PNP 2025-087, Supplement to Request for Additional Information Regarding Second Request for Exemption from Requirements O 10 CFR 26.205, Fitness for Duty Programs - Work Hours

From kanterella
(Redirected from ML25365A936)
Jump to navigation Jump to search

Supplement to Request for Additional Information Regarding Second Request for Exemption from Requirements O 10 CFR 26.205, Fitness for Duty Programs - Work Hours
ML25365A936
Person / Time
Site: Palisades Entergy icon.png
Issue date: 12/31/2025
From: Fleming J
Holtec, Holtec Palisades
To:
Office of Nuclear Reactor Regulation, Document Control Desk
References
PNP 2025-087
Download: ML25365A936 (0)


Text

27780 Blue Star Highway, Covert, MI 49043 PNP 2025-087 10 CFR 26.9 December 31, 2025 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-0001 Palisades Nuclear Plant NRC Docket No. 50-255 Renewed Facility Operating License No. DPR-20

Subject:

Supplement to Request for Additional Information Regarding Second Request for Exemption from Requirements of 10 CFR 26.205, "Fitness for Duty Programs -

Work Hours" By letter dated August 12, 2025 (Reference 1), in accordance with Title 10 of the Code of Federal Regulations (10 CFR), Part 26, Fitness for Duty Programs, Section 26.9, Specific exemptions, Palisades Energy, LLC (Palisades Energy) requested U.S. Nuclear Regulatory Commission (NRC) approval of a one-time exemption from the specific requirements of 10 CFR 26.205, Work hours. The proposed exemption, as supplemented by the letter dated October 15, 2025 (Reference 2), would allow the use of the less restrictive work hour limitations specified in 10 CFR 26.205(d)(4) and (d)(5) in lieu of the requirements of 10 CFR 26.205(d)(3) and (d)(7) for an additional 60-day period to support outage activities for restart of the Palisades Nuclear Plant (PNP).

On October 24, 2025 (Reference 3), the NRC granted the requested one-time exemption to use the less restrictive outage work hour controls in 10 CFR 26.205(d)(4) and (d)(5) for a period not to exceed 60 days to support restart activities during the period of the proposed exemption. The exemption period commenced on November 3, 2025 and will expire on January 1, 2026.

By letter dated December 12, 2025 (Reference 4), Palisades Energy requested a second request for a one-time exemption from the specific requirements of 10 CFR 26.205. This proposed exemption would allow use of the less restrictive outage work hour controls in 10 CFR 26.205(d)(4) for an additional period of 60 days, to commence on January 2, 2026, after a two week rest and reset period. The proposed exemption would apply to personnel performing duties specified in 10 CFR 26.4(a)(2) [Health Physics and Chemistry] and 10 CFR 26.4(a)(4) [Maintenance and Projects].

On December 22, 2025 (Reference 5), Palisades Energy received a Request for Additional Information (RAI) by electronic mail (email) regarding the second request for exemption from the requirement of 10 CFR 26.205. Palisades Energy provided the responses to the RAI on December 26, 2025 (Reference 6).

On December 30, 2025, the NRC staff and representatives of Palisades Energy held a clarification call to discuss the RAI response. The Enclosure to this letter supplements the previous RAI response as agreed during the call to provide additional descriptions and

PNP 2025-087 Page 2 of 3 provisions for managing and bounding cumulative fatigue. The attachment to the Enclosure provides three new commitments regarding the controls on work hours.

Palisades Energy requests approval of the exemption request no later than January 01, 2026 to support the ongoing activities that are critical for the successful completion of the current outage and restart of PNP.

If you have any questions regarding this submittal, please contact Kami Miller, Regulatory Assurance Manager, at (269) 764-2375.

Respectfully, Jean A. Fleming Vice President, Licensing and Regulatory Assurance Holtec International

References:

1.

