Letter Sequence Other |
---|
|
|
MONTHYEARML22213A0102022-08-0101 August 2022 NRR E-mail Capture - Acceptance Review - Vogtle, Units 1 and 2 - Exemption Request from 10 CFR 50.68 to Allow Use of 6-Weight Percent Enriched Fuel Rods in 4 LTAs (L-2022-LLE-0022) Project stage: Acceptance Review ML22224A1272022-08-12012 August 2022 Dashboard Report 8-12-2022 Project stage: Request NL-22-0583, Request for Fee Exemption for NRC Review Fees for the Licensing Amendment and 10 CFR 50.68 Exemption Submitted for Lead Test Assemblies with Increased Enrichment2022-08-12012 August 2022 Request for Fee Exemption for NRC Review Fees for the Licensing Amendment and 10 CFR 50.68 Exemption Submitted for Lead Test Assemblies with Increased Enrichment Project stage: Request ML22228A2122022-08-12012 August 2022, 29 September 2022 Request for a Fee Exemption for NRC Review Fees for the Licensing Amendment Submitted for Lead Test Assemblies with Increased Enrichment Project stage: Request ML22234A0692022-09-15015 September 2022 Request for Withholding Info from Public Disclosure LAR and Exemptions to Allow Use of LTAs for ATF - Enclosure 1, Evaluation of the Proposed Change (Proprietary) EPID L-2022-LLA-0097, LLE-0020, LLE-0021, LLE-0022 Project stage: Approval ML22266A0492022-09-28028 September 2022 Request for Withholding Info from Public Disclosure LAR and Exemptions to Allow Use of LTAs for ATF - Encl. 1, SNC Response to Requests for Additional Info Attachment 2 Proprietary Response to Questions 2-6 EPID L-2022-LLA-0097 Project stage: Approval ML22228A2202022-09-29029 September 2022 Request for Fee Exemption for NRC Review Fees for the Licensing Amendment for Lead Test Assemblies with Increased Enrichment Project stage: Other ML23017A0922023-01-17017 January 2023 NRR E-mail Capture - Revised Estimated Hours - Vogtle, Units 1 and 2 - Exemption Request from 10 CFR 50.68 to Allow Use of 6-Weight Percent Enriched Fuel Rods in 4 LTAs (L-2022-LLE-0022) Project stage: Other NL-23-0012, Post-Audit Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-01-20020 January 2023 Post-Audit Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel Project stage: Supplement NL-23-0360, Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel2023-05-0505 May 2023 Supplement to License Amendment Request and Exemptions to Allow Use of Lead Test Assemblies for Accident-Tolerant Fuel Project stage: Supplement ML23094A1192023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- Letter Project stage: Approval ML23094A1142023-08-0101 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- Exemption Project stage: Approval ML23094A0992023-08-0202 August 2023 Exemption from the Requirements of 10 CFR Part 50, Section 68, Criticality Accident Requirements (EPID L-2022-LLE-0022)- FRN Project stage: Approval 2022-09-29
[Table View] |
|
---|
Category:E-Mail
MONTHYEARML24290A1572024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds (L-2024-LLR-0047) ML24290A1552024-10-16016 October 2024 NRR E-mail Capture - for Your Action - RAI - Farley, Hatch, and Vogtle 1 and 2 - Proposed Alternative Request for Code Case N-572 ML24289A2002024-10-15015 October 2024 NRR E-mail Capture - for Your Action - RAI - Proposed License Amendment Request (LAR) for Vogtle Electric Generating Plant, Units 3 and 4 TS 3.7.6 Action E and SR 3.7.6.5 (L-2024-LLA-0083) ML24261B9282024-09-17017 September 2024 NRR E-mail Capture - for Your Action Discussion Points - Steam Generator Tube Inspection Call with SNC Regarding Vogtle, Unit 3 ML24250A1132024-09-0303 September 2024 Inspection Report 2024004 Radiation Safety Baseline Inspection Information Request ML24247A0092024-09-0303 September 2024 NRR E-mail Capture - Fyi - Revised Estimated Completion Date - Vogtle 3 and 4 - UFSAR Scheduler Exemption Request ML24250A1922024-08-29029 August 2024 Amendment Nos. 223/206 (1) - Email ML24232A0052024-08-16016 