- 1) ACAD 00-003 Revision 1, Guidelines for Initial Training and Quaiification of Licensed Operators
- 2) ANSVANS-3.1-1978, American National Standard for Selection and, Training Of Nuclear Power Plant Personnel
- 3) Regulatory Guide 1.8 Revision 3, Qualification and Trair!ing of Personnelfor Nuclear Power Plants
- 4) Regulatory Issue Summary 01-001, Eligibility of Operator License Applicants
- 5) Information Notice No. 98-37, Eligibility of Operator License Applicants
- 6) NUREG-I 021 Draft Revision 9, Operator Licensing Examination Standards for Power Reactors
- 7) Examination Standard-202, FrequentlyAsked Questions About Operator Licensing Program, NRC Website (www.nrc.gov/reactors/operator-licensinglfaq.htmI#ES-202)
Dear Sir:
Indian Point Energy Center (IPEC) is committed to ANSI-3.1 1978. Section 4.3.1 of ANSI 3.1 states, At least six months of the nuclear power plant experience shall be at the plant of which he seeks a license unless such experience is acquired on a similar unit. This requirement is also discussed in several additional documents listed under the reference section. The six months can be in any of several positions as outlined in Reference 1.
Docket No. 50-247 NL-04-093 Page 2 of 5 The Entergy Corporation recently purchased Indian Point Unit 2 (IP2) and Indian Point Unit 3 (IP3). Although some individuals are still assigned to specific units, the majority of the staff is assigned responsibilities for both units. It is our belief that IP2 and IP3 are similar units as referred to in ANSI 3.1. This conclusion was reached based upon a systematic review as discussed below.
In an effort to integrate the units and streamline production, several processes have been combined. Some of these processes have been changed to Entergy Corporation, Entergy Nuclear Northeast, and/or IPEC station procedures/expectations. Even though IP2 and IP3 maintain separate licenses, these common practices are the same. In obtaining the six-month experience, a staff member or any individual assigned to the various departments/positions will use these processes. In fact, other than the on-watch personnel engaged in licensed and non-licensed duties at the station, there is little or no difference in the processes used regardless of the unit involved.
IPEC has undertaken an aggressive integration plan, now in its final stages, to combine the two units. Staff members are now responsible for activities for both units.
Engineering, Maintenance, Health Physics, Chemistry, Security, Licensing, Corrective Action, Operations Staff, Operations Procedure Group, Training, Human Resources, Finance, Purchasing, Accounting, Outage Planning, Safety, Quality Assurance, Information Technology, Records and Documents, Administrative Services, Facilities, Emergency Planning, and Work Control are now IPEC Departments. The site Fire Brigade and the Emergency Response Organization now have members from both units. Non-licensed and licensed operators are also trained to perform selected cross unit activities.
Examples of processes that are combined include:
e IPEC Site Management Manual Process e IPEC ImplementingProcedure Preparation, Review, and Approval e Distribution of Controlled Documents e IPEC Procedure Writing Manual e Records Management Program e All Emergency Plan Procedures e IPEC Fire Protection Program Plan e Preventive Maintenance Program e Check Valve Reliability Program e Surveillance Test Program e Process for Control of Indian Point 1
Docket No. 50-247 NL-04-093 Page 3 of 5 e Inservice Inspection /Test Program 0 IPEC Spill/Release Response Plan e Waste Management Program e Pre-job Briefing and Post Job Critiques e Electrical Safety e Electrical Safety Program e Exposure Control Plan for Bloodborne Pathogens e Corrective Action Review Board e Operating LicenseAmendments e Notice of Enforcement Discretion e Event Notification and Reporting e Notices, Instructions and Reports to Workers: Inspection and Investigations e NRC Commitment Management Program 0 Technical Specification Bases, Technical Requirements Manual and Updated Final Safety Analysis Report (UFSAR) Amendment Preparation and Control e PerformanceIndicator Preparation Process e Operational Decision-Making Issues (ODMI) Process e New York Public Service Commission Notifications and Document Transmittals e IPEC Trending Process e Site Communications e IPEC Troubleshooting and Repair e IPEC Calibration and Control of Measuring and Test Equipment (MTE) e Housekeeping Policy e FIN (Fix It Now) e Fuel Assembly Receipt Inspection e Reactivity Management Program e Offsite Power Continuous Monitoring and Notification e Post Transient Evaluation e Plant Labeling Program e Outage Management e Startup Management e Project Funding Policy e Quality Assurance FunctionalArea Evaluation e Temporary Shielding Program e Radiation Exposure Guidelines e ALARA Program
Docket No. 50-247 NL-04-093 Page 4 of 5 Guidelines for Response to Acts Involving TamperingISabotageDirected Against Plant Equipment In and Out-Processing Multiple Training Program for Maintenance, Operations and ESP Work Control Process Planning Rapid Response Cont ingency Planning In conclusion, the processes used at IPEC are, for the most part, not unit-specific.
IPEC is proposing that any individual assigned to either unit routinely interfaces with these processes and therefore obtains the same level of experience. This experience should therefore be credited for the six-month on-site requirement.
We look forward to hearing your comments on this justification, and respectfully request a response by August 31, 2004. Should you or your staff have any questions regarding this matter, please contact Mr. Patric W. Conroy, Manager, Licensing at (914) 734-6668.
There are no commitments contained in this letter.
Sincerely,
/--I Patric N.Conroy Manager, Licensing Indian Point Energy Center cc: seepage5
Docket No. 50-247 NL-04-093 Page 5 of 5 cc: U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Mail Station 0-PI -17 Washington, DC 20555-0001 Mr. Samuel J. Collins Regional Administrator - Region I U.S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, PA 19406-1415 Mr. Patrick D. Milano, Sr. Project Manager Project Directorate I Division of Licensing Project Management Office of Nuclear Reactor Regulation U.S. Nuclear Regulatory Commission Mail Stop 0-8-C2 Washington, DC 20555-0001 Resident Inspectors Office Indian Point Unit 2 U.S. Nuclear Regulatory Commission PO Box 59 Buchanan, NY 10511-0059 Resident Inspectors Office Indian Point Unit 3 U.S. Nuclear Regulatory Commission PO Box 337 Buchanan, NY 10511-0337