CNL-23-052, Application to Adopt TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System Operability
| ML24009A170 | |
| Person / Time | |
|---|---|
| Site: | Watts Bar |
| Issue date: | 01/09/2024 |
| From: | Hulvey K Tennessee Valley Authority |
| To: | Office of Nuclear Reactor Regulation, Document Control Desk |
| References | |
| CNL-23-052 | |
| Download: ML24009A170 (1) | |
Text
1101 Market Street, Chattanooga, Tennessee 37402 CNL-23-052 January 9, 2024 10 CFR 50.90 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Units 1 and 2 Facility Operating License Nos. NPF-90 and NPF-96 NRC Docket Nos. 50-390 and 50-391
Subject:
Application to Adopt TSTF-427-A, Revision 2, "Allowance for Non-Technical Specification Barrier Degradation on Supported System OPERABILITY"
References:
- 1. TSTF-427-A, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System OPERABILITY, dated May 3, 2006 (ML061240055) 2.
Notice of Availability of Model Application Concerning Technical Specification Improvement to Modify Requirements Regarding the Addition of LCO 3.0.9 on the Unavailability of Barriers Using the Consolidated Line Item Improvement Process, dated October 3, 2006 (71 Fed. Reg. 58444)
In accordance with the provisions of Section 50.90 of Title 10 of the Code of Federal Regulations (10 CFR), Tennessee Valley Authority (TVA) is submitting a request for an amendment to the Technical Specifications (TS) for Watts Bar Nuclear Plant (WBN), Units 1 and 2. The proposed amendment would modify TS requirements for unavailable barriers by adding Limiting Condition for Operation (LCO) 3.0.9. The proposed changes are consistent with Nuclear Regulatory Commission (NRC) approved Technical Specification Task Force (TSTF) Standard Technical Specification change, TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System OPERABILITY, dated May 3, 2006 (Reference 1). The availability of this TS improvement was announced in the Federal Register on October 3, 2006 (71 FR 58444) as part of the consolidated line item improvement process (CLllP) (Reference 2). provides a description of the proposed change, the requested confirmation of applicability, and plant-specific variations. Attachment 1 to the enclosure provides the existing WBN Unit 1 TS pages marked up to show the proposed changes. Attachment 2 to the
U.S. Nuclear Regulatory Commission CNL-23-052 Page 2 January 9, 2024 enclosure provides the existing WBN Unit 2 TS pages marked up to show the proposed changes. Attachment 3 to the enclosure provides the existing WBN Units 1 and 2 TS Bases pages marked up to show the proposed changes. Changes to the existing TS Bases are provided for information only and will be implemented under the TS Bases Control Program.
TVA requests that the amendment be reviewed under the CLIIP. Approval of the proposed amendment is requested within six months of completion of the NRCs acceptance review.
Once approved, the amendment shall be implemented within 120 days.
TVA has determined that there are no significant hazards considerations associated with the proposed change and that the TS change qualifies for a categorical exclusion from environmental review pursuant to the provisions of 10 CFR 51.22(c)(9). In accordance with 10 CFR 50.91(b)(1), TVA is sending a copy of this letter and enclosures to the Tennessee State Department of Environment and Conservation.
contains the new regulatory commitments associated with this submittal. Please address any questions regarding this request to Stuart L. Rymer, Senior Manager, Fleet Licensing, at slrymer@tva.gov.
I declare under penalty of perjury that the foregoing is true and correct. Executed on this 9th day of January 2024.