August 2024 NRR E-mail Capture - Acceptance Review - LAR and Exemption Request to Remove Tier 1 and Tier 2 Requirements for Vogtle 3 and 4 ML24253A0722024-08-15015 August 2024 Perspectives on Proposed Removal of Tier 1 and Tier 2 Requirements ML24225A0062024-08-0909 August 2024 NRR E-mail Capture - Acceptance Review - Vogtle 3 and 4 - LAR Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves), Action a and SR 3.7.6.6 (L-2024-LLA-0101) ML24206A0252024-07-20020 July 2024 NRR E-mail Capture - for Your Comments - State of Georgia - Vogtle Unit 1 - Emergency License Amendment Request for Technical Specification 3.7.9 ML24199A1592024-07-17017 July 2024 NRR E-mail Capture - Request for Additional Information - Vogtle 3 and 4 - Exemption for the Requirements in 10 CFR 50.71 Pertaining to the Submittal of Updated Final Safety Analysis Report ML24198A1672024-07-16016 July 2024 NRR E-mail Capture - Acceptance Review Vogtle 3 and 4 - License Amendment Request Changes to Technical Specification 3.7.6, Main Control Room Emergency Habitability System (Ves) Surveillance Requirement L-2024-LLA-0083 ML24197A1572024-07-15015 July 2024 NRR E-mail Capture - Acceptance Review - Farley and Vogtle 1 and 2, LAR - TSTF-589, Eliminate Automatic Diesel Generator Start During Shutdown ML24197A0172024-07-12012 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley and Vogtle 1 and 2 - Alternative Request for Pressurizer Welds ML24194A0032024-07-11011 July 2024 NRR E-mail Capture - Fyi - Acceptance Review - Farley, Hatch, and Vogtle 1 and 2 - Alternative Request for Code Case N-572 ML24180A0012024-06-26026 June 2024 NRR E-mail Capture - Acceptance Review Farley 1 and 2 and Vogtle 1 and 2 - Proposed Inservice Inspection Alternative GEN-ISI-ALT-2024-002 for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) (L-2024-LLR-0041) ML24170A9362024-06-18018 June 2024 NRR E-mail Capture - Fyi - Change to Estimated Completion Date for the SNC Fleet Physical Barrier Exemptions (L-2023-LLE-0018 and L-2023-LLE-0021) ML24178A3422024-05-16016 May 2024 NRR E-mail Capture - Request for Call - Proposed Vogtle 3 & 4 Tier 1 and Tier 2 Exemptions and LAR ML24120A0262024-04-29029 April 2024 COL Docs - FW Vogtle Electric Generating Plant, Unit 4 - Project Manager Reassignment ML24120A0462024-04-29029 April 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24119A0012024-04-28028 April 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Power Ascension Tests ML24108A0132024-04-16016 April 2024 NRR E-mail Capture - (External_Sender) Responses from Wednesday 4/10/2024 Call with Southern Nuclear Operating Co. Vogtle 3&4 Licensing Actions ML24107A9322024-04-15015 April 2024 Document Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection Report 2024-02 ML24107A7292024-04-15015 April 2024 Request for Vogtle Electric Generating Plant Units 1 & 2 - Radiation Protection Inspection - Inspection Report 2024-02 ML24106A0522024-04-12012 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle 1 and 2 - Emergency Diesel Generator (EDG) Voltage and Frequency License Amendment Request (LAR) (L-2024-LLA-0031) ML24100A7842024-04-0909 April 2024 NRR E-mail Capture - for Your Action - Request for Additional Information (RAI) - Vogtle, Units 3 and 4 - Alternative Request for Explosively Actuated Valves (L-2023-LLR-0016) ML24099A0372024-04-0505 April 2024 NRR E-mail Capture - Acceptance Review - Vogtle Unit 3, License Amendment Request (LAR) Technical Specification (TS) 5.5.13, Ventilation Filter Testing Program (VFTP) - L-2024-LLA-0043 ML24095A2412024-04-0404 April 2024 NRR E-mail Capture - Acceptance Review for the Exemption Request Regarding the Final Safety Analysis Report Update Schedule at Vogtle, Units 3 and 4 ML24072A3982024-03-12012 March 2024 NRR E-mail Capture - for Your Action - Second Round Request for Additional Information (RAI) - Vogtle, Unit 1 - SG Tube