H.B. Robinson Steam Electric Plant, Unit 2 Subsequent License Renewal Application (SLRA)
Safety Pre-Application Meeting February 5, 2025 Andrew Siwy Safety Project Manager License Renewal Projects Branch Division of New and Renewed Licenses Office of Nuclear Reactor Regulation
Meeting Agenda
- Subsequent License Renewal Review Process +
Inputs into NRC Licensing Decision
- Safety Review:
o Process Overview o Tentative Review Schedule
- NRC Contact Information
- Conclusion / Questions 2
Subsequent License Renewal Review Process +
Inputs into NRC Licensing Decision Environmental Review (10 CFR 51)
NRC Renewal Decision (10 CFR 54.29)
Subsequent License RenewalApplication (SLRA) Accepted Safety Review (10 CFR 54)
ACRS Recommendation (10 CFR 54.25)
Hearings*
10 CFR 2 3
Safety Review:
Process Overview Issue Safety Evaluation (SE)
Acceptance Review In-Office Technical Review Audit On-SiteAudit BreakoutAudit 4
Tentative Safety Review Schedule 5
Estimated Date Activity April 2025 Application Submission Date May 2025 Acceptance Date (Project Start Date)
May 2025 In-Office Technical Review Audit May 2025 On-Site Audit June 2025 Breakout Audit May 2026 Safety Evaluation Report July 2026 Advisory Committee on Reactor Safeguards (ACRS) Full Committee Meeting October 2026 Licensing Decision Note: The review schedule below is tentative and subject tochange.
The schedule is only finalized once the application has been accepted forreview and docketing.
NRC Contact Information 6
SafetyProjectManager AndrewSiwy(Andrew.Siwy@nrc.gov)
SafetyBranchChief BillRogers(Bill.Rogers@nrc.gov)
EnvironmentalProjectManger KarenLoomis(Karen.Loomis@nrc.gov)
EnvironmentalBranchChief SteveKoenick(Stephen.Koenick@nrc.gov)
Questions?