Letter Sequence Supplement |
---|
|
|
MONTHYEARCP-202300474, (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-02-28028 February 2024 (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program Project stage: Request CP-202400092, (CPNPP) - Supplement to Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-04-0101 April 2024 (CPNPP) - Supplement to Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program Project stage: Supplement ML24177A2692024-08-0707 August 2024 Issuance of Amendment Nos. 188 and 188, Respectively, Revision to Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program Project stage: Approval 2024-04-01
[Table View] |
|
---|
Category:Letter type:CP
MONTHYEARCP-202400335, License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel2024-09-12012 September 2024 License Amendment Request to Adopt TSTF-51, TSTF-471, and TSTF-571-T to Eliminate Use of the Term Core Alterations and Revise Requirements During Handling of Irradiated Fuel CP-202400294, (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule2024-08-15015 August 2024 (CPNPP) - Response to RAI for Exemption Request from 10 CPR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202400319, (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-13013 August 2024 (CPNPP) - Revision to CPNPP Letter to the NRC, Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality CP-202400315, (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality2024-08-0505 August 2024 (Cpnpp), Multiple Relief Requests for Unit 2 Third Ten-Year Inservice Inspection Interval from 10CFR50.55(a) Inspection Requirements Due to Impracticality CP-202400253, (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 52024-06-26026 June 2024 (Cpnpp), Units 1 & 2 Inservice Testing Plan for Pumps & Valves Third Interval, Revision 5 CP-202400235, (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 02024-06-18018 June 2024 (Cpnpp), Units 1 & 2, Inservice Testing Plan for Pumps & Valves Fourth Interval, Revision 0 CP-202400205, (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval2024-05-30030 May 2024 (Cpnpp), Units 1and 2, Submittal of the Snubber Inservice Program Plan for the Fourth Ten Year Interval CP-202400175, (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator2024-05-16016 May 2024 (CPNPP) - Supplement to License Amendment Request to Extend the Allowed Outage Time for an Inoperable Emergency Diesel Generator CP-202400153, (Cpnpp), Registration of Dry Spent Fuel Storage Canisters2024-04-29029 April 2024 (Cpnpp), Registration of Dry Spent Fuel Storage Canisters CP-202400107, (CPNPP) - 2023 Annual Radiological Environmental Operating Report2024-04-18018 April 2024 (CPNPP) - 2023 Annual Radiological Environmental Operating Report CP-202400099, (CPNPP) - Registration of Dry Spent Fuel Storage Canisters2024-04-0909 April 2024 (CPNPP) - Registration of Dry Spent Fuel Storage Canisters CP-202400092, (CPNPP) - Supplement to Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-04-0101 April 2024 (CPNPP) - Supplement to Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program CP-202400089, Property Damage Insurance2024-03-25025 March 2024 Property Damage Insurance CP-202400087, (CPNPP) - Notification of Deviation from Electric Power Research Institute (EPRI) MRP 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in Non-Isolatable2024-03-21021 March 2024 (CPNPP) - Notification of Deviation from Electric Power Research Institute (EPRI) MRP 2019-008, Interim Guidance for NEI 03-08 Needed Requirements for Us PWR Plants for Management of Thermal Fatigue in Non-Isolatable CP-202400085, (CPNPP) - Revised Requested Compliance Date - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2024-03-0707 March 2024 (CPNPP) - Revised Requested Compliance Date - Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation CP-202400073, (CPNPP) - Response to RAI for License Amendment Request to Extend Allowed Outage Time for an Inoperable Emergency Diesel Generator2024-03-0404 March 2024 (CPNPP) - Response to RAI for License Amendment Request to Extend Allowed Outage Time for an Inoperable Emergency Diesel Generator CP-202400072, (Cpnpp), Unit 1, Special Report 1-SR-24-001-00, Inoperable Post Accident Monitoring Instrumentation2024-02-29029 February 2024 (Cpnpp), Unit 1, Special Report 1-SR-24-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300470, (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown2024-02-28028 February 2024 (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown CP-202300474, (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program2024-02-28028 February 2024 (Cpnpp), Application to Revise Technical Specifications to