MONTHYEARML22091A2182022-03-29029 March 2022 BWRVIP-321-A Irradiation Schedule Change Request Project stage: Request ML22101A2802022-04-29029 April 2022 NRC 897, Topical Report Withholding Determination, - BWRVIP-321, Completeness and Proprietary Reviews for BWRVIP-321, BWR and Internals Project, Plan for Extension of the BWR ISP Through SLR Project stage: Other ML22101A2792022-05-0202 May 2022 NRC 898, Topical Report Completeness Determination - BWRVIP-321, Completeness and Proprietary Reviews for BWRVIP-321, BWR and Internals Project, Plan for Extension of the BWR ISP Through SLR Project stage: Other ML22186A0622022-08-0808 August 2022 Draft SE Associated with an Irradiation Schedule Change Request for BWRVIP-321-A, BWR Vessel and Internals Project, Plan for Extension of the BWR ISP Through the Second License Renewal (Slr), (BWRVIP-321) Email-(EPIDs L-2022-TOP-0011; L-202 Project stage: Draft Approval ML22271A7792022-09-26026 September 2022 EPRI, BWRVIP Response to Draft Safety Evaluation Associated with an Irradiation Schedule Change Request to BWRVIP-321-A Project stage: Request ML22320A5552022-11-16016 November 2022 Email - Status of Final Safety Evaluation for Topical Report BWRVIP-321, BWR and Internals Project, Plan for Extension of the BWR Integrated Surveillance Program (ISP) Through the Second License Renewal (SLR) Project stage: Approval ML22290A2032022-12-14014 December 2022 E-mail - Final Safety Evaluation Associated with an Irradiation Schedule Change Request for BWRVIP-321-A, BWR Vessel and Internals Project, Plan for Extension of the BWR ISP Through the Second License Renewal (EPIDs L-2022-TOP-0011; L-2022- Project stage: Approval ML22290A2052022-12-14014 December 2022 Final Safety Evaluation Associated with an Irradiation Schedule Change Request for BWRVIP-321-A, BWR Vessel and Internals Project, Plan for Extension of the BWR ISP Through the Second License Renewal (EPIDs L-2022-TOP-0011; L-2022-NTR-0000) Project stage: Approval ML23135A5002023-05-30030 May 2023 BWRVIP-321, Plan for Extension of the BWR ISP Throug SLR - NRC 896 Project stage: Other ML23135A4342023-05-31031 May 2023 E-mail - Transmittal of the Completed U.S. Nuclear Regulatory Commission Form 896, a Topical Report Verification, Plan for Extension of the BWR ISP Through SLR Project stage: Other 2022-05-02
[Table View] |
Text
From:
Lois James To:
McGruder, Wynter Cc:
Lois James; On Yee; Dan Widrevitz; John Tsao; Adam Rau; Ngola Otto; Santosh Bhatt
Subject:
STATUS of Final Safety Evaluation for Topical Report BWRVIP-321, BWR and Internals Project, Plan for Extension of the BWR Integrated Surveillance Program (ISP) Through the Second License Renewal (SLR)
Date:
Wednesday, November 16, 2022 3:07:07 PM Good afternoon, Wynter,
We just received a request from the Advisory Committee for Reactor Safeguards to review the safety evaluation (SE) for Topical Report BWRVIP-321, BWR and Internals Project, Plan for Extension of the BWR Integrated Surveillance Program (ISP) Through the Second License Renewal (SLR).
We issued the draft SE on August 8, 2022 (Agencywide Documents Access and Management System (ADAMS) Accession No. (ML22186A062) and asked the Electric Power Research Institute (EPRI) if there was any proprietary information in the draft SE.
On September 26, 2022 (ADAMS Accession No. ML22271A779), EPRI confirmed that there was no proprietary information in the SE.
Therefore, I will be making the draft SE publicly available today to support and ACRS committee meeting as soon as possible.
Respectfully,
Lois James, Senior Project Manager Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
ADAMS Nos. Pkg - ML22320A552; Email - ML22320A555; SE - ML22320A556