Schedule Revision for the Subsequent License Renewal Application Review
ML25198A191
Person / Time
Site: Dresden  Constellation icon.png
Issue date: 08/07/2025
From: Michele Sampson
NRC/NRR/DNRL
To: Wilson C
Constellation Energy Company
References
EPID L-2024-SLR-0000, EPID L-2024-SLE-0000
Download: ML25198A191 (1)


Text

.

Christopher D. Wilson Director, License Renewal Constellation Energy Generation, LLC 200 Constellation Way, KSA-3E Kennet Square, PA 19348

SUBJECT:

REVISION OF SCHEDULE FOR THE REVIEW OF THE DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3, SUBSEQUENT LICENSE RENEWAL APPLICATION (EPID NOS. L-2024-SLR-0000 AND L-2024-SLE-0002)

(DOCKET NUMBERS: 50-237 AND 50-249)

Dear Christopher D. Wilson:

By letter dated April 17, 2024 (Agencywide Documents Access and Management System (ADAMS) Package Accession No. ML24108A007), Constellation Energy Generation, LLC (CEG or the applicant) submitted an application for subsequent license renewal of Facility Operating License Nos. DPR-19 and DPR-25 for Dresden Nuclear Power Station, Units 2 and 3 (DNPS),

to the U.S. Nuclear Regulatory Commission (NRC or staff), pursuant to Title 10 of the Code of Federal Regulations Part 54, Requirements for Renewal of Operating Licenses for Nuclear Power Plants.

By letter dated June 14, 2024 (ML24128A274), the staff concluded that the application was acceptable for docketing. By letter dated August 2, 2024 (ML24184A171), the staff issued the staffs projected review schedule for the DNPS license renewal application.

The purpose of this letter is to inform you of changes in the review schedule for the DNPS subsequent license renewal application (SLRA). The revisions reflect several staff efficiencies that have been applied to the environmental and safety reviews since the original schedule was set.

The enclosure of this letter provides the staffs revised projected schedule for the DNPS SLRA review. The staff will strive to meet the milestones ahead of the revised schedule whenever feasible.

Based on the current status of the review and implemented efficiencies, the staff estimates that the review of the SLRA will take approximately 12,200 hours0.00231 days <br />0.0556 hours <br />3.306878e-4 weeks <br />7.61e-5 months <br /> to complete. This reflects an estimate of 6,950 hours0.011 days <br />0.264 hours <br />0.00157 weeks <br />3.61475e-4 months <br /> for the safety review and 5,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> for the environmental review.

These estimates are a reduction from the original estimates of 8,000 for the safety review and 6,000 hours0 days <br />0 hours <br />0 weeks <br />0 months <br /> for the environmental review.

If you have any questions related to this review schedule, please contact Mark Yoo at Mark.Yoo@nrc.gov.

August 7, 2025

C. Wilson Sincerely, Michele Sampson, Director Division of New and Renewed Licenses Office of Nuclear Reactor Regulation Docket Nos. 50-237 and 50-249

Enclosure:

Subsequent License Renewal Application Review Schedule cc w/encl: Listserv Signed by Sampson, Michele on 08/07/25

ML25198A191 via-Econcurrence NRR-106 OFFICE NRR/DNRL/NLRP/PM NRR/DNRL/NLRP/LA NMSS/REFS/EMPB1/PM NAME MYoo KBratcher ASabet DATE 07/17/2025 07/17/2025 07/23/2025 OFFICE NMSS/REFS/EMPB1/

BC NRR/DNRL/NLRP/BC NRR/DNRL/D NAME SKoenick ANeuhausen MSampson DATE 07/23/2025 07/23/2025

Enclosure DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 SUBSEQUENT LICENSE RENEWAL APPLICATION REVIEW SCHEDULE Subsequent License Renewal Application Review Schedule from U.S. Nuclear Regulatory Commission Letter dated August 2, 2024 (ML24184A171)

Milestone Scheduled Receive Subsequent License Renewal Application (SLRA) 04/2024 Publish Federal Register Notice (FRN) - SLRA Availability 04/2024 Publish FRN - Docketing Acceptance/Rejection and Opportunity for Hearing 06/2024 Publish FRN - Notice of Intent to Prepare an Environmental Impact Statement and Conduct Scoping 08/2024 Public Meeting - Overview of Subsequent License Renewal Process and Environmental Scoping 08/2024 Deadline for Filing Hearing Requests and Petitions for Intervention 08/2024 Environmental Scoping Period Ends 09/2024 Issue Draft Supplemental Environmental Impact Statement (SEIS) 06/2025 05/2025 Public Meeting - Draft SEIS Meeting, If Needed TBD Draft SEIS Comment Period Ends 07/2025 Issue Safety Evaluation 09/2025 Issue Final SEIS 10/2025 09/2025 Advisory Committee on Reactor Safeguards Full Committee Meeting 11/2025 U.S. Environmental Protection Agency FRN Published -

Availability of Final SEIS 11/2025 09/2025 Decision - Director, Office of Nuclear Reactor Regulation 12/2025 11/13/2025