Respectfully, Kimberly D. Hulvey Director, Nuclear Regulatory Affairs
Enclosures:
- 1. Description and Assessment
- 2. Summary of Commitments cc: (Enclosures):
NRC Regional Administrator - Region II NRC Senior Resident Inspector - Watts Bar Nuclear Plant NRC Project Manager - Watts Bar Nuclear Plant Director of Radiological Health - Tennessee Department of Environment and Conservation Digitally signed by Edmondson, Carla Date: 2024.01.09 05:31:28 -05'00' CNL-23-052 E1 1 of 3 Description and Assessment
Subject:
License Amendment Request for Application to Adopt TSTF-427-A, Revision 2, Allowance for Non Technical Specification Barrier Degradation on Supported System OPERABILITY CONTENTS
1.0 DESCRIPTION
................................................................................................................... 2
2.0 ASSESSMENT
................................................................................................................... 2 2.1 Applicability of Published Safety Evaluation.................................................................. 2 2.2 Optional Changes and Variations.................................................................................. 2
3.0 REGULATORY ANALYSIS
................................................................................................ 2 3.1 No Significant Hazards Consideration Analysis............................................................ 2 3.2 Verification and Commitments...................................................................................... 3 4.0 ENVIRONMENTAL EVALUATION.................................................................................... 3
5.0 REFERENCES
................................................................................................................... 3 Attachments:
- 1. Proposed TS Changes (Mark-Ups) for WBN Unit 1
- 2. Proposed TS Changes (Mark-Ups) for WBN Unit 2
- 3. Proposed TS Bases Page Changes (Mark-Ups) for WBN Units 1 and 2 (For Information Only)
CNL-23-052 E1 2 of 3
1.0 DESCRIPTION
The proposed amendment would modify Watts Bar Nuclear Plant (WBN), Units 1 and 2, Technical Specification (TS) requirements for unavailable barriers by adding Limiting Condition for Operation (LCO) 3.0.9. The proposed changes are consistent with Nuclear Regulatory Commission (NRC) approved Technical Specification Task Force (TSTF) Standard Technical Specification change, TSTF-427-A, Revision 2, Allowance for Non-Technical Specification Barrier Degradation on Supported System OPERABILITY, dated May 3, 2006. The availability of this TS improvement was announced in the Federal Register on October 3, 2006 (71 FR 58444) as part of the consolidated line item improvement process (CLllP).
2.0 ASSESSMENT
2.1 Applicability of Published Safety Evaluation Tennessee Valley Authority (TVA) has reviewed the safety evaluation (71 FR 58444) dated October 3, 2006 as part of the CLllP. This included a review of the NRC staffs evaluation, as well as information provided to support TSTF-427. TVA has concluded that the justifications presented in the TSTF-427 proposal and the safety evaluation prepared by the NRC staff are applicable to WBN Units 1 and 2, and justify this amendment for the incorporation of the changes to the WBN Units 1 and 2 TS.
The TVA Probabilistic Risk Assessment (PRA) Applications group has reviewed the PRA conclusions in the NRC Safety Evaluation (SE). While the initiating event frequencies in the SE do not in all cases bound the WBN PRA initiating event frequencies, a WBN-specific analysis was developed using the NRCs process, and the results indicate that WBNs risk for a 30-day barrier unavailability falls in the very low risk category of Regulatory Guide (RG) 1.174.
Therefore, the NRCs generic risk conclusions are applicable to WBN Units 1 and 2.
2.2 Optional Changes and Variations TVA is not proposing any variations or deviations from the TS changes described in the TSTF-427 Revision 2 or the NRC staffs model safety evaluation dated October 3, 2006.
The mark-up of the TS Bases associated with LCO 3.0.9 as presented in TSTF-427, is included in Attachment 3 for information purposes. The LCO 3.0.9 Bases in TSTF-427 indicate that risk assessments will be conducted using the procedures and guidance endorsed by RG 1.182, Assessing and Managing Risk Before Maintenance Activities at Nuclear Power Plants. In the Federal Register dated November 27, 2012 (77 FR 70846), the NRC provided notice that RG 1.182 had been withdrawn and the subject matter had been incorporated into RG 1.160, Monitoring the Effectiveness of Maintenance at Nuclear Power Plants. The TSTF issued a letter (Reference 1) noting which approved TSTF travelers are affected and described the effect of withdrawal of RG 1.182. An NRC letter (Reference 2) endorsed the TSTF's approach in the handling of future license amendment requests. As such, TVA is referencing RG 1.160 in the TS Bases associated with this amendment request.
3.0 REGULATORY ANALYSIS
3.1 No Significant Hazards Consideration Analysis CNL-23-052 E1 3 of 3 Tennessee Valley Authority (TVA) has reviewed the proposed no significant hazards consideration determination (NSHCD) published in the Federal Register as part of the CLllP.
TVA has concluded that the proposed NSHCD presented in the Federal Register dated October 3, 2006 (71 FR 58444) notice is applicable to WBN Units 1 and 2, and is hereby incorporated by reference to satisfy the requirements of 10 CFR 50.91(a), Notice for public comment.
3.2 Verification and Commitments As discussed in the notice of availability published in the Federal Register dated October 3, 2006 (71 FR 58444) for this TS improvement, plant-specific verifications will be performed as follows.
- 1. TVA commits to the guidance of NUMARC 93-01 Section 11 (Reference 3), which provides guidance and details on the assessment and management of risk during maintenance.
- 2. TVA will revise procedures to ensure that the risk assessment and management process described in Nuclear Energy Institute (NEI) 04-08 (Reference 4) is used whenever a barrier is considered unavailable and the requirements of LCO 3.0.9 are to be applied, in accordance with an overall configuration risk management program to ensure that potentially risk-significant configurations resulting from maintenance and other operational activities are identified and avoided.
