ML25234A196

From kanterella
Jump to navigation Jump to search

Letter Dated August 5, 2025 from Adrian Rony (Edlow) to Dr. Ryan Vierling (Dot), Subject: Request for Priority Review for USA Validation of Japanese NT-XII Package
ML25234A196
Person / Time
Site: 07103104
Issue date: 08/05/2025
From: Rony A
Edlow International Co, Edlow
To: Vierling R
US Dept of Transportation (DOT), Office of Hazardous Materials Safety
References
001942, L-2025-DOT-0001
Download: ML25234A196 (1)


Text

Page 1 of 1 Edlow International Company 1828 L Street, N.W., Suite 404 Washington, D.C. 20036 U.S.A.

Tel: 1 (202) 483-4959 www.edlow.com FMC License No. 019368F August 5, 2025 Dr. Ryan Vierling U.S. Department of Transportation, PHMSA 1200 New Jersey Avenue, S.E.

Washington, D.C. 20590-0001

Subject:

Request for Priority Review for USA Validation of Japanese NT-XII Package

Dear Dr.Vierling,

Edlow International Company respectfully requests prioritization of the NRC review process and subsequent issuance of the DOT revalidation certificate for the Japanese NT-XII package. Our objective is to obtain revalidation no later than December 31, 2025, to support critical project timelines. Please find below our clients proposed schedule and supporting information for your review:

1. Aug 2025: Receipt of RAIs from NRC
2. By the end of Sep: Complete all Q&As regarding RAI from NRC
3. By the end of Oct: NRC submits Safety Evaluation Report to DOT
4. By the end of Dec: Revalidation issued by DOT We understand that the NT-XII revalidation request is a new application and that RAIs, particularly those related to criticality, may require time to address. Close adherence to the above timeline would be greatly appreciated to avoid delays that could impact fuel delivery obligations to Japanese utilities. If any RAIs have already been issued or are forthcoming, we would be grateful to review them at the earliest opportunity We thank you in advance for your assistance and consideration.

Cordially, Adrian Rony Edlow International Company