MONTHYEARML24306A1422024-11-0101 November 2024 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Adopt Alternative Seismic Method for 50.69 Categorization of SSCs ML24262A2232024-09-18018 September 2024 Part Event Notification 57330. Part 21 - Control Relay Defect ML24256A1402024-09-0505 September 2024 Preliminary Data Needs and Agenda to Support the Supplemental Environmental Audit for Point Beach, Units 1 and 2 - File Copy ML24226A6842024-08-13013 August 2024 NRR E-mail Capture - Point Beach, Units 1 and 2 - Acceptance of License Amendment Request to Adopt TSTF-577 ML24215A2092024-08-0101 August 2024 NRR E-mail Capture - Final RAI - Point Beach 1 & 2 - License Amendment Request to Modify Containment Average Air Temperature Requirements ML24199A2142024-07-17017 July 2024 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Modify Containment Average Air Temperature Requirements ML24149A3532024-05-24024 May 2024 Change in Estimated Review Schedule for Nextera Common Emergency Plan Amendment ML24122C6922024-05-0101 May 2024 NextEra Fleet EP Amendment - Demonstration Drill ML24108A1022024-04-17017 April 2024 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Revision to Reactor Vessel Surveillance ML24053A0112024-02-21021 February 2024 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Relief Request CISI-03-01 for Containment Unbonded Post-Tensioning System Inservice Inspection Requirements 3 ML23271A1542023-09-28028 September 2023 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Revise TS 5.5.17, Pre-Stressed Concrete Containment Tendon Surveillance Program ML23208A3072023-07-27027 July 2023 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Relief Requests Regarding I6-RR-1, I6-RR-2, and I6-RR-3 (EPIDs L-2023-LLR-0030, L-2023-LLR-0031, L-2023-LLR-0032) ML23173A1522023-06-22022 June 2023 Request for Additional Information NextEra Fleet Emergency Plan Amendment Request ML23136A2782023-05-0505 May 2023 Email to R Coffey Point Beach SLRA Second Annual Update - Request for Additional Information Set 1 ML23122A0132023-05-0101 May 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding Risk-Informed Approach to Address GSI-191 ML23109A1862023-04-19019 April 2023 And Turkey Point – Acceptance of Requested Licensing Action Proposed Alternative to Asme Section XI Authorizing Implementation of Asme Code Case N-752-1 ML23033A0292023-01-31031 January 2023 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI (Volume 2) - License Amendment Request Regarding TSTS-505 ML22354A1612022-12-20020 December 2022 NRR E-mail Capture - Point Beach 1 & 2 - Final RAI - License Amendment Request Regarding TSTS-505 ML22291A3692022-10-18018 October 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment Request to Use Beacon Power Distribution Monitoring System ML22249A0052022-09-0202 September 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of License Amendment and Exemptions Regarding Risk-Informed Approach to Address GSI-191 ML22229A1052022-08-17017 August 2022 Response to Questions Regarding Point Beach Nuclear Power Plant with Attachment ML22229A1022022-07-18018 July 2022 Original Request - Questions Regarding Point Beach Nuclear Power Plant ML22196A0062022-07-15015 July 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - RITSTF Initiative 4b ML22094A0802022-04-0404 April 2022 NRR E-mail Capture - Point Beach Nuclear Plant, Units 1 and 2 - Acceptance of Requested Licensing Action License Amendment Request to Adopt TSTF-366 ML22006A2762022-01-0606 January 2022 SLR - FW: Subsequent License Renewal of Point Beach Nuclear Plant Unit Numbers 1 and 2, Manitowoc County, Wisconsin ML22006A2012022-01-0606 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22006A1952022-01-0606 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments Nrc’S Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22004A3202022-01-0404 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments Nrc’S Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22004A0012022-01-0404 