From:
Adrian Muniz To:
Jessica Maddocks Cc:
Maggie Staiger
Subject:
Completeness determination - X-energy"s Training Programs Methodology Topical Report Date:
Wednesday, April 24, 2024 3:57:00 PM Attachments:
NRC Form 898 Topical Report Completeness Determination - X-energy Training Programs Topical Report.pdf
- Jessica,
Attached is the U.S. Nuclear Regulatory Commission (NRC) staff completeness determination for X-energys Training Programs Methodology topical report. The NRC staff determined that it provided sufficient information for the NRC staff to begin a detailed technical review.
As discussed, the NRC staff plans to issue its draft safety evaluation by April 15, 2025. If needed, the NRC staff will issue a request for additional information (RAI) by November 4, 2024, with a request for X-energy to provide a response within 30 days. The NRC staff estimates that 250 staff hours will be needed to complete the technical review and issue the safety evaluation. The schedule and level of effort could change due to several factors (e.g., the need for additional RAIs, unanticipated changes to the scope of the review, and unsolicited supplements to the topical report). The NRC staff will communicate any significant changes to the review schedule or estimated staff hours, including the reason(s) for the changes.
If you have any questions, please feel free to contact me at 301-415-4093 or by email at Adrian.Muniz@nrc.gov.
Project No.: 99902071 EPID: L-2024-TOP-0008
- Regards,
Adrian Muniz, Senior Project Manager Advanced Reactor Licensing Branch 2 (UAL2)
Division of Advanced Reactors and Non-Power Production and Utilization Facilities (DANU)