Inspection Report - 1R24 (L-2023-LRO-0067) ML24061A2372024-03-0101 March 2024 SNC Email Dated March 1, 2024, Regarding SNC Response to NRC Letter for Vogtle 3 & 4 RES Info ML24057A0872024-02-23023 February 2024 NRR E-mail Capture - Acceptance Review - Alternative Request for Explosively Actuated Valves at Vogtle, Units 3 and 4 ML24046A1352024-02-15015 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 - Completion of Initial Criticality and Low-Power Testing ML24039A0882024-02-0808 February 2024 COL Docs - Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1122024-02-0808 February 2024 COL Docs - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24039A1922024-02-0808 February 2024 COL Docs - Correction - Re Fyi - SNC Notification Received of Vogtle Unit 4 Completion of Pre-Critical Tests ML24031A0502024-01-31031 January 2024 COL Docs - FW Erroneous Description of Tier 2 Change Process in Construction Lessons-Learned Report ML24017A1122024-01-17017 January 2024 NRR E-mail Capture - Request for Access to Cyber Security Data - Vogtle, Units 3 and 4 ML23360A0042023-12-23023 December 2023 NRR E-mail Capture - Fyi - Office of Nuclear Regulatory Research (RES) Requests for Vogtle 3 & 4 ML23348A0782023-12-13013 December 2023 NRR E-mail Capture - Voluntary Request for Closed Meeting Regarding Cyber Security Assessments at Vogtle, Units 3 and 4 ML23342A0802023-12-0808 December 2023 NRR E-mail Capture - Request for Additional Information (RAI) - Vogtle, Unit 1 - Review of SG Tube Inspection Report for Refueling Outage 24 (L-2023-LRO-0067) ML23331A9992023-11-27027 November 2023 COL Docs - Re Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23331A9492023-11-26026 November 2023 Email Dated November 26, 2023, from Bo Pham to SNC and NRC - Vogtle Seismic Hazard Report ML23331A9622023-11-22022 November 2023 Email Dated November 22, 2023, from SNC to NRC - Vogtle Seismic Hazard Report ML23326A2802023-11-22022 November 2023 COL Docs - Re Re ML23079A125 - Vogtle Electric Generating Station, Unit 3, NRC Response Letter to P. Durand, Regarding Comment on Federal Register Notice License Amendment No. 189 ML23320A0342023-11-16016 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23320A2372023-11-0808 November 2023 NRR E-mail Capture - (External_Sender) Proposed LAR Regarding the Ultimate Heat Sink at Vogtle, Units 1 and 2 ML23312A2632023-11-0808 November 2023 COL Docs - Action Request for State of Georgia Comment by 5pm Monday, November 13, 2023 - Vogtle Units 3&4, LAR-22-002, TS 3.8.3, Inverters - Operating Completion Time Extension ML23311A1512023-11-0707 November 2023 COL Docs - Re Acceptance Review of Southern Nuclear Operating Company’S License Amendment Request to Remove Combined License Appendix C (EPID No. 2023-LLA-0123) ML23304A2272023-10-31031 October 2023 NRR E-mail Capture - Request for State of Georgia Comment by 5pm Monday, Nov. 6, 2023 - License Amendment Request for Vogtle Unit 4 - to Remove Combined License Appendix C 2024-09-03
[Table view] |
Text
From: John Lamb Sent: Tuesday, January 17, 2023 10:05 AM To: Pournaras, DeLisa S.
Cc: Lowery, Ken G.; Chamberlain, Amy Christine
Subject:
Revised Estimated Hours - Vogtle, Units 1 and 2 - Exemption Request from 10 CFR 50.68 to Allow Use of 6-Weight Percent Enriched Fuel Rods in 4 LTAs (L-2022-LLE-0022)
Importance: High
- DeLisa,
By email dated August 1, 2022 (ML22213A010), the U.S. Nuclear Regulatory Commission (NRC) staff accepted the Southern Nuclear Operating Company (SNC) exemption request for Vogtle Electric Generating Plant (Vogtle), Units 1 and 2. SNC requests a proposed exemption from the provisions of Title 10 of the Code of Federal Regulations (10 CFR), 50.68, Criticality accident requirements, to permit the use of 4 Lead Tests Assemblies (LTAs) with a limited number of fuel rods with a maximum nominal U-235 enrichment of up to six percent by weight.