Holtec Palisades, LLC (Holtec Palisades) letter to U.S. Nuclear Regulatory Commission (NRC), Request for Exemption from Requirements of 10 CFR 26.205, "Fitness for Duty Programs - Work Hours," dated August 12, 2025 (ADAMS Accession No. ML25224A206)

2.

Holtec Palisades letter to NRC, Supplement and Response to Request for Confirmatory Information Regarding Request for Exemption from Requirements of 10 CFR 26.205, dated October 15, 2025 (ADAMS Accession No. ML25288A074)

3.

NRC letter to Holtec Palisades, Palisades Nuclear Plant - One-Time Exemption from the Requirements of 10 CFR 26.205(d)(3) and (d)(7) (EPID L-2025-LLE-0022), dated October 24, 2025 (ADAMS Accession Nos.

ML25293A005 and ML25293A007)

4.

Holtec Palisades letter to NRC, Second Request for Exemption from Requirements of 10 CFR 26.205, "Fitness for Duty Programs - Work Hours,"

dated December 12, 2025 (ADAMS Accession No. ML25346A199)

5.

NRC email to Holtec Palisades, Request for Additional Information RE:

Request for Second Exemption from Part 26 Work Hours (LL-2025-LLE-0032), dated December 22, 2025

6.

Holtec Palisades letter to NRC, Request for Additional Information Regarding Second Request for Exemption from Requirements of 10 CFR 26.205, "Fitness for Duty Programs - Work Hours," dated December 26, 2025 Digitally signed by Jean A. Fleming DN: cn=Jean A. Fleming, c=US, o=Holtec Decommissioning International, LLC, ou=Regulatory and Environmental Affairs, email=J.Fleming@Holtec.com Date: 2025.12.31 10:55:32 -05'00' Jean A.

Fleming

PNP 2025-087 Page 3 of 3

Enclosure:

Supplement to Request for Additional Information Regarding Second Request for Exemption from Requirements of 10 CFR 26.205 Enclosure

Attachment:

List of Regulatory Commitments cc:

NRC Region III Regional Administrator NRC Senior Resident Inspector - Palisades Nuclear Plant NRC Project Manager - Palisades Nuclear Plant

PNP 2025-087 Enclosure Page 1 of 10 PNP 2025-087 Enclosure Supplement to Request for Additional Information Regarding Second Request for Exemption from Requirements of 10 CFR 26.205

PNP 2025-087 Enclosure Page 2 of 10 Supplement to Request for Additional Information Regarding Second Request for Exemption from Requirements of 10 CFR 26.205

=

Background===

By letter dated August 12, 2025 (Reference 1), Palisades Energy, LLC (Palisades Energy) requested U.S. Nuclear Regulatory Commission (NRC) approval of a one-time exemption from the specific requirements of Title 10 of the Code of Federal Regulations (10 CFR), 10 CFR 26.205, Work hours. The proposed exemption, as supplemented, would allow the use of the less restrictive work hour limitations specified in 10 CFR 26.205(d)(4) and (d)(5) in lieu of the requirements of 10 CFR 26.205(d)(3) and (d)(7) for an additional 60-day period to support outage activities for restart of the Palisades Nuclear Plant (PNP). The NRC granted the exemption on October 24, 2025 (Reference 2).

By letter dated December 12, 2025 (Reference 3), Palisades Energy requested a second request for a one-time exemption from the specific requirements of 10 CFR 26.205. This proposed exemption would allow use of the less restrictive outage work hour controls in 10 CFR 26.205(d)(4) for an additional period of 60 days. The proposed exemption would apply to personnel performing duties specified in 10 CFR 26.4(a)(2) [Health Physics and Chemistry]

and 10 CFR 26.4(a)(4) [Maintenance and Projects].

