ML23251A028

From kanterella
Jump to navigation Jump to search
FOIA-2023-000163 - Responsive Record - Public ADAMS Document Report. Part 17 of 19
ML23251A028
Person / Time
Issue date: 08/31/2023
From:
NRC/OCIO
To:
- No Known Affiliation
Shared Package
ML23251A034 List:
References
FOIA-2023-000163
Download: ML23251A028 (1)


Text

4 I

'CCELERATED DIS(.-'GBUTION DEMONSTRi.-.TION SYSTEM .

, REGULATOLs INFORMATION DISTRIBUTION bsSTEM (RIDS)

SSION NBR:9211170033 DOC.DATE: 92/10/27 NOTARIZED: NO DOCKET IL:50-410 Nine Mile Point Nuclear Station, Unit 2, Niagara Moha 05000410 UTH.NAME AUTHOR AFFILIATION SYLVIAPB.R. Niagara Mohawk Power Corp.

RECIP.NAME RECIPIENT AFFILIATION HODGES,M.W. Region 1 (Post 820201)

SUBJECT:

Suppls 920511 response to NRC request for util perspectives on findings & conclusions contained in NUREG-1455 re transformer failure on 910813 & NRC comments raised during Znsp Rept 50-410/92-27.Deviation/event rept initiated.

DISTRIBOTION CODE: IEOID COPIES RECEIVED:LTR TITLE: General (50 Dkt)-Insp Rept/Notice of J ENCL Violation

+ SIZE:

Response

D NOTES:

RECIPIENT COPIES RECIPIENT COPIES ID CODE/NAME LTTR ENCL ID CODE/NAME LTTR ENCL PD1-1 PD MENNING,J D

INTERNAL: ACRS AEOD AEOD/DEIB AEOD/DSP/TPAB AEOD/TTC DEDRO NRR MORISSEAUPD NRR/DLPQ/LHFBPT NRR/DLPQ/LPEB10 NRR/DOEA/OEAB NRR/DREP/PEPB9H NRR/PMAS/ILRB12 NUDOCS-ABSTRACT 8%&M OGC/HDS1 REG FILE 02 RGN1 FILE 01 EXTERNAL: EG&G/BRYCEPJ.H. NRC PDR 1 1 NSIC D

D NOTE TO ALL "RIDS RECIPIENTS:

PLEASE HELP US TO REDUCE WASTE! CONTACT THE DOCUMENT CONTROL DESK.

ROOM Pl-S7 (EXT. 504-2065) TO ELIMINATEYOUR NAME FROM DISTRIBUTION LISTS FOR DOCUMENTS YOU DON'T NEED!

TOTAL NUMBER OF COPIES REQUIRED: LTTR 24 ENCL

V NlASARA P

u MOHAWK NIAGARAMOHAWKPOWER CORPORATION/NINE MILE POINT, Po. BOX 63, LYCOMING, NY 13093/TELEPHONE (315) 349-2882 B. Raiph Sylvia October 27, 1992 Executive Vice President Nuclear NMP2L 1360 Mr. Marvin W. Hodges Director, Division of Reactor Safety, Region I U. S. Nuclear Regulatory Commission 475 Allendale Road King of Prussia, Pennsylvania 19406 Re: Nine Mile Point Unit 2 Docket No. 50-410 NPF-

Dear Mr. Hodges:

SUBJECT:

INFORMATION AND CORRECTIVE ACTIONS RELATED TO AUGUST 13, 1991 INCIDENT AT NINE MILE POINT UNIT 2 Niagara Mohawk Power Corporation (NMPC) submitted letter NMP2L1345 dated May 11, 1992 in response to the NRC's request for NMPC perspectives on the findings and conclusions contained in NUREG-1455, "Transformer Failure and Common-Mode Loss of Instrument Power at Nine Mile Point Unit 2 on August 13, 1991 ~" In that letter, we discussed actions taken by the damage control team with respect to restoration of the Uninterruptible Power Supplies (UPS's). That discussion is contained in the section entitled "Adequacy of Plant Specific Operation and Recovery Procedures." Subsequent review by the NRC staff and discussion with Niagara Mohawk personnel during the course of inspection 50-410i92-27 led to indications at the exit meeting that a portion of the response may be unclear or misleading. The purpose of this letter is to address that comment.

The portion of our response in question is as follows:

"The team worked expeditiously on one unit at a time in accordance with the procedure for restoring UPS power from the maintenance feed. Additional precautions were taken based on their special knowledge of the UPS units and the conditions at the time".

After further evaluation, we agree that this wording is subject to misinterpretation and should be clarified.

LDUU'f'~

003017LL 9211170033 921027 o/

PDR ADOCK 05000410 8 PDR

Page 2 The discussion in section 5.6.5 of NUREG-1455 correctly characterizes the concern of the Emergency Director with respect to the power supply for the UPS loads via the unfiltered maintenance supply, and his desire to establish the most reliable configuration possible.

Niagara Mohawk's response reaffirmed this as the basis for the Emergency Director's

'decision to direct the damage control team's restoration actions. We remain convinced that this was the most prudent course of action.

The NUREG discussion regarding the restoration activities of the damage control team is also basically correct. However, Niagara Mohawk had offered comments in its response to clarify a possible misperception in this discussion that the tasks carried out by the team were in no way addressed by procedures. While it is correct the team had concluded that the available procedural guidance was not adequate, they had not concluded that the procedure did not apply at all. In fact, with the exception of the added precautions, their actions were consistent with the procedure steps. The additional precautions referred to in NMPC's response were precisely precautions to avoid the possibility of further challenges to the plant and staff. Specifically, the motor operator was lifted off the circuit breaker (CB-4) before the logic was reset. The step of lifting the motor operator was not included in the procedure, but was considered prudent in case the logic did not reset properly.

We agree that the situation. at the time was such that restoration was not necessary on an emergency basis. In fact, restoration actions were well thought out and planned. When the damage control team determined that they needed to take the additional precautions noted, prior to performing any actions they notified and sought verbal permission of a Control Room Senior Reactor Operator to carry out the additional precautions in conjunction with the procedure. When they began implementation, the team started with the least significant UPS unit in terms of plant impact, so that should another unit failure occur, there would have been minimal impact on the station.

All actions taken were appropriate and technically correct. However, the step that was overlooked for this evolution was an administrative procedure revision before proceeding with the additional precautions. Emergency Plan Implementing Procedure EPIP-EPP-22 (formerly S-EPP-22), "Damage Control", was being used during the event, and it provides for the modification of existing procedures when necessary in conjunction with development of a damage control team and mission. A form of the additional precautions referred to in this instance was subsequently incorporated into appropriate sections of OP-71, "13.8KV/4160V/600V A.C. Power Distribution". Therefore, the additional precautions taken would have been approved had the procedure revisions been developed in conjunction with damage control team activities.

003017LL

C l"

Page 3 A Deviation/Event Report (DER) has been initiated to address this issue. As noted, the specific corrective action to address the precautions has been accomplished. We will develop appropriate corrective actions to address the issue of procedure changes for damage control team activities.

Ifyou have any additional questions, please contact us.

Very truly yours, B. ph Sy via Exec. Vice President WDB/sek 003 017LL xc: Regional Administrator, Region I Mr. W. L. Schmidt, Senior Resident Inspector Mr. R, A. Capra, Director, Project Directorate I-l, NRR Mr. J. E. Menning, Project Manager, NRR Records Management

0