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22004A3212022-01-0404 January 2022 SLR - FW: Comments of Michael J Keegan on Dseis Point Beach ML22004A1732022-01-0404 January 2022 SLR - FW: (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments Nrc’S Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, D ML22006A1942022-01-0404 January 2022 SLR - (External_Sender) 3 Additional Organizations Endorsing the Coalition (Now 50 Organizations, and 27 Individuals) Public Comments Nrc’S Dsgeis on NextEra Point Beach Nuclear Power Plant Subsequent License Renewal, Docke ML22004A3192022-01-0404 January 2022 SLR - FW: Point Beach ML22004A3182022-01-0404 January 2022 SLR - FW: EPA Comment Letter - Point Beach SEIS ML22004A1672022-01-0404 January 2022 SLR - Ref: Point Beach ML22006A1992022-01-0303 January 2022 SLR - (External_Sender) Comments of Michael J Keegan on Dseis Point Beach ML22004A3172021-12-21021 December 2021 SLR - (External_Sender) EPA Comment Letter - Point Beach SEIS ML21362A6822021-12-17017 December 2021 SLRA Safety RAIs Set 14 Final Email ML21362A6712021-12-15015 December 2021 SLRA Safety RAIs Set 13 Final Email ML22006A2752021-12-0202 December 2021 SLR - (External_Sender) Subsequent License Renewal of Point Beach Nuclear Plant Unit Numbers 1 and 2, Manitowoc County, Wisconsin ML21341A6102021-11-16016 November 2021 SLRA Safety RAI Set 12 Final Email ML21314A4212021-11-10010 November 2021 Fws to NRC, Concurrence with ESA Determination for Point Beach Subsequent License Renewal ML21307A1522021-11-0909 November 2021 NRC to Fws, Request for Concurrence with Endangered Species Act Determinations for Point Beach Subsequent License Renewal ML21287A0852021-10-14014 October 2021 SLRA Safety RAI Set 11 Final Email ML21286A6032021-10-0505 October 2021 SLRA Safety RAIs Set 10 Final Email ML21279A1202021-10-0505 October 2021 Email: Wi SHPO Review Point Beach Nuclear Plant SLR ML21273A0232021-09-0202 September 2021 SLRA Safety RAI Set 9 Final Email ML21242A2292021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 Email ML21242A2282021-08-27027 August 2021 SLRA Draft Safety RAI Set 9 ML21242A2462021-08-26026 August 2021 SLRA Safety RAIs Set 8 Final Email 2024-09-05
[Table view] |
Text
From: Murrell, Bob To: Hoc, HOO X
Subject:
[External_Sender] Point Beach Part Event Notification#57330 Date: Wednesday, September 18, 2024 1:35:52 PM
Here is the wording from the EN for Point Beach.
Part 21 - CONTROL RELAY DEFECT
NextEra Energy Point Beach, LLC (NextEra) makes the following notification under 10 CFR 21.21(d)(3)(i) of a defect found in a Westinghouse relay, model NBFD31S, during pre-installation bench testing. Specifically, the relay was found to not function as required due to its internal plunger not operating properly. This malfunctioning caused the plunger to not fully extend and cause the normally open contacts to remain closed. Investigations completed by Westinghouse determined that the plunger would not function properly because its kickout spring was misaligned due to human error. This relay was procured from Westinghouse for safety related nuclear applications.
NextEra has concluded that this defect constitutes a Substantial Safety Hazard (SSH). An SSH exists because of the nature of the defect was such that the relay would not be able to perform its safety function, if installed, and would result in a loss of redundancy in a safety related system, in this case, the Reactor Protection System.
On September 17, 2024, the Point Beach Site Vice President was notified of the requirement to report this event under 10 CFR 21.21. This is a non-emergency notification required by 10 CFR 21.21(d)(3)(i). A written notification in accordance with 10 CFR 21.21(d)(3(ii) will be provided within 30 days.
Since this defect was discovered prior to installation, in accordance with station requirements for bench testing, and the vendor has concluded that this event is an isolated case, there were no actual impacts on Safety Related equipment.
The NRC Resident Inspector has been notified.