On December 22, 2025 (Reference 4), Palisades Energy received a Request for Additional Information (RAI) by electronic mail (email) regarding the second request for exemption from the requirement of 10 CFR 26.205. Palisades Energy provided the responses to the RAI on December 26, 2025 (Reference 5). Following submittal of the RAI responses, the NRC staff and representatives of Palisades Energy held a clarification call on December 30, 2025 to discuss the RAI response. As a result of the call, Palisades Energy agreed to supplement the RAI response. The supplemental information is provided in this Enclosure.

Supplement to Palisades Energy Response to RAI 1.a:

As understood in the clarification call conducted between the NRC and Palisades Energy on December 30, 2025, Palisades Energy hereby provides the following tables which include updated commitments for Tesco Projects, the Fuel Handling Equipment (FHE) project, and the Alloy 600 project. The tables also provide updated work schedules from November 3 to December 30, 2025, demonstrating cumulative average weekly hours for that period. Lastly, Palisades Energy has concluded that the covered individuals which were categorized under Framatome Projects have completed their scope of work and are not currently scheduled for future work. Therefore, the individuals categorized under Framatome Projects no longer apply to this exemption request.

PNP 2025-087 Enclosure Page 3 of 10 Fatigue Management - Affected Group: 10 CFR 26.4(a)(2) 10 CFR Position Schedule 11/03 to 12/18/2025 26.4(a)(2)

Chemistry The majority of the individuals in the Chemistry department worked between 8 and 9-hour shifts for 5 consecutive days followed by 2 consecutive days off.

Additional days off were provided where practicable to support fatigue management.

This schedule was in compliance with 10 CFR 26.205(d)(1), (d)(2) and (d)(7),

and resulted in a cumulative average of 37.92 hours0.00106 days <br />0.0256 hours <br />1.521164e-4 weeks <br />3.5006e-5 months <br /> per week.

The highest weekly average was 50.29 hours3.356481e-4 days <br />0.00806 hours <br />4.794974e-5 weeks <br />1.10345e-5 months <br /> per week.

There are no current plans to increase work hours until primary system passivation activities commence. The date for the start of passivation is not yet determined.

The Chemistry department is currently observing a rest and reset period in which no individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 36.51 hours5.902778e-4 days <br />0.0142 hours <br />8.43254e-5 weeks <br />1.94055e-5 months <br /> per week.

PNP 2025-087 Enclosure Page 4 of 10 Fatigue Management - Affected Group: 10 CFR 26.4(a)(2) 10 CFR Position Schedule 11/03 to 12/18/2025 26.4(a)(2)

Health Physics The majority of the individuals in the Health Physics department worked 12-hour shifts for 4 consecutive days followed by 1 day off.

Additional days off were provided where practicable to support fatigue management.

This schedule was in compliance with 10 CFR 26.205(d)(1), (d)(2) and (d)(4),

and resulted in a cumulative average of 63.79 hours9.143519e-4 days <br />0.0219 hours <br />1.306217e-4 weeks <br />3.00595e-5 months <br /> per week.

The highest weekly average was 70.38 hours4.398148e-4 days <br />0.0106 hours <br />6.283069e-5 weeks <br />1.4459e-5 months <br /> per week.

The Health Physics department does not plan to deviate from this work schedule during the proposed exemption period.

The Health Physics department is currently observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/3 to 12/30/2025: 59.73 hours8.449074e-4 days <br />0.0203 hours <br />1.207011e-4 weeks <br />2.77765e-5 months <br /> per week.

Summary As described in the Group 10 CFR 26.4(a)(2) table above, to support the ongoing PNP outage activities and subsequent plant restart, the covered individuals in Chemistry and Health Physics work different schedules. The schedules will remain in compliance with 10 CFR 26.205(d)(1), (d)(2), and (d)(4). To ensure an adequate reset before continuing outage activities, the individuals in this Group are currently observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from December 19, 2025 through January 1, 2026.