Adopt TSTF-591, Revise Risk Informed Completion Time (RICT) Program CP-202300502, Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions2024-02-23023 February 2024 Notice of Planned Closing of Transaction and Provision of Documents to Satisfy Order Conditions CP-202400063, (CPNPP) - Inservice Inspection (ISI) Owners Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 23 (1RF23)2024-02-12012 February 2024 (CPNPP) - Inservice Inspection (ISI) Owners Activity Reports (OAR-1 Forms) for Unit 1 Refueling Outage 23 (1RF23) CP-202400030, License Renewal Application Revision 0 - Supplement 3, Revision 12024-01-31031 January 2024 License Renewal Application Revision 0 - Supplement 3, Revision 1 CP-202400034, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1)2024-01-29029 January 2024 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 1) CP-202300575, (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 22023-12-13013 December 2023 (Cpnpp), License Amendment Request to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors Supplement 2 CP-202300566, (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation2023-12-12012 December 2023 (Cpnpp), Special Report 1-SR-23-001-00, Inoperable Post Accident Monitoring Instrumentation CP-202300494, License Renewal Application Revision 0, Supplement 32023-12-0606 December 2023 License Renewal Application Revision 0, Supplement 3 CP-202300349, License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation2023-11-20020 November 2023 License Amendment Request (Lar) 23-004 Technical Specifications (TS) 3.9.3, Nuclear Instrumentation CP-202300416, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-10-12012 October 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300432, Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 42023-10-0404 October 2023 Response to Request for Additional Information Regarding the Safety Review of the License Renewal Application - Set 4 CP-202300442, (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program2023-09-15015 September 2023 (CPNPP) - Request to Use Later Code Edition for Inservice Inspection (ISI) Program CP-202300391, (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule2023-08-24024 August 2023 (CPNPP) - Request for Exemption from 10 CFR 50.71(e)(4) Final Safety Analysis Update Schedule CP-202300411, (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20)2023-08-17017 August 2023 (Cpnpp), Inservice Inspection (ISI) Owner'S Activity Reports (OAR-1 Forms) for Unit 2 Refueling Outage 20 (2RF20) CP-202300361, (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report2023-08-17017 August 2023 (CPNPP) - Unit 2 Refueling Outage 20 (2RF20) Steam Generator 180 Day Report CP-202300401, 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 0182023-08-15015 August 2023 10CFR50.59 Evaluation Summary Report 024, 10CFR72.48 Evaluation Summary Report 009, and Commitment Material Change Evaluation Report 018 CP-202300358, (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 1122023-08-0101 August 2023 (Cpnpp), Transmittal of Electronic Licensing Basis Documents Including Certified FSAR Amendment 112 CP-202300322, Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 32023-07-27027 July 2023 Response to Requests for Additional Information Regarding Review of the License Renewal Application Sets 2 and 3 CP-202300348, (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48)2023-07-18018 July 2023 (Cpnpp), Transmittal of Revised Emergency Plan (Revision 48) CP-202300285, Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 12023-07-12012 July 2023 Response to Request for Additional Information Regarding Review of the License Renewal Application - Set 1 CP-202300262, Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 22023-06-20020 June 2023 Response to Request for Confirmation of Information Regarding Review of the License Renewal Application - Set 2 CP-202300263, Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements2023-06-15015 June 2023 Supplemental Information to Facilitate Acceptance of Licensee Amendment Request 23-002, Application Regarding GDC-5 Shared System Requirements CP-202300248, Response to Request for Additional Information Regarding License Renewal Application - Set 12023-06-13013 June 2023 Response to Request for Additional Information Regarding License Renewal Application - Set 1 CP-202300209, Response to Request for Additional Information - License Renewal Application Environmental Review2023-06-0606 June 2023 Response to Request for Additional Information - License Renewal Application Environmental Review CP-202300207, Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-052023-05-25025 