The NRC staff estimated that it would take approximately 150 hours0.00174 days <br />0.0417 hours <br />2.480159e-4 weeks <br />5.7075e-5 months <br /> to complete this exemption request. The NRC staff is changing its initial estimated hours from 150 hours0.00174 days <br />0.0417 hours <br />2.480159e-4 weeks <br />5.7075e-5 months <br /> to 400 hours0.00463 days <br />0.111 hours <br />6.613757e-4 weeks <br />1.522e-4 months <br />, because this exemption request is more challenging than estimated initially.
Thanks.
John
From: Lamb, John Sent: Monday, August 1, 2022 7:01 AM To: Pournaras, DeLisa S. <DSPOURNA@SOUTHERNCO.COM>
Cc: Lowery, Ken G. <KGLOWERY@southernco.com>
Subject:
Acceptance Review - Vogtle, Units 1 and 2 - Exemption Request from 10 CFR 50.68 to Allow Use of 6-Weight Percent Enriched Fuel Rods in 4 LTAs (L-2022-LLE-0022)
- DeLisa,
By letter dated June 30, 2022 (ML22181B156), Southern Nuclear Operating Company (SNC, the licensee) submitted an exemption request for Vogtle Electric Generating Plant (Vogtle),
Units 1 and 2. SNC requests a proposed exemption from the provisions of Title 10 of the Code of Federal Regulations (10 CFR), 50.68, Criticality accident requirements, to permit the use of 4 Lead Tests Assemblies (LTAs) with a limited number of fuel rods with a maximum nominal U-235 enrichment of up to six percent by weight.
The purpose of this e-mail is to provide the results of the U.S. Nuclear Regulatory Commission (NRC) staffs acceptance review of this [amendment/relief] request. The acceptance review was performed to determine if there is sufficient technical information in scope and depth to allow the NRC staff to begin its detailed technical review. The acceptance review is also intended to identify whether the application has any readily apparent information insufficiencies in its characterization of the regulatory requirements or the licensing basis of the plant.
The NRC staff has reviewed your application and concluded that it does provide technical information in sufficient detail to enable the NRC staff to complete its detailed technical review and make an independent assessment regarding the acceptability of the proposed amendment in terms of regulatory requirements and the protection of public health and safety and the environment. Given the lesser scope and depth of the acceptance review as compared to the detailed technical review, there may be instances in which issues that impact the NRC staffs ability to complete the detailed technical review are identified despite completion of an adequate acceptance review. If additional information is needed, you will be advised by separate correspondence.
Based on the information provided in your submittal and discussions during the pre-licensing meeting on January 27 (ML22028A046), and May 11, 2022 (ML22132A010), the NRC staff has estimated that this licensing request will take approximately 150 hours0.00174 days <br />0.0417 hours <br />2.480159e-4 weeks <br />5.7075e-5 months <br /> to complete. The NRC staff expects to complete this review in approximately one year from the date of this email. If there are emergent complexities or challenges in our review that would cause changes to the initial forecasted completion date or significant changes in the forecasted hours, or review by NRC advisory committees, the reasons for the changes, along with the new estimates, will be communicated during the routine interactions with the assigned project manager.
Additional delay may occur if the submittal is provided to the NRC in advance or in parallel with industry program initiatives or pilot applications.
If you have any questions, please contact me.
John G. Lamb, Senior Project Manager Plant Licensing Branch II-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Hearing Identifier: NRR_DRMA Email Number: 1912
Mail Envelope Properties (MN2PR09MB50849D772B8255A7BBE9F4F1FAC69)
Subject:
Revised Estimated Hours - Vogtle, Units 1 and 2 - Exemption Request from 10 CFR 50.68 to Allow Use of 6-Weight Percent Enriched Fuel Rods in 4 LTAs (L-2022-LLE-0022)
Sent Date: 1/17/2023 10:04:34 AM Received Date: 1/17/2023 10:04:00 AM From: John Lamb
Created By: John.Lamb@nrc.gov
Recipients:
"Lowery, Ken G." <KGLOWERY@southernco.com>
Tracking Status: None "Chamberlain, Amy Christine" <ACCHAMBE@southernco.com>
Tracking Status: None "Pournaras, DeLisa S." <DSPOURNA@SOUTHERNCO.COM>
Tracking Status: None
Post Office: MN2PR09MB5084.namprd09.prod.outlook.com
Files Size Date & Time MESSAGE 4110 1/17/2023 10:04:00 AM
Options Priority: High Return Notification: No Reply Requested: No Sensitivity: Normal Expiration Date: