Summary of August 4, 2023, NRC Public Observation Meeting with the Pressurized Water Reactor Owners Group to Discuss Clarification of Requests for Additional Information on Topical Report PWROG-18068-NP
ML23270B860
Person / Time
Site: 99902037
Issue date: 10/05/2023
From: Leslie Fields
Licensing Processes Branch
To: Gerond George
Licensing Processes Branch
Shared Package
ML23270B859 List:
References
EPID L-2021-TOP-0027
Download: ML23270B860 (4)


Text

October 5, 2023 MEMORANDUM TO:

Gerond A. George, Chief Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM:

Leslie C. Fields, Senior Project Manager /RA/

Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF AUGUST 4, 2023, U.S. NUCLEAR REGULATORY COMMISSION PUBLIC OBSERVATION MEETING WITH THE PRESSURIZED WATER REACTOR OWNERS GROUP TO DISCUSS CLARIFICATION OF REQUESTS FOR ADDITIONAL INFORMATION ON TOPICAL REPORT PWROG-18068-NP, REVISION 1 (EPID L-2021-TOP-0027)

On August 4, 2023, the U.S. Nuclear Regulatory Commission (NRC) staff held a public meeting with the Pressurized Water Reactor Owners Group (PWROG) to provide clarification on Request for Additional Information (RAI) questions regarding Topical Report (TR)

PWROG-18068-NP, Revision 1, Use of Direct Fracture Toughness for Evaluation of Reactor Pressure Vessel Integrity (Agencywide Documents Access and Management System ADAMS Accession No. ML21209A933) transmitted for NRC review and approval on July 17, 2021. The meeting was held virtually and provided the opportunity to discuss PWROGs proposed responses to NRCs RAI questions in an open and collaborative environment. The meeting notice and presentation slides are publicly available at ADAMS Package Accession No. ML23209A041. A list of the meeting attendees is enclosed in this meeting summary.

TR PWROG-18068 provides an alternative methodology to the Reactor Pressure Vessel material integrity requirements which are available in Title 10 of the Code of Federal Regulations Appendix G to Part 50, Fracture Toughness Requirements, Section 50.60, Acceptance criteria for fracture prevention measures for lightwater nuclear power reactors for normal operation, and Section 50.61, Fracture toughness requirements for protection against pressurized thermal shock events. As a result of the technical review of TR PWROG-18068, Rev. 1, the NRC staff transmitted RAI questions and PWROG provided the proposed responses to the RAIs. During the August 4, 2023, public observation meeting, the NRC staff provided clarification on the first half of PWROGs draft responses up to RAI 13, but due to the meeting time constraint no additional draft RAI responses were discussed. The entire draft RAI response markup is available at ADAMS Accession No. ML23180A161.

CONTACT: Leslie Fields, NRR/DORL 301-415-1186

Subsequently, to complete the discussion on the second half of the PWROGs draft responses, it was determined that Part 2 of this public meeting would be scheduled in the near future. All information regarding the future meeting will be posted on NRCs Public Meeting Notification System.

At the conclusion of the meeting, there was an opportunity for the public to provide comments and ask questions. It was noted that no public comments were received.

Please direct any inquiries to me at (301) 415-1186 or by e-mail at Leslie.Fields@nrc.gov.

Docket No. 99902037

Enclosure:

List of Meeting Attendees

Enclosure

SUMMARY

OF AUGUST 4, 2023, PUBLIC MEETING U.S. NUCLEAR REGULATORY COMMISSION CLARIFICATION OF REQUEST FOR ADDITIONAL INFORMATION RESPONSES ON TOPICAL REPORT PWROG-18068 ATTENDANCE LIST Name Organization Leslie Fields U.S. Nuclear Regulatory Commission (NRC)

Gerond George NRC David Dijamco NRC Angie Buford NRC John Tsao NRC Robert Tregoning NRC Dan Widrevitz NRC Carol Moyer NRC Carolyn Fairbanks NRC Steven Levitus NRC David Rudland NRC Michael Benson NRC Patrick Raynaud NRC Eric Palmer NRC Allen Hiser NRC James Molkenthin Westinghouse Chad Holderbaum Westinghouse James Andrachek Westinghouse Brett Lynch Westinghouse Brian Hall Westinghouse Jianwei Chen Westinghouse Benjamin Mays Westinghouse

ML23270B859 (Package)

ML23209A041 (Notice)

ML23180A161 (NRC Draft Responses)

ML23208A201 (Slides)

ML23270B860 (Summary)

OFFICE NRR/DORL/LLPB/PM NRR/DORL/LLPB/LA NRR/DNRL/NVIB/BC NAME LFields DHarrison ABuford DATE 09/28/2023 10/3/2023 10/05/2023 OFFICE NRR/DORL/LLPB/BC NRR/DORL/LLPB/PM NAME GGeorge LFields DATE 10/05/2023 10/05/2023