ND-17-0482, ITAAC Completion and Operational Program Implementation Schedule Updates (Required by 10 CFR 52.99(a) and License Conditions 2.D.(11) and 2.D.(12)(e))

From kanterella
Jump to navigation Jump to search
ITAAC Completion and Operational Program Implementation Schedule Updates (Required by 10 CFR 52.99(a) and License Conditions 2.D.(11) and 2.D.(12)(e))
ML17263B123
Person / Time
Site: Summer  South Carolina Electric & Gas Company icon.png
Issue date: 09/20/2017
From: Ayanna Rice
South Carolina Electric & Gas Co
To:
Document Control Desk, Office of New Reactors
References
NND-17-0482
Download: ML17263B123 (2)


Text

April Rice

< sCE&G@ A SCANA COM PAN Y Manager New Nuclear Licensing September 20, 2017 NND-17-0482 10 CFR 52.97 10 CFR 52.99 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001 Virgil C. Summer Nuclear Station (VCSNS) Units 2 and 3 Combined License Nos. NPF-93 and NPF-94 Docket Numbers52-027 and 52-028

Subject:

ITAAC Completion and Operational Program Implementation Schedule Updates (Required by 10 CFR 52.99(a) and License Conditions 2.D.(11) and 2.D.(12)(e))

References:

1. Letter from Jeffery B. Archie to NRC, V.C. Summer, Units 2 and 3 - Notification of Termination of Project Construction, dated August 17, 2017(ML172298487)
2. Letter from April Rice to NRC, 10 CFR 52.99(a) ITAAC Completion Schedule Submittal, dated March 22, 2017 (ML17082A282)
3. Letter from April Rice to NRC, Operational Program Implementation Schedule in Accordance With License Conditions 2.D.(11) and 2.D.(12)(e), dated March 23, 2017 (ML17082A490)

Pursuant to 10 CFR 52.99(a) and in accordance with License Conditions 2.D.(11) and 2.D.(12)(e) of Combined Licenses (COLs) NPF-93 and NPF-94, South Carolina Electric & Gas (SCE&G) is submitting this letter to update the ITAAC Completion and Operational Program Implementation Schedules for Virgil C. Summer Units 2 and 3.

10 CFR 52.99(a), Licensee schedule for completing inspections, tests, or analyses, requires that SCE&G as a COL holder under 10 CFR Part 52, submit to the NRC updates to its ITAAC schedules per its prescribed frequencies.

License Conditions 2.D.(11) and 2.D.(12)(e) require that the Operational Program Implementation Schedule be updated every 6 months until 12 months before scheduled fuel loading, and every month thereafter until each license condition has been fully implemented.

As described in Reference 1, SCE&G stopped construction activities on the VCSNS Units 2 & 3 site and placed the two partially-constructed nuclear units in a terminated status, consistent with the Commission's policy statement on deferred and terminated plants (52 Fed.

Reg. 38,077). Accordingly, this letter provides the required schedule updates by informing the NRC that all previously uncompleted ITAAC and Operational Program Implementation activities, described in References 2 and 3, are now in a suspended, To Be Determined (TBD) state, pending further action on disposition of COLs NPF-93 and NPF-94.

SCE&G I New Nuclear Deployment* P. 0 . Box 88

  • www.sceg.com

Document Control Desk NND-17-0482 This letter contains no regulatory commitments.

Should you have any questions regarding this letter, please contact me by telephone at (803) 941-9858, or by email at april.rice@scana.com I declare under penalty of perjury that the foregoing is true and correct.

Executed on this ~ day of S "1 -\-0!'\ b.t.A 2017.

Sincerely,

~L April Rice Manager New Nuclear Licensing JRB/ARR/jrb c

Vanna Ordaz Cathy Haney Billy Gleaves Tom Fredette Tomy Nazario Jim Reece Stephen A. Byrne Jeffrey B. Archie Alvis J. Bynum April Rice Bruce Thompson Justin Bouknight VCSummerMail@westinghouse.com VCSummer2&3project@westinghouse.com DCRM-EDMS@SCANA. COM VCSNN DCorrespondence@scana.com Carl Churchman Susan E. Jenkins William M. Cherry