Additional Information Report for the Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Environmental Review
ML24319A075
Person / Time
Site: Peach Bottom  Constellation icon.png
Issue date: 11/14/2024
From: Wilson C
Constellation Energy Generation
To:
Office of Nuclear Reactor Regulation, Document Control Desk
Shared Package
ML24319A074 List:
References
RS-24-105
Download: ML24319A075 (1)


Text

200 Energy Way Kennett Square, PA 19348 www.constellation.com RS-24-105 10 CFR 50 10 CFR 51 10 CFR 54 November 14, 2024 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Peach Bottom Atomic Power Station, Units 2 and 3 Subsequent Renewed Facility Operating License Nos. DPR-44 & DPR-56 NRC Docket Nos. 50-277 & 50-278

Subject:

Additional Information Report for the Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Environmental Review

References:

1. Letter from Christopher D. Wilson (Constellation Energy Generation, LLC) to U.S. NRC, Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3, dated June 5, 2024 (ML24157A069)
2. Letter from U.S. NRC to Christopher D. Wilson (Constellation Energy Generation, LLC), Response to Request for Re-Engagement Regarding the Subsequent License Renewal Environmental Review for Peach Bottom Atomic Power Station, Units 2 and 3 (Docket Numbers: 50-0277 and 50-0278), dated September 6, 2024 (ML24221A258)
3. Peach Bottom Atomic Power Station, Units 2 & 3 - Applicants Environmental Report, dated July 10, 2018 (ML18201A219)
4. NUREG-1437, Supplement 10, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Supplement 10, Second Renewal, Regarding Subsequent License Renewal for Peach Bottom Atomic Power Station Units 2 & 3, dated January 31, 2020 (ML20023A937)

In Reference 1, Constellation Energy Generation, LLC (CEG) requested the U.S. Nuclear Regulatory Commission (NRC) provide its plan for re-engagement and completion of the Peach Bottom Atomic Power Station (PBAPS) Units 2 and 3 Subsequent License Renewal (SLR) environmental review and restoration of the end dates for the subsequent periods of extended operations. The NRC provided its plan for completing the required regulatory activities associated with this action in Reference 2.

To complete the SLR environmental review in accordance with 10 CFR 51.92, the NRC is seeking updated information from CEG to include any new and potentially significant information relevant to the previously submitted Environmental Report (ER) (Reference 3) to prepare a supplement to the January 2020 Final Supplemental Environmental Impact Statement (SEIS)

(Reference 4) for PBAPS SLR. Attachment 1 of this letter provides an Additional Information Report to support the NRCs preparation and issuance of the PBAPS Final SEIS supplement.

November 14, 2024 U.S. Nuclear Regulatory Commission Page 2 The enclosed additional information to the PBAPS Units 2 and 3 SLR ER will:

Provide an updated status on the PBAPS Units 2 and 3 permits, licenses, and authorizations.

Provide results of the review of potentially new and significant information since the submittal of the 2018 SLR ER, and the NRCs audit concerning the SLR ER, conducted November 2018, regarding Category 1 issues, and to compare to NUREG-1437, Generic Environmental Impact Statement for License Renewal of Nuclear Plants, Revision 2, Final (GEIS).

Provide review of potentially new and significant information since the submittal of the SLR ER and NRCs audit concerning the SLR ER regarding Category 2 issues contained in the GEIS.

Provide an assessment of applicable new Category 2 environmental issues from the GEIS.

There are no regulatory commitments contained in this letter.

For questions related to this submittal, please contact Hannah Pell, Regulatory Engineer, License Renewal Projects, at 717-599-2436 or via email at hannah.pell@constellation.com.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 14th of November 2024.

Respectfully, Christopher D. Wilson Director, License Renewal Constellation Energy Generation, LLC

- Peach Bottom Atomic Power Station Units 2 and 3 Subsequent License Renewal Environmental Report Additional Information cc:

NRC Director, Division of License Renewal, NRR NRC Senior Environmental Project Manager, NMSS NRC Regional Administrator - Region I NRC Senior Resident Inspector - Peach Bottom Atomic Power Station Director, Bureau of Radiation Protection - Pennsylvania Dept of Environmental Protection Wilson, Christopher D Digitally signed by Wilson, Christopher D Date: 2024.11.14 09:02:25 -05'00'