The Group 10 CFR 26.4(a)(2) table includes the scheduled 30-minute shift turnover time as part of the work hour averaging calculation. This is conservative because shift turnover time may be excluded from the calculation of an individual's work hours (

References:

Nuclear Energy Institute (NEI) 06-11, Section 8.1, and NRC Regulatory Guide 5.73, Appendix B, page B-11).

PNP 2025-087 Enclosure Page 5 of 10 Fatigue Management - Affected Group: 10 CFR 26.4(a)(4) 10 CFR Position: Maintenance /

Projects Schedule 11/03 to 12/18/2025 26.4(a)(4)

Framatome Projects 12-hour shifts, 6 days on, 1 day off.

Additional days off provided where practicable.

Cumulative average: 57.36 hours4.166667e-4 days <br />0.01 hours <br />5.952381e-5 weeks <br />1.3698e-5 months <br /> per week.

Highest weekly average: 75.00 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

The scope of work for the individuals in this group has been completed, and they are not scheduled for work. Framatome Projects no longer applies to this exemption request.

26.4(a)(4)

Alloy 600 Mitigation Project 12-hour shifts, 6 days on, 1 day off.

Cumulative average: 70.63 hours7.291667e-4 days <br />0.0175 hours <br />1.041667e-4 weeks <br />2.39715e-5 months <br /> per week.

Highest weekly average: 72.28 hours3.240741e-4 days <br />0.00778 hours <br />4.62963e-5 weeks <br />1.0654e-5 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Committed to transitioning into online averaging rules on January 25, 2026, for the remainder of the proposed exemption period.

Updated cumulative average from 11/03 to 12/30/2025: 66.62 hours7.175926e-4 days <br />0.0172 hours <br />1.025132e-4 weeks <br />2.3591e-5 months <br /> per week.

26.4(a)(4)

Mechanical Maintenance 12-hour shifts, 4 days on, 3 days off.

Cumulative average: 48.30 hours3.472222e-4 days <br />0.00833 hours <br />4.960317e-5 weeks <br />1.1415e-5 months <br /> per week.

Highest weekly average: 56.38 hours4.398148e-4 days <br />0.0106 hours <br />6.283069e-5 weeks <br />1.4459e-5 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged

PNP 2025-087 Enclosure Page 6 of 10 Fatigue Management - Affected Group: 10 CFR 26.4(a)(4) 10 CFR Position: Maintenance /

Projects Schedule 11/03 to 12/18/2025 over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 46.18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> per week.

26.4(a)(4)

Electricians 10-hour shifts, 5 days on, 2 days off.

Cumulative average: 51.58 hours6.712963e-4 days <br />0.0161 hours <br />9.589947e-5 weeks <br />2.2069e-5 months <br /> per week.

Highest weekly average: 51.73 hours8.449074e-4 days <br />0.0203 hours <br />1.207011e-4 weeks <br />2.77765e-5 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 49.97 hours0.00112 days <br />0.0269 hours <br />1.603836e-4 weeks <br />3.69085e-5 months <br /> per week.

26.4(a)(4)

Fuel Handling Equipment (FHE) Upgrade Project 12-hour shifts, 6 days on, 1 day off.

Additional days off provided where practicable.

Cumulative average: 61.58 hours6.712963e-4 days <br />0.0161 hours <br />9.589947e-5 weeks <br />2.2069e-5 months <br /> per week.

Highest weekly average: 71.21 hours2.430556e-4 days <br />0.00583 hours <br />3.472222e-5 weeks <br />7.9905e-6 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Committed to transitioning to online averaging rules on February 8, 2026, for the remainder of the proposed exemption period.

Updated cumulative average from 11/03 to 12/30/2025: 54.39 hours4.513889e-4 days <br />0.0108 hours <br />6.448413e-5 weeks <br />1.48395e-5 months <br /> per week.

26.4(a)(4)

Tesco Projects 12-hour shifts, maximum of 6 days on, 1 day off.

Additional days off provided where practicable.