4.0 ENVIRONMENTAL EVALUATION TVA has reviewed the environmental evaluation included in the model safety evaluation dated October 3, 2006 as part of the CLllP. TVA has concluded that the staff's findings presented in that evaluation are applicable to WBN and the evaluation is hereby incorporated by reference for this application.
5.0 REFERENCES
- 1. Letter from the Technical Specifications Task Force to U.S. Nuclear Regulatory Commission, Revision of References to Regulatory Guide 1.182 in Approved Travelers, TSTF-14-10, dated September 16, 2014 (ML14259A575)
- 2. Letter from A. Mendiola (U.S. Nuclear Regulatory Commission) to Technical Specifications Task Force (TSTF), U.S. Nuclear Regulatory Commission Response to the TSTF Letter Regarding References to Regulatory Guide 1.182 in Approved Travelers, dated February 26, 2015 (ML15033A152)
- 3. NUMARC 93-01, Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants
- 4. NEI 04-08, Allowance for Non-Technical Specification Barrier Degradation on Supported System OPERABILITY (TSTF-427), dated March 2006 (ML061220426)
CNL-23-052 Proposed TS Changes (Mark-Ups) for WBN Unit 1
LCO Applicability 3.0 (continued)
Watts Bar-Unit 1 3.0-1 Amendment 55, 111, 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY LCO 3.0.1 LCOs shall be met during the MODES or other specified conditions in the Applicability, except as provided in LCO 3.0.2, LCO 3.0.7, and LCO 3.0.8, and LCO 3.0.9.
LCO 3.0.2 Upon discovery of a failure to meet an LCO, the Required Actions of the associated Conditions shall be met, except as provided in LCO 3.0.5 and LCO 3.0.6.
If the LCO is met or is no longer applicable prior to expiration of the specified Completion Time(s), completion of the Required Action(s) is not required unless otherwise stated.
LCO 3.0.3 When an LCO is not met and the associated ACTIONS are not met, an associated ACTION is not provided, or if directed by the associated ACTIONS the unit shall be placed in a MODE or other specified condition in which the LCO is not applicable. Action shall be initiated within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to place the unit, as applicable, in:
- a.
MODE 3 within 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />;
- b.
MODE 4 within 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br />; and
- c.
MODE 5 within 37 hours4.282407e-4 days <br />0.0103 hours <br />6.117725e-5 weeks <br />1.40785e-5 months <br />.
Exceptions to this Specification are stated in the individual Specifications.
Where corrective measures are completed that permit operation in accordance with the LCO or ACTIONS, completion of the actions required by LCO 3.0.3 is not required.
LCO 3.0.3 is only applicable in MODES 1, 2, 3, and 4.
LCO 3.0.4 When an LCO is not met, entry into a MODE or other specified condition in the Applicability shall only be made:
- a.
When the associated ACTIONS to be entered permit continued operation in the MODE or other specified condition in the Applicability for an unlimited period of time;
LCO Applicability 3.0 Watts Bar-Unit 1 3.0-4 Amendment 3.0 LCO APPLICABILITY LCO 3.0.9 When one or more required barriers are unable to perform their related support function(s), any supported system LCO(s) are not required to be declared not met solely for this reason for up to 30 days provided that at least one train or subsystem of the supported system is OPERABLE and supported by barriers capable of providing their related support function(s), and risk is assessed and managed. This specification may be concurrently applied to more than one train or subsystem of a multiple train or subsystem supported system provided at least one train or subsystem of the supported system is OPERABLE and the barriers supporting each of these trains or subsystems provide their related support function(s) for different categories of initiating events.
If the required OPERABLE train or subsystem becomes inoperable while this specification is in use, it must be restored to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or the provisions of this specification cannot be applied to the trains or subsystems supported by the barriers that cannot perform their related support function(s).
At the end of the specified period, the required barriers must be able to perform their related support function(s) or the supported system LCO(s) shall be declared not met.
SR Applicability 3.0 (continued)
Watts Bar-Unit 1 3.0-5 Amendment 42, 114, 121, 135,158, 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY SR 3.0.1 SRs shall be met during the MODES or other specified conditions in the Applicability for individual LCOs, unless otherwise stated in the SR. Failure to meet a Surveillance, whether such failure is experienced during the performance of the Surveillance or between performances of the Surveillance, shall be failure to meet the LCO. Failure to perform a Surveillance within the specified Frequency shall be failure to meet the LCO except as provided in SR 3.0.3.
