UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001 Richard W. Boyle, Chief of Research and Development Branch Radioactive Materials Branch U.S. Department of Transportation 1200 New Jersey Avenue SE Washington, D.C. 20590
SUBJECT:
REQUEST FOR REVIEW OF APPLICATION FOR MODEL 880 SERIES PACKAGES - ENTERPRISE PROJECT IDENTIFICATION NUMBER L-2024-LLA-0112
Dear Richard Boyle:
By \
letter dated July 18, 2024 (Agencywide Documents Access and Management System
[ADAMS] Accession No. ML24261B174), as supplemented by QSA Global on November 7, 2024 (ML24331A246), the U.S. Department of Transportation requested that the U.S. Nuclear Regulatory Commission (NRC) staff perform a review of the QSA Global application for issuance of a revision to the Competent Authority Certificate No. USA/9296/B(U)-96, for the Model No. 880 Series transport package and make a recommendation concerning the endorsement of the package to the International Atomic Energy Agency Regulations for the Safe Transport of Radioactive Material, 2018 Edition, No. SSR-6 (Rev. 1).
The NRC staff performed an acceptance review of the application and supplementation to determine if it contains sufficient technical information in scope and depth to allow the staff to complete the detailed technical review. This letter is to advise you that, based on our acceptance review, the application contains sufficient technical information. Based on our preliminary evaluation, our technical review schedule includes the issuance, if needed, of a request for additional information (RAI) by March 3, 2025, and, provided that we receive the responses to the RAIs within 60 days after its issuance, we anticipate issuing our recommendation by July 2025. The NRC staff estimates that completing the review of the application will require approximately 400 staff hours. We will promptly communicate significant schedule changes, if any.
December 6, 2024
R. Boyle 2
In accordance with Title 10 of the Code of Federal Regulations Part 2, Agency Rules of Practice and Procedure, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room (PDR) or from the Publicly Available Records component of the NRCs ADAMS. ADAMS is accessible from the NRC website at http://www.nrc.gov/reading-rm/adams.html. The PDR is open by appointment. To make an appointment to visit the PDR, please send an email to PDR.Resource@nrc.gov or call 1-800-397-4209 or 301-415-4737, between 8 a.m. and 4 p.m. eastern time (ET), Monday through Friday, except Federal holidays.
If you have any questions regarding this communication, please contact me at 301-287-3664, or via e-mail to heath.stroud@nrc.gov.
Sincerely, Heath Stroud, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards Docket No.: 71-9296 License/Certificate No.: 9296 EPID: L-2024-LLA-0112 Signed by Stroud, Heath on 12/06/24
ML24338A266 OFFICE NMSS/DFM NMSS/DFM NMSS/DFM NMSS/DFM NAME HStroud SFigueroa JNguyen for YDiaz-Sanabria HStroud DATE 12/4/2024 12/4/2024 12/6/2024 12/6/2024