Cumulative average: 58.81 hours9.375e-4 days <br />0.0225 hours <br />1.339286e-4 weeks <br />3.08205e-5 months <br /> per week.

Highest weekly average: 67.56 hours6.481481e-4 days <br />0.0156 hours <br />9.259259e-5 weeks <br />2.1308e-5 months <br /> per week.

PNP 2025-087 Enclosure Page 7 of 10 Fatigue Management - Affected Group: 10 CFR 26.4(a)(4) 10 CFR Position: Maintenance /

Projects Schedule 11/03 to 12/18/2025 Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Committed to transitioning to online averaging rules on February 15, 2026, for the remainder of the proposed exemption period.

Updated cumulative average from 11/03 to 12/30/2025: 51.04 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per week.

26.4(a)(4)

Electrical Maintenance 12-hour shifts, 4 days on, 3 days off, or 5 days on, 2 days off.

Cumulative average: 53.89 hours0.00103 days <br />0.0247 hours <br />1.471561e-4 weeks <br />3.38645e-5 months <br /> per week.

Highest weekly average: 60.87 hours0.00101 days <br />0.0242 hours <br />1.438492e-4 weeks <br />3.31035e-5 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 44.72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> per week.

26.4(a)(4)

Instrumentation and Controls (I&C) Maintenance 12-hour shifts, 4 days on, 3 days off.

Cumulative average: 46.99 hours0.00115 days <br />0.0275 hours <br />1.636905e-4 weeks <br />3.76695e-5 months <br /> per week.

Highest weekly average: 52.04 hours4.62963e-5 days <br />0.00111 hours <br />6.613757e-6 weeks <br />1.522e-6 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 43.22 hours2.546296e-4 days <br />0.00611 hours <br />3.637566e-5 weeks <br />8.371e-6 months <br /> per week.

26.4(a)(4)

Insulators/Ironworkers 10-hour shifts, 5 days on, 2 days off.

Cumulative average: 51.73 hours8.449074e-4 days <br />0.0203 hours <br />1.207011e-4 weeks <br />2.77765e-5 months <br /> per week.

Highest weekly average: 51.73 hours8.449074e-4 days <br />0.0203 hours <br />1.207011e-4 weeks <br />2.77765e-5 months <br /> per week.

Observing a rest and reset period in

PNP 2025-087 Enclosure Page 8 of 10 Fatigue Management - Affected Group: 10 CFR 26.4(a)(4) 10 CFR Position: Maintenance /

Projects Schedule 11/03 to 12/18/2025 which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 50.58 hours6.712963e-4 days <br />0.0161 hours <br />9.589947e-5 weeks <br />2.2069e-5 months <br /> per week.

26.4(a)(4)

Pipefitters 10-hour shifts, 5 days on, 2 days off.

After a very light schedule in the month of November, transitioned into 12-hour shifts with a maximum of 6 days on, 1 day off.

Cumulative average: 26.37 hours4.282407e-4 days <br />0.0103 hours <br />6.117725e-5 weeks <br />1.40785e-5 months <br /> per week.

Highest weekly average: 40.32 hours3.703704e-4 days <br />0.00889 hours <br />5.291005e-5 weeks <br />1.2176e-5 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 25.48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week.

26.4(a)(4)

Boilermakers 10-hour shifts, 5 days on, 2 days off.

Cumulative average: 51.58 hours6.712963e-4 days <br />0.0161 hours <br />9.589947e-5 weeks <br />2.2069e-5 months <br /> per week.

Highest weekly average: 53.56 hours6.481481e-4 days <br />0.0156 hours <br />9.259259e-5 weeks <br />2.1308e-5 months <br /> per week.

Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 50.74 hours8.564815e-4 days <br />0.0206 hours <br />1.223545e-4 weeks <br />2.8157e-5 months <br /> per week.

26.4(a)(4)

Master Lee Projects 8-hour, 10-hour and 12-hour shifts with sufficient days off to effectively mitigate cumulative fatigue.