Surveillances do not have to be performed on inoperable equipment or variables outside specified limits.
SR 3.0.2 The specified Frequency for each SR is met if the Surveillance is performed within 1.25 times the interval specified in the Frequency, as measured from the previous performance or as measured from the time a specified condition of the Frequency is met.
For Frequencies specified as "once," the above interval extension does not apply.
If a Completion Time requires periodic performance on a "once per..." basis, the above Frequency extension applies to each performance after the initial performance.
Exceptions to this Specification are stated in the individual Specifications.
SR 3.0.3 If it is discovered that a Surveillance was not performed within its specified Frequency, then compliance with the requirement to declare the LCO not met may be delayed, from the time of discovery, up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or up to the limit of the specified Frequency, whichever is greater. This delay period is permitted to allow performance of the Surveillance. The delay period is only applicable when there is a reasonable expectation the surveillance will be met when performed. A risk evaluation shall be performed for any Surveillance delayed greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and the risk impact shall be managed.
If the Surveillance is not performed within the delay period, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.
When the Surveillance is performed within the delay period and the Surveillance is not met, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.
SR Applicability 3.0 Watts Bar-Unit 1 3.0-6 Amendment 55, 135, 3.0 SR APPLICABILITY SR 3.0.4 Entry into a MODE or other specified condition in the Applicability of an LCO shall only be made when the LCO's Surveillances have been met within their specified Frequency, except as provided by SR 3.0.3. When an LCO is not met due to Surveillances not having been met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with LCO 3.0.4.
This provision shall not prevent entry into MODES or other specified conditions in the Applicability that are required to comply with ACTIONS or that are part of a shutdown of the unit.
CNL-23-052 Proposed TS Changes (Mark-Ups) for WBN Unit 2
LCO Applicability 3.0 (continued)
Watts Bar - Unit 2 3.0-1 Amendment 6 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY LCO 3.0.1 LCOs shall be met during the MODES or other specified conditions in the Applicability, except as provided in LCO 3.0.2, 3.0.7, and 3.0.8, and 3.0.9.
LCO 3.0.2 Upon discovery of a failure to meet an LCO, the Required Actions of the associated Conditions shall be met, except as provided in LCO 3.0.5 and LCO 3.0.6.
If the LCO is met or is no longer applicable prior to expiration of the specified Completion Time(s), completion of the Required Action(s) is not required unless otherwise stated.
LCO 3.0.3 When an LCO is not met and the associated ACTIONS are not met, an associated ACTION is not provided, or if directed by the associated ACTIONS the unit shall be placed in a MODE or other specified condition in which the LCO is not applicable. Action shall be initiated within 1 hour1.157407e-5 days <br />2.777778e-4 hours <br />1.653439e-6 weeks <br />3.805e-7 months <br /> to place the unit, as applicable, in:
a.
MODE 3 within 7 hours8.101852e-5 days <br />0.00194 hours <br />1.157407e-5 weeks <br />2.6635e-6 months <br />; b.
MODE 4 within 13 hours1.50463e-4 days <br />0.00361 hours <br />2.149471e-5 weeks <br />4.9465e-6 months <br />; and c.
MODE 5 within 37 hours4.282407e-4 days <br />0.0103 hours <br />6.117725e-5 weeks <br />1.40785e-5 months <br />.
Exceptions to this Specification are stated in the individual Specifications.
Where corrective measures are completed that permit operation in accordance with the LCO or ACTIONS, completion of the actions required by LCO 3.0.3 is not required.
LCO 3.0.3 is only applicable in MODES 1, 2, 3, and 4.
LCO 3.0.4 When an LCO is not met, entry into a MODE or other specified condition in the Applicability shall only be made:
a.
When the associated ACTIONS to be entered permit continued operation in the MODE or other specified condition in the Applicability for an unlimited period of time;
LCO Applicability 3.0 3.0 LCO APPLICABILITY Watts Bar - Unit 2 3.0-4 Amendment LCO 3.0.9 When one or more required barriers are unable to perform their related support function(s), any supported system LCO(s) are not required to be declared not met solely for this reason for up to 30 days provided that at least one train or subsystem of the supported system is OPERABLE and supported by barriers capable of providing their related support function(s), and risk is assessed and managed. This specification may be concurrently applied to more than one train or subsystem of a multiple train or subsystem supported system provided at least one train or subsystem of the supported system is OPERABLE and the barriers supporting each of these trains or subsystems provide their related support function(s) for different categories of initiating events.
If the required OPERABLE train or subsystem becomes inoperable while this specification is in use, it must be restored to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or the provisions of this specification cannot be applied to the trains or subsystems supported by the barriers that cannot perform their related support function(s).
