April 8, 2025 Technical Specifications Task Force 11921 Rockville Pike, Suite 100 Rockville, MD 20852
SUBJECT:
ACCEPTANCE FOR REVIEW REGARDING TRAVELER TSTF-585, REVISION 4, REVISE LCO 3.0.3 TO REQUIRE MANAGING RISK (EPID: L-2023-PMP-0000)
Dear Members of the Technical Specifications Task Force:
By letter dated March 7, 2025 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25066A098), you submitted a request to the U.S. Nuclear Regulatory Commission (NRC) to incorporate Revision 4 of Traveler TSTF-585, "Revise LCO [Limiting Condition for Operation] 3.0.3 to Require Managing Risk, the standard technical specifications.
Section 170.21 of Title 10 of the Code of Federal Regulations requires that Travelers are subject to fees based on the full cost of the review. You did not request a fee waiver; therefore, NRC staff hours will continue to be billed accordingly. The NRC staff estimates that the review will require approximately 1015 staff hours including hours already charged reviewing previous revisions.
The NRC staff has completed a preliminary review of your submission and determined it is sufficiently complete and appropriate to initiate a more comprehensive review. The review will generally follow the schedule below.
MILESTONE SCHEDULE DATE Issue Draft Safety Evaluation September 17, 2025 Issue Final Safety Evaluation December 19, 2025 If you have any questions, please contact me at (301) 415-1774 or via email to Michelle.Honcharik@nrc.gov.
Sincerely,
/RA/
Michelle C. Honcharik, Senior Project Manager Technical Specifications Branch Division of Safety Systems Office of Nuclear Reactor Regulation Project No. 753 cc: See next page
Technical Specifications Task Force Project No. 753 cc:
Technical Specifications Task Force c/o EXCEL Services Corporation 11921 Rockville Pike, Suite 100 Rockville, MD 20852 Attention: Brian D. Mann Email: brian.mann@excelservices.com Jordan L. Vaughan Duke Energy 525 S. Tryon St.
B0009-037-B Charlotte, NC 28202 Email: jordan.vaughan@duke-energy.com Shane Jurek PSEG Nuclear PO Box 236 Hancocks Bridge, NJ 08038-0221 Email: Shane.Jurek@pseg.com Drew Richards STP Nuclear Operating Company 12090 FM 521 Mail Code: N5016 Wadsworth, TX 77483 Email: amrichards@stpegs.com Rebecca L. Steinman Constellation Energy Generation 4300 Winfield Road Warrenville IL 60555 Email: Rebecca.Steinman@constellation.com
- via email NRR-106 OFFICE NRR/DSS/STSB/BC*
NRR/DSS/STSB/PM*
NAME SMehta MHoncharik DATE 4/8/2025 4/8/2025