Cumulative average: 49.83 hours9.606481e-4 days <br />0.0231 hours <br />1.372354e-4 weeks <br />3.15815e-5 months <br /> per week.

Highest weekly average: 53.18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> per week.

PNP 2025-087 Enclosure Page 9 of 10 References

1.

Holtec Palisades, LLC (Holtec Palisades) letter to U.S. Nuclear Regulatory Commission (NRC), Request for Exemption from Requirements of 10 CFR 26.205, "Fitness for Duty Programs - Work Hours," dated August 12, 2025 (ADAMS Accession No. ML25224A206)

2.

NRC letter to Holtec Palisades, Palisades Nuclear Plant - One-Time Exemption from the Requirements of 10 CFR 26.205(d)(3) and (d)(7) (EPID L-2025-LLE-0022), dated October 24, 2025 (ADAMS Accession Nos. ML25293A005 and ML25293A007)

3.

Holtec Palisades letter to NRC, Second Request for Exemption from Requirements of 10 CFR 26.205, "Fitness for Duty Programs - Work Hours," dated December 12, 2025 (ADAMS Accession No. ML25346A199)

4.

NRC email to Holtec Palisades, Request for Additional Information RE: Request for Second Exemption from Part 26 Work Hours (LL-2025-LLE-0032), dated December 22, 2025 Fatigue Management - Affected Group: 10 CFR 26.4(a)(4) 10 CFR Position: Maintenance /

Projects Schedule 11/03 to 12/18/2025 Observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from 12/19/2025 to 01/01/2026.

Updated cumulative average from 11/03 to 12/30/2025: 52.80 hours9.259259e-4 days <br />0.0222 hours <br />1.322751e-4 weeks <br />3.044e-5 months <br /> per week.

Summary As described in the table above, to support the ongoing PNP outage activities and subsequent plant restart, the covered individuals in Group 10 CFR 26.4(a)(4) will be required to work various schedules. All schedules will remain compliant with 10 CFR 26.205(d)(1), (d)(2), and (d)(4). To ensure an adequate reset before continuing outage activities, the individuals in this Group are currently observing a rest and reset period in which no covered individual will work more than 48 hours5.555556e-4 days <br />0.0133 hours <br />7.936508e-5 weeks <br />1.8264e-5 months <br /> per week, averaged over the two-week span from December 19, 2025 through January 1, 2026.

The Group 10 CFR 26.4(a)(4) table includes the scheduled 30-minute shift turnover time as part of the work hour averaging calculation. This is conservative because shift turnover time may be excluded from the calculation of an individual's work hours (

References:

NEI 06-11, Section 8.1, and NRC Regulatory Guide 5.73, Appendix B, page B-11).

PNP 2025-087 Enclosure Page 10 of 10

5.

Holtec Palisades letter to NRC, Request for Additional Information Regarding Second Request for Exemption from Requirements of 10 CFR 26.205, "Fitness for Duty Programs - Work Hours," dated December 26, 2025

Enclosure Attachment PNP 2025-087 List of Regulatory Commitments (1 Page Follows)

List of Regulatory Commitments The table below identifies actions discussed in this letter for which, upon approval, Holtec commits to perform. Any other actions discussed in this submittal are described for U.S.

Nuclear Regulatory Commission (NRC) information and are not commitments.

Commitment Proposed Completion Date

1. Palisades Energy will ensure that covered individuals working on the Alloy 600 project will transition to online averaging rules on January 25, 2026, for the remainder of the proposed exemption period.

01/25/2026

2. Palisades Energy will ensure that covered individuals working on Tesco Projects will transition to online averaging rules on February 15, 2026, for the remainder of the proposed exemption period.

02/15/2026

3. Palisades Energy will ensure that covered individuals working on the FHE project will transition to online averaging rules on February 8, 2025, for the remainder of the proposed exemption period.

02/08/2026