Text
Exhibit KRS-002
Hermes Mandatory Hearing - Over view Panel
MICHAEL LAUFER, CHIEF EXECUTIVE OFFICER PER PETERSON, CHIEF NUCLEAR OFFICER OCTOBER 19, 2023
Copyright © 2023 Kairos Power LLC. All Rights Reserved. 1 No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Kairos Power s mission is to enable the worlds transition to clean energy, with the ultimate goal of dramatically improving peoples quality of life while protecting the environment.
Copyright © 2023 Kairos Power LLC. All Rights Reserved. 2 No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Over view of Kairos Power
- Kairos Power is a privately owned nuclear energy engineering, Kairos Power Headquarters design, and manufacturing company singularly focused on the commercialization of the fluoride salt-cooled high-temperature reactor (FHR)
Founded in 2016 and headquartered in Alameda California 360+ Employees with a majority engineering and manufacturing
- Kairos Power is pursuing a novel approach to nuclear development, highly informed by the success of SpaceX, that includes iterative hardware demonstrations and in-house manufacturing to achieve disruptive cost reduction and provide Kairos Power Team true cost certainty for commercialization
- Our cost target objectives are set to be competitive with natural gas in the US electricity market
- We are targeting a US commercial demonstration by 2030 (or earlier) and rapid deployment ramp in 2030s
Copyright © 2023 Kairos Power LLC. All Rights Reserved.
No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Kairos Power Locations
Molten Salt Purification Plant Elmore, OH Instrumentation Labs Rexford, NY T-Facility / Engineering Test Unit HQ / R-Lab / S-LabProduction Development Facility Alameda, CA Albuquerque, NM Hermes Reactor Licensing Office Oak Ridge, TN Charlotte, NC
Kairos Power Facilities
Copyright © 2023 Kairos Power LLC. All Rights Reserved.
No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Kairos Power Business Model Focuses on Reducing Risk and Improving Build Cost Certainty
KP-FHR Design Technology Certainty
Te s t P r o g r a m Licensing Certainty Licensing Cost Supply Chain Certainty
Certainty Fuel Development Build Salt Development Certainty
Copyright © 2023 Kairos Power LLC. All Rights Reserved.
No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Kairos Power NuclearDevelopment Pa ra d i g m S h i f t :
Rapid Hardware Iterations Enable Innovation and Build True Cost Certainty
Conventional Nuclear Development Cycle is Slow and Capital Intensive PLAN DESIGN BUILD TEST
Inner Loop of Plan-Design is Common for Conventional Nuclear TEST EXPERIENCE Kairos Power Iterative Test Cycles Accelerate Technology and Manufacturing Development
PLAN DESIGN BUILD TEST PLAN DESIGN BUILD TEST PLAN DESIGN BUILD TEST Test Test Experience Experience
TEST EXPERIENCE
Copyright © 2023 Kairos Power LLC. All Rights Reserved. 6 No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Path to Commercialization
PLAN DESIGN BUILD TEST KP-X Commercial Plant
KP-X
User Facility PLAN DESIGN BUILD TEST Reactor Demonstration Unit (Non-Nuclear)
U-Facility
PLAN DESIGN BUILD TEST Hermes Demo Reactor Series
Hermes Hermes 2 Nuclear
Engineering Test Units Produces electricity PLAN DESIGN BUILD TEST (Non-Nuclear) and connected to grid ETU 1.0 ETU 2.0 ETU 3.0
Copyright © 2023 Kairos Power LLC. All Rights Reserved.
No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Hermes Reactor
- What? KP-X / U-Facility A low power demonstration reactor that will prove Kairos Power s capability to deliver low-cost nuclear heat
- Why? Operations Cost: Establish competitive cost through iterative learning cycles ETU / Hermes Supply Chain: Advance the supply chain for KP-FHR specialized components and materials while vertical integrating critical systems Design / Test: Deliberate and incremental risk reduction Licensing Approach: NRC will license Hermes as a non-power reactor and facilitate licensing certainty for KP-FHR Operations: Provide a complete demonstration of nuclear functions including reactor physics, fuel and structural materials irradiation, and radiological controls
Hermes will ultimately demonstrate the U.S. aptitude to license an advanced reactor in a timely manner
Copyright © 2023 Kairos Power LLC. All Rights Reserved.
No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Hermes Over view
- Fluoride-salt cooled, high temperature reactor (FHR)
- Pebble bed core with Tri-structural, isotropic (TRISO) fuel particles, graphite moderator/refle ctor
- Reactor Thermal Power: 35 MWth
- Coolant Operating Temperature:550°C - 650°C
- 316H stainless steel reactor vessel
- Passive safety systems Shutdown elements insert via gravity D ecay heat removal system removes heat during postulated events without active components
Copyright © 2023 Kairos Power LLC. All Rights Reserved. 9 No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Hermes Site
- The site is located in Oak Ridge, Tennessee in Roane County within the East Tennessee Technology Park (ET TP)
- The Hermes test reactor will be located on former Department of Energy gaseous diffusion plant (K-33) building site
- The site boundary encompasses approximately 185 acres About 30 acres would be permanently disturbed for operations of the facility
Copyright © 2023 Kairos Power LLC. All Rights Reserved.
No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.
Artist s rendering of the Hermes facilityArtist s rendering of the Hermes facility Hermes Construction Pe r m i t Application (CPA)
- Hermes CPA developed using guidance in NUREG 1537
- Hermes PSAR submitted September 2021
- Hermes ER submitted October 2021
- NRC accepted Kairos Power s CPA for review in November 2021
- Hermes ER Rev 1 submitted March 2023
- FEIS issued August 2023
- Hermes PSAR Rev 3 submitted May 2023
Copyright © 2023 Kairos Power LLC. All Rights Reserved.* FSER issued June 2023 11 No Reproduction or Distribution Without Express Written Permission of Kairos Power LLC.