At the end of the specified period, the required barriers must be able to perform their related support function(s) or the supported system LCO(s) shall be declared not met.
SR Applicability 3.0 Watts Bar - Unit 2 3.0-5 Amendment No. 3, 12, 39, 66, 3.0 SURVEILLANCE REQUIREMENT (SR) APPLICABILITY SR 3.0.1 SRs shall be met during the MODES or other specified conditions in the Applicability for individual LCOs, unless otherwise stated in the SR.
Failure to meet a Surveillance, whether such failure is experienced during the performance of the Surveillance or between performances of the Surveillance, shall be failure to meet the LCO. Failure to perform a Surveillance within the specified Frequency shall be failure to meet the LCO except as provided in SR 3.0.3. Surveillances do not have to be performed on inoperable equipment or variables outside specified limits.
SR 3.0.2 The specified Frequency for each SR is met if the Surveillance is performed within 1.25 times the interval specified in the Frequency, as measured from the previous performance or as measured from the time a specified condition of the Frequency is met.
For Frequencies specified as "once," the above interval extension does not apply.
If a Completion Time requires periodic performance on a "once per..."
basis, the above Frequency extension applies to each performance after the initial performance.
Exceptions to this Specification are stated in the individual Specifications.
SR 3.0.3 If it is discovered that a Surveillance was not performed within its specified Frequency, then compliance with the requirement to declare the LCO not met may be delayed, from the time of discovery, up to 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> or up to the limit of the specified Frequency, whichever is greater. This delay period is permitted to allow performance of the Surveillance. The delay period is only applicable when there is a reasonable expectation the surveillance will be met when performed. A risk evaluation shall be performed for any Surveillance delayed greater than 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> and the risk impact shall be managed.
If the Surveillance is not performed within the delay period, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.
When the Surveillance is performed within the delay period and the Surveillance is not met, the LCO must immediately be declared not met, and the applicable Condition(s) must be entered.
SR Applicability 3.0 Watts Bar - Unit 2 3.0-6 Amendment No. 3, 39, 3.0 SR APPLICABILITY SR 3.0.4 Entry into a MODE or other specified condition in the Applicability of an LCO shall only be made when the LCO's Surveillances have been met within their specified Frequency, except as provided by SR 3.0.3. When an LCO is not met due to Surveillances not having been met, entry into a MODE or other specified condition in the Applicability shall only be made in accordance with LCO 3.0.4.
This provision shall not prevent entry into MODES or other specified conditions in the Applicability that are required to comply with ACTIONS or that are part of a shutdown of the unit.
CNL-23-052 Proposed TS Bases Page Changes (Mark-Ups) for WBN Units 1 and 2 (For Information Only)
LCO Applicability B 3.0 (continued)
Watts Bar-Unit 1 B 3.0-1 Revision 133, 186, Amendment 111, 158, B 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY BASES LCOs LCO 3.0.1 through LCO 3.0.89 establish the general requirements applicable to all Specifications and apply at all times, unless otherwise stated.
LCO 3.0.1 LCO 3.0.1 establishes the Applicability statement within each individual Specification as the requirement for when the LCO is required to be met (i.e.,
when the unit is in the MODES or other specified conditions of the Applicability statement of each Specification).
LCO 3.0.2 LCO 3.0.2 establishes that upon discovery of a failure to meet an LCO, the associated ACTIONS shall be met. The Completion Time of each Required Action for an ACTIONS Condition is applicable from the point in time that an ACTIONS Condition is entered, unless otherwise specified. The Required Actions establish those remedial measures that must be taken within specified Completion Times when the requirements of an LCO are not met. This Specification establishes that:
- a.
Completion of the Required Actions within the specified Completion Times constitutes compliance with a Specification; and
- b.
Completion of the Required Actions is not required when an LCO is met within the specified Completion Time, unless otherwise specified.
There are two basic types of Required Actions. The first type of Required Action specifies a time limit in which the LCO must be met. This time limit is the Completion Time to restore an inoperable system or component to OPERABLE status or to restore variables to within specified limits. If this type of Required Action is not completed within the specified Completion Time, a shutdown may be required to place the unit in a MODE or condition in which the Specification is not applicable. (Whether stated as a Required Action or not, correction of the entered Condition is an action that may always be considered upon entering ACTIONS.) The second type of Required Action specifies the remedial measures that permit continued operation of the unit that is not further restricted by the Completion Time. In this case, compliance with the Required Actions provides an acceptable level of safety for continued operation.