May 2023 Revision to Comanche Peak Nuclear Power Plant'S Response to Notice of Violation (NOV) 05000445/2021011-05 CP-202300182, Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application2023-05-0808 May 2023 Response to Requests for Confirmation of Information Regarding the Environmental Review of the License Renewal Application CP-202300201, (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0)2023-05-0404 May 2023 (CPNPP) - Core Operating Limits Report (Colr), Unit 2 Cycle 21, (ERX-23-001, Revision 0) CP-202300160, (Cpnpp), 2022 Annual Radiological Environmental Operating Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Environmental Operating Report CP-202300159, (Cpnpp), 2022 Annual Radiological Effluent Release Report2023-04-27027 April 2023 (Cpnpp), 2022 Annual Radiological Effluent Release Report CP-202300165, License Renewal Application Revision 0 - Supplement 22023-04-24024 April 2023 License Renewal Application Revision 0 - Supplement 2 CP-202300175, Submittal of 2022 Annual Environmental Operating Report (Non-Radiological)2023-04-20020 April 2023 Submittal of 2022 Annual Environmental Operating Report (Non-Radiological) CP-202300181, ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments2023-04-20020 April 2023 ISFSI, Beaver Valley, Units 1 and 2, ISFSI, Davis-Besse, Unit 1, ISFSI, Perry, Unit 1, ISFSI, Corrected Affidavit for Application for Order Consenting to Transfer of Licenses and Conforming License Amendments 2024-09-12
[Table view] |
Text
Comanche Peak Nuclear Power Plant Jay Lloyd Vice President Nuclear Engineering P.O. Box 1002 6322 North FM 56 Glen Rose, TX 76043
CP-202400092 TXX-24019 April 1, 2024
ATTN: Document Control Desk Ref 10 CFR 50.90 U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
Comanche Peak Nuclear Power Plant (CPNPP)
Docket Nos. 50-445 and 50 -446
Subject:
Supplement to Application to Revise Technical Specifications to Adopt TSTF-591, "Revise Risk Informed Completion Time (RICT) Program"
References:
- 1. Letter, J. Lloyd to NRC, "Application to Revise Technical Specifications to Adopt TSTF-591,
"Revise Risk Informed Completion Time (RICT) Program "," February 28, 2024, ML24059A390.
2. Letter, TSTF to NRC, "Correction of TSTF-591, Revision 0, "Revise the Risk Informed Completion Time (RICT) Program. ", " March 22, 2024, TSTF-24-03.
Dear Sir or Madam :
By Reference 1, Vistra Operations Company LLC (Vistra OpCo) requested adoption of TSTF-591, "Revise Risk Informed Completion Time (RICT) Program," which is an approved change to the Standard Technical Specifications (STS), into the CPNPP Units 1 and 2 Technical Specifications (TS). After submittal of Reference 1, Vistra OpCo was made aware of an error in TSTF-591 related to the provided TS mark-up. To address this error as recommended in Reference 2, Vistra OpCo submits the following attachments on a replacement page bases as a supplement to Reference 1. Attachment 1 provides replacement TS mark-up pages. Attachment 2 provides replacement revised (clean) TS pages.
This communication contains no new commitments regarding CPNPP Units 1 and 2.
Should you have any questions, please contact Nie Boehmisch at (254) 897-5064 or nicholas.boehmisch@luminant.com.
I state under penalty of perjury that the foregoing is true and correct. Executed on April 1, 2024.
Sincerely,
Jay Lloyd
Attachments: 1. Proposed Technical Specification Changes (Mark-Up)
- 2. Revised Technical Specification Pages
6555 SIERRA DRIVE IRVING, TEXAS 75039 o 214-812-4600 VISTRACORP.COM TXX-24019 Page 2 of 2
cc:
NRC Regional Administrator, Region IV NRC Project Manager, CPNPP NRC Senior Resident Inspector, CPNPP NRC Resident Inspector, CPNPP Attachment 1 to TXX-24019
Proposed Technical Specification Changes (Mark-Up)
No Changes. For Information Only. Programs and Manuals 5.5
5.5 Programs and Manuals
5.5.23 Risk Informed Completion Time Program
This program provides controls to calculate a Risk Informed Completion Time (RICT) and must be implemented in accordance with NEI 06-09-A, Revision 0, "Risk-Managed Technical Specifications (RMTS) Gu idelines." The program shall include the following:
- a. The RICT may not exceed 30 days;
- b. A RICT may only be utilized in MODE 1 and 2;
- c. When a RICT is being used, any change to the plant configuration, as define d in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
- 1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
- 2. For emergent conditions, the revised RICT must be determined with in the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
- 3. Revising the RICT is not required if the plant configuration chang e would lower plant risk and would result in a longer RICT.
- d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceed ing the Completion Time, the RICT shall ac count for the increased possibility of common cause failure (CCF) by either:
- 1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
- 2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, an d, if practicable, reduce the frequency of initiating events that challenge th e function(s) performed by the inoperable SSCs.
COMANCHE PEAK - UNITS 1 AND 2 5.5-18Amendment No. 183 Programs and Manuals 5.5
5.5 Programs and Manuals
5.5.23 Risk Informed Completion Time Program (continued)
- e. The risk assessment approaches and methods shall be acceptable to the NRC. The plant PRA shall be based on the as-built, as-operated, and maintained plant; and reflect the operating experience at the plant, as specified in Regulatory Guide 1.200, Revision 2. Methods to assess the risk from extending the Completion Times must be PRA methods approved for use with this program, or other methods approved by the NRC for generic use; and any change in the PRA methods to assess risk that are outside these approval boundaries require prior NRC approval.
- e. A RICT calculation must include the following hazard groups: Internal flood and internal events PRA model, internal fire PRA model, seismic penalty factor, and extreme winds and tornado penalty factor. Changes to these means of assessing the hazard groups require prior NRC approval.
- f. The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities."
- g. A report shall be submitted in accordance with Specification 5.6.10 before a newly developed method is used to calculate a RICT.
COMANCHE PEAK - UNITS 1 AND 2 5.5-19Amendment No. 183 Reporting Requirements 5.6
5.6 Reporting Requirements
5.6.9 Steam Generator Tube Inspection Report (continued)
- d. An analysis summary of the tube integr ity conditions predicted to exist at the next scheduled inspection (the forward-looking tube integrity assessment) relative to the applicable performance criteria, including the analysis methodology, inputs, and results;
- e. The number and percentage of tubes plugged to date, and the effective plugging percentage in each SG;
- f. The results of any SG secondary side inspections;
- g. For Unit 2, the primary to secondary leakage rate observed in each SG (if it is not practical to assign the leakage to an individual SG, the entire primary to secondary leakage should be conservatively assumed to be from one SG) during the cycle preceding the inspecti on which is the subject of the report;
- h. For Unit 2, the calculated accident induced leakage rate from the portion of the tubes below 14.01 inches from the top of the tubesheet for the most limiting accident in the most limiting SG. In addition, if the calculated accident induced leakage rate from the most limiting accident is less than 3.16 times the maximum operational primary to secondary leakage rate, the report should describe how it was determined; and
- i. For Unit 2, the results of monitoring for tube axial displacement (slippage). If slippage is discovered, the implications of the discovery and corrective action shall be provided.
5.6.10 Risk Informed Completion Time (RICT) Program Upgrade Report
A report describing newly developed methods and their implementation must be submitted following a probabilistic risk assessment (PRA) upgrade associated with newly developed methods and prior to the first use of those methods to calculate a RICT. The report shall include:
- a. The PRA models upgraded to include newly developed methods;
- b. A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
- c. Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and
- d. All changes to key assumptions related to newly developed methods or their implementation.
COMANCHE PEAK - UNITS 1 AND 2 5.6-6Amendment No. 158, 182 Attachment 2 to TXX-24019
Revised Technical Specification Pages
No Changes. For Information Only. Programs and Manuals 5.5
5.5 Programs and Manuals
5.5.23 Risk Informed Completion Time Program
This program provides controls to calculate a Risk Informed Completion Time (RICT) and must be implemented in accordance with NEI 06-09-A, Revision 0, "Risk-Managed Technical Specifications (RMTS) Gu idelines." The program shall include the following:
- a. The RICT may not exceed 30 days;
- b. A RICT may only be utilized in MODE 1 and 2;
- c. When a RICT is being used, any change to the plant configuration, as defined in NEI 06-09-A, Appendix A, must be considered for the effect on the RICT.