LCO Applicability B 3.0 BASES (continued)
Watts Bar-Unit 1 B 3.0-11 Revision 133, Amendment 111, LCO 3.0.8 LCO 3.0.8.a applies when one or more snubbers are not capable of providing (continued) their associated support function(s) to a single train or subsystem of a multiple train or subsystem supported system or to a single train or subsystem supported system. LCO 3.0.8.a allows 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> to restore the snubber(s) before declaring the supported system inoperable. The 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> Completion Time is reasonable based on the low probability of a seismic event concurrent with an event that would require operation of the supported system occurring while the snubber(s) are not capable of performing their associated support function and due to the availability of the redundant train of the supported system.
LCO 3.0.8.b applies when one or more snubbers are not capable of providing their associated support function(s) to more than one train or subsystem of a multiple train or subsystem supported system. LCO 3.0.8.b allows 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to restore the snubber(s) before declaring the supported system inoperable. The 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Completion Time is reasonable based on the low probability of a seismic event concurrent with an event that would require operation of the supported system occurring while the snubber(s) are not capable of performing their associated support function.
LCO 3.0.8 requires that risk be assessed and managed. Industry and NRC guidance on the implementation of 10 CFR 50.65(a)(4) (the Maintenance Rule) does not address seismic risk. However, use of LCO 3.0.8 should be considered with respect to other plant maintenance activities, and integrated into the existing Maintenance Rule process to the extent possible so that maintenance on any unaffected train or subsystem is properly controlled, and emergent issues are properly addressed. The risk assessment need not be quantified, but may be a qualitative awareness of the vulnerability of systems and components when one or more snubbers are not able to perform their associated support function.
LCO 3.0.9 LCO 3.0.9 establishes conditions under which systems described in the Technical Specifications are considered to remain OPERABLE when required barriers are not capable of providing their related support function(s).
Barriers are doors, walls, floor plugs, curbs, hatches, installed structures or components, or other devices, not explicitly described in Technical Specifications, that support the performance of the safety function of systems described in the Technical Specifications. This LCO states that the supported system is not considered to be inoperable solely due to required barriers not capable of performing their related support function(s) under the described conditions. LCO 3.0.9 allows 30 days before declaring the supported system(s) inoperable and the LCO(s) associated with the supported system(s) not met. A maximum time is placed on each use of this allowance to ensure that as required barriers are found or are otherwise made unavailable, they are restored. However, the allowable duration may be less than the specified maximum time based on the risk assessment.
LCO Applicability B 3.0 BASES (continued)
Watts Bar-Unit 1 B 3.0-11a Revision Amendment LCO 3.0.9 (continued)
If the allowed time expires and the barriers are unable to perform their related support function(s), the supported systems LCO(s) must be declared not met and the Conditions and Required Actions entered in accordance with LCO 3.0.2.
This provision does not apply to barriers which support ventilation systems or to fire barriers. The Technical Specifications for ventilation systems provide specific Conditions for inoperable barriers. Fire barriers are addressed by other regulatory requirements and associated plant programs. This provision does not apply to barriers which are not required to support system OPERABILITY (see NRC Regulatory Issue Summary 2001-09, Control of Hazard Barriers, dated April 2, 2001).
The provisions of LCO 3.0.9 are justified because of the low risk associated with required barriers not being capable of performing their related support function. This provision is based on consideration of the following initiating event categories:
Loss of coolant accidents; High energy line breaks; Feedwater line breaks; Internal flooding; External flooding; Turbine missile ejection; and Tornado or high wind.
The risk impact of the barriers which cannot perform their related support function(s) must be addressed pursuant to the risk assessment and management provision of the Maintenance Rule, 10 CFR 50.65 (a)(4), and the associated implementation guidance, Regulatory Guide 1.160, "Monitoring the Effectiveness of Maintenance at Nuclear Power Plants." Regulatory Guide 1.160 endorses the guidance in Section 11 of NUMARC 93-01, "Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants." This guidance provides for the consideration of dynamic plant configuration issues, emergent conditions, and other aspects pertinent to plant operation with the barriers unable to perform their related support function(s).
These considerations may result in risk management and other compensatory actions being required during the period that barriers are unable to perform their related support function(s).
LCO Applicability B 3.0 BASES (continued)
Watts Bar-Unit 1 B 3.0-11b Revision Amendment LCO 3.0.9 (continued)
LCO 3.0.9 may be applied to one or more trains or subsystems of a system supported by barriers that cannot provide their related support function(s), provided that risk is assessed and managed (including consideration of the effects on Large Early Release and from external events). If applied concurrently to more than one train or subsystem of a multiple train or subsystem supported system, the barriers supporting each of these trains or subsystems must provide their related support function(s) for different categories of initiating events. For example, LCO 3.0.9 may be applied for up to 30 days for more than one train of a multiple train supported system if the affected barrier for one train protects against internal flooding and the affected barrier for the other train protects against tornado missiles. In this example, the affected barrier may be the same physical barrier but serve different protection functions for each train.