- 1. For planned changes, the revised RICT must be determined prior to implementation of the change in configuration.
- 2. For emergent conditions, the revised RICT must be determined with in the time limits of the Required Action Completion Time (i.e., not the RICT) or 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> after the plant configuration change, whichever is less.
- 3. Revising the RICT is not required if the plant configuration change would lower plant risk and would result in a longer RICT.
- d. For emergent conditions, if the extent of condition evaluation for inoperable structures, systems, or components (SSCs) is not complete prior to exceeding the Completion Time, the RICT shall ac count for the increased possibility of common cause failure (CCF) by either:
- 1. Numerically accounting for the increased possibility of CCF in the RICT calculation; or
- 2. Risk Management Actions (RMAs) not already credited in the RICT calculation shall be implemented that support redundant or diverse SSCs that perform the function(s) of the inoperable SSCs, an d, if practicable, reduce the frequency of initiating events that challenge the function(s) performed by the inoperable SSCs.
COMANCHE PEAK - UNITS 1 AND 2 5.5-18Amendment No. 183 Programs and Manuals 5.5
5.5 Programs and Manuals
5.5.23 Risk Informed Completion Time Program (continued)
- e. A RICT calculation must include the following hazard groups: Internal flood and internal events PRA model, internal fire PRA model, seismic penalty factor, and extreme winds and tornado penalty factor. Changes to these means of assessing the hazard groups require prior NRC approval.
- f. The PRA models used to calculate a RICT shall be maintained and upgraded in accordance with the processes endorsed in the regulatory positions of Regulatory Guide 1.200, Revision 3, "Acceptability of Probabilistic Risk Assessment Results for Risk-Informed Activities."
- g. A report shall be submitted in accordance with Specification 5.6.10 before a newly developed method is used to calculate a RICT.
COMANCHE PEAK - UNITS 1 AND 2 5.5-19Amendment No. 183 Reporting Requirements 5.6
5.6 Reporting Requirements
5.6.9 Steam Generator Tube Inspection Report (continued)
- d. An analysis summary of the tube integr ity conditions predicted to exist at the next scheduled inspection (the forward-looking tube integrity assessment) relative to the applicable performance criteria, including the analysis methodology, inputs, and results;
- e. The number and percentage of tubes plugged to date, and the effective plugging percentage in each SG;
- f. The results of any SG secondary side inspections;
- g. For Unit 2, the primary to secondary leakage rate observed in each SG (if it is not practical to assign the leakage to an individual SG, the entire primary to secondary leakage should be conservatively assumed to be from one SG) during the cycle preceding the inspecti on which is the subject of the report;
- h. For Unit 2, the calculated accident induced leakage rate from the portion of the tubes below 14.01 inches from the top of the tubesheet for the most limiting accident in the most limiting SG. In addition, if the calculated accident induced leakage rate from the most limiting accident is less than 3.16 times the maximum operational primary to secondary leakage rate, the report should describe how it was determined; and
- i. For Unit 2, the results of monitoring for tube axial displacement (slippage). If slippage is discovered, the implications of the discovery and corrective action shall be provided.
5.6.10 Risk Informed Completion Time (RICT) Program Upgrade Report
A report describing newly developed methods and their implementation must be submitted following a probabilistic risk assessment (PRA) upgrade associated with newly developed methods and prior to the first use of those methods to calc ulate a RICT. The report shall include:
- a. The PRA models upgraded to include newly developed methods;
- b. A description of the acceptability of the newly developed methods consistent with Section 5.2 of PWROG-19027-NP, Revision 2, "Newly Developed Method Requirements and Peer Review;"
- c. Any open findings from the peer-review of the implementation of the newly developed methods and how those findings were dispositioned; and
- d. All changes to key assumptions related to newly developed methods or their implementation.
COMANCHE PEAK - UNITS 1 AND 2 5.6-6Amendment No. 158, 182