If during the time that LCO 3.0.9 is being used, the required OPERABLE train or subsystem becomes inoperable, it must be restored to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Otherwise, the train(s) or subsystem(s) supported by barriers that cannot perform their related support function(s) must be declared inoperable and the associated LCOs declared not met. This 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period provides time to respond to emergent conditions that would otherwise likely lead to entry into LCO 3.0.3 and a rapid plant shutdown, which is not justified given the low probability of an initiating event which would require the barrier(s) not capable of performing their related support function(s). During this 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period, the plant risk associated with the existing conditions is assessed and managed in accordance with 10 CFR 50.65(a)(4).
LCO Applicability B 3.0 (continued)
Watts Bar - Unit 2 B 3.0-1 Revision 7, 65, Amendment 6, 66, B 3.0 LIMITING CONDITION FOR OPERATION (LCO) APPLICABILITY BASES LCOs LCO 3.0.1 through LCO 3.0.89 establish the general requirements applicable to all Specifications and apply at all times, unless otherwise stated.
LCO 3.0.1 LCO 3.0.1 establishes the Applicability statement within each individual Specification as the requirement for when the LCO is required to be met (i.e., when the unit is in the MODES or other specified conditions of the Applicability statement of each Specification).
LCO 3.0.2 LCO 3.0.2 establishes that upon discovery of a failure to meet an LCO, the associated ACTIONS shall be met. The Completion Time of each Required Action for an ACTIONS Condition is applicable from the point in time that an ACTIONS Condition is entered, unless otherwise specified.
The Required Actions establish those remedial measures that must be taken within specified Completion Times when the requirements of an LCO are not met. This Specification establishes that:
- a.
Completion of the Required Actions within the specified Completion Times constitutes compliance with a Specification; and
- b.
Completion of the Required Actions is not required when an LCO is met within the specified Completion Time, unless otherwise specified.
There are two basic types of Required Actions. The first type of Required Action specifies a time limit in which the LCO must be met. This time limit is the Completion Time to restore an inoperable system or component to OPERABLE status or to restore variables to within specified limits. If this type of Required Action is not completed within the specified Completion Time, a shutdown may be required to place the unit in a MODE or condition in which the Specification is not applicable. (Whether stated as a Required Action or not, correction of the entered Condition is an action that may always be considered upon entering ACTIONS.) The second type of Required Action specifies the remedial measures that permit continued operation of the unit that is not further restricted by the Completion Time. In this case, compliance with the Required Actions provides an acceptable level of safety for continued operation.
LCO Applicability B 3.0 BASES (continued)
Watts Bar - Unit 2 B 3.0-10d Revision 7, Amendment 6, LCO 3.0.8 (continued)
LCO 3.0.8.b applies when one or more snubbers are not capable of providing their associated support function(s) to more than one train or subsystem of a multiple train or subsystem supported system. LCO 3.0.8.b allows 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> to restore the snubber(s) before declaring the supported system inoperable. The 12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> Completion Time is reasonable based on the low probability of a seismic event concurrent with an event that would require operation of the supported system occurring while the snubber(s) are not capable of performing their associated support function.
LCO 3.0.8 requires that risk be assessed and managed. Industry and NRC guidance on the implementation of 10 CFR 50.65(a)(4) (the Maintenance Rule) does not address seismic risk. However, use of LCO 3.0.8 should be considered with respect to other plant maintenance activities, and integrated into the existing Maintenance Rule process to the extent possible so that maintenance on any unaffected train or subsystem is properly controlled, and emergent issues are properly addressed. The risk assessment need not be quantified, but may be a qualitative awareness of the vulnerability of systems and components when one or more snubbers are not able to perform their associated support function.
LCO 3.0.9 LCO 3.0.9 establishes conditions under which systems described in the Technical Specifications are considered to remain OPERABLE when required barriers are not capable of providing their related support function(s).
Barriers are doors, walls, floor plugs, curbs, hatches, installed structures or components, or other devices, not explicitly described in Technical Specifications, that support the performance of the safety function of systems described in the Technical Specifications. This LCO states that the supported system is not considered to be inoperable solely due to required barriers not capable of performing their related support function(s) under the described conditions. LCO 3.0.9 allows 30 days before declaring the supported system(s) inoperable and the LCO(s) associated with the supported system(s) not met. A maximum time is placed on each use of this allowance to ensure that as required barriers are found or are otherwise made unavailable, they are restored. However, the allowable duration may be less than the specified maximum time based on the risk assessment.
If the allowed time expires and the barriers are unable to perform their related support function(s), the supported systems LCO(s) must be declared not met and the Conditions and Required Actions entered in accordance with LCO 3.0.2.
LCO Applicability B 3.0 BASES (continued)
Watts Bar - Unit 2 B 3.0-10e Revision 7, Amendment LCO 3.0.9 (continued)
This provision does not apply to barriers which support ventilation systems or to fire barriers. The Technical Specifications for ventilation systems provide specific Conditions for inoperable barriers. Fire barriers are addressed by other regulatory requirements and associated plant programs. This provision does not apply to barriers which are not required to support system OPERABILITY (see NRC Regulatory Issue Summary 2001-09, Control of Hazard Barriers, dated April 2, 2001).
The provisions of LCO 3.0.9 are justified because of the low risk associated with required barriers not being capable of performing their related support function. This provision is based on consideration of the following initiating event categories:
Loss of coolant accidents; High energy line breaks; Feedwater line breaks; Internal flooding; External flooding; Turbine missile ejection; and Tornado or high wind.
The risk impact of the barriers which cannot perform their related support function(s) must be addressed pursuant to the risk assessment and management provision of the Maintenance Rule, 10 CFR 50.65 (a)(4),
and the associated implementation guidance, Regulatory Guide 1.160, "Monitoring the Effectiveness of Maintenance at Nuclear Power Plants."
Regulatory Guide 1.160 endorses the guidance in Section 11 of NUMARC 93-01, "Industry Guideline for Monitoring the Effectiveness of Maintenance at Nuclear Power Plants." This guidance provides for the consideration of dynamic plant configuration issues, emergent conditions, and other aspects pertinent to plant operation with the barriers unable to perform their related support function(s). These considerations may result in risk management and other compensatory actions being required during the period that barriers are unable to perform their related support function(s).
LCO Applicability B 3.0 BASES Watts Bar - Unit 2 B 3.0-10f Revision 7, Amendment LCO 3.0.9 (continued)
LCO 3.0.9 may be applied to one or more trains or subsystems of a system supported by barriers that cannot provide their related support function(s), provided that risk is assessed and managed (including consideration of the effects on Large Early Release and from external events). If applied concurrently to more than one train or subsystem of a multiple train or subsystem supported system, the barriers supporting each of these trains or subsystems must provide their related support function(s) for different categories of initiating events. For example, LCO 3.0.9 may be applied for up to 30 days for more than one train of a multiple train supported system if the affected barrier for one train protects against internal flooding and the affected barrier for the other train protects against tornado missiles. In this example, the affected barrier may be the same physical barrier but serve different protection functions for each train.
If during the time that LCO 3.0.9 is being used, the required OPERABLE train or subsystem becomes inoperable, it must be restored to OPERABLE status within 24 hours2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br />. Otherwise, the train(s) or subsystem(s) supported by barriers that cannot perform their related support function(s) must be declared inoperable and the associated LCOs declared not met. This 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period provides time to respond to emergent conditions that would otherwise likely lead to entry into LCO 3.0.3 and a rapid plant shutdown, which is not justified given the low probability of an initiating event which would require the barrier(s) not capable of performing their related support function(s). During this 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period, the plant risk associated with the existing conditions is assessed and managed in accordance with 10 CFR 50.65(a)(4).
CNL-23-052 E2 1 of 1 The following table identifies those actions committed to by Tennessee Valley Authority (TVA) in this document. Any other statements in this submittal are provided for information purposes and are not considered to be regulatory commitments. Please direct questions regarding these commitments to Stuart L. Rymer, Senior Manager, Fleet Licensing.
COMMITMENT COMMITTED DATE OR OUTAGE COMMITMENT TYPE One-Time Action (Yes/No)
Programmatic (Yes/No)
- 1. TVA commits to the guidance of NUMARC 93-01, Section 11, which provides guidance and details on the assessment and management of risk during maintenance.
120 days following approval No Yes
- 2. TVA will revise procedures to ensure that the risk assessment and management process described in NEI 04-08 is used whenever a barrier is considered unavailable and the requirements of LCO 3.0.9 are to be applied, in accordance with an overall configuration risk management program to ensure that potentially risk-significant configurations resulting from maintenance and other operational activities are identified and avoided.
120 days following approval No Yes