MONTHYEARML23338A2542023-12-14014 December 2023 Letter - Kairos Power LLC - Issuance of Construction Permit for Hermes Test Reactor ML23328A3972023-11-24024 November 2023 Request for Withholding Information from Public Disclosure - Enclosures of the Construction Permit Application for the Kairos Power, LLC Hermes Non-Power Reactor Facility ML23328A3982023-11-24024 November 2023 Request for Withholding Information from Public Disclosure Kairos Power LLC Postulated Event Analysis Methodology Technical Report, Kp TR 018 P ML23317A1672023-11-17017 November 2023 Request for Withholding Information from Public Disclosure - Kairos Power LLC Response to NRC Question on Salt Spills from Chapters 4 and 13 on Hermes Preliminary Safety Analysis Report ML23317A4202023-11-17017 November 2023 Request for Withholding Information from Public Disclosure - Kairos Power LLC, Response to NRC Question on Decay Heat Removal Testing from Audit on Hermes PSAR Section 6.3 ML23317A4212023-11-17017 November 2023 Request for Withholding Information from Public Disclosure - Kairos Power LLC, Response to NRC Request for Additional Information 350 on Hermes Preliminary Safety Analysis Report ML23317A4232023-11-17017 November 2023 Request for Withholding Information from Public Disclosure - Kairos Power LLC Response to NRC Question on Fluidic Diode Testing and PSAR Chapter 4 Changes ML23321A2442023-11-17017 November 2023 Request for Withholding Information from Public Disclosure - Kairos Power LLC, Changes to Hermes Construction Permit Application Financial Information ML23313A1232023-11-16016 November 2023 Request from Withholding Information from Public Disclosure - Enclosures of the Construction Permit Application for the Kairos Power LLC Non-Power Reactor Facility ML23313A1972023-11-16016 November 2023 Request for Withholding Information from Public Disclosure - Kairos Power LLC Changes to KP-FHR Core Design and Analysis Methodology Technical Report KP-TR-017-P ML23313A2072023-11-16016 November 2023 Request for Withholding Information from Public Disclosure - Kairos Power LLC, Changes to KP-FHR Core Design and Analysis Methodology Technical Report KP-TR-017-P ML23268A0092023-11-0303 November 2023 Kairos Power, LLC - Approval of Kairos Power Safeguards Information Protection Plan ML23310A0742023-11-0202 November 2023 Letter to THC NHPA Section 106 Consultation Summary for the Hermes CP Review Redacted ML23304A2502023-10-25025 October 2023 NHPA Section 106 Consultation Summary for the Kairos Hermes CP Review - Redacted ML23268A3272023-09-25025 September 2023 Letter from EPA Regarding Kairos Hermes CP Feis ML23230A7092023-08-21021 August 2023 Ltr to Alabama-Quassarte Tribal Town, Notification of Issuance of the Feis for the Construction Permit ML23195A0762023-08-17017 August 2023 Issuance of the Final Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor ML23199A0062023-08-17017 August 2023 Letter to USFW Mary Jennings Kairos Hermes CP Review-Notice of Issuance of Final Environmental Impact Statement ML23199A0132023-08-17017 August 2023 Letter to NPS Niki S. Nicholas Kairos Hermes CP Review-Notice of Issuance of Final Environmental Impact Statement ML23199A0292023-08-17017 August 2023 Letter to Achp Blythe Semmer Kairos Hermes CP Review-Notice of Issuance of Final Environmental Impact Statement ML23199A0352023-08-17017 August 2023 Letter to THC E. Patrick Mcintyre Kairos Hermes CP Review-Notice of Issuance of Final Environmental Impact Statement ML23201A1372023-08-17017 August 2023 Letter to Absentee Shawnee Tribe, Notification of Issuance of the Final Environmental Impact Statement for the Construction Permit ML23214A1382023-08-17017 August 2023 Ltr to Alabama-Coushatta Tribe of Texas, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tennessee ML23214A1402023-08-17017 August 2023 Ltr to Cherokee Nation, Notification of Issuance of Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1412023-08-17017 August 2023 Letter to Coushatta Tribe of Louisiana, Notification of Issuance of the Final Environmental Impact Statement for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1422023-08-17017 August 2023 Ltr to Eastern Band of Cherokee Indians, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1492023-08-17017 August 2023 Ltr to Eastern Shawnee Tribe of Oklahoma, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1502023-08-17017 August 2023 Ltr to Jena Band of Choctaw Indians, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1512023-08-17017 August 2023 Ltr to Kialegee Tribal Town, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1532023-08-17017 August 2023 Ltr to Muscogee Creek Nation, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1592023-08-17017 August 2023 Ltr to Poarch Band of Creek Indians, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1602023-08-17017 August 2023 Ltr to Seminole Nation of Oklahoma, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1612023-08-17017 August 2023 Ltr to Seminole Tribe of Florida, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1622023-08-17017 August 2023 Ltr to Shawnee Tribe, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1632023-08-17017 August 2023 Ltr to Thlopthlocco Tribal Town, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23214A1692023-08-17017 August 2023 Ltr to United Keetoowah Band of Cherokee Indians of Oklahoma, Notification of Issuance of the Feis for the Construction Permit for the Kairos Hermes Test Reactor in Oak Ridge, Tn ML23195A0152023-08-17017 August 2023 Letter to Environmental Protection Agency, Notification of the Issuance of the Final EIS for the Construction Permit for Kairos Hermes Test Reactor ML23178A0962023-06-23023 June 2023 Kairos Power, LLC - Supplemental Information for Environmental Report ML23158A2662023-06-13013 June 2023 Transmittal of Safety Evaluation for Hermes Construction Permit Application ML23151A7442023-05-31031 May 2023 Kairos Power, LLC, Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), Revision 3 ML23139A2272023-05-19019 May 2023 Kairos Power LLC, Presentation Materials for the May 22, 2023 Pre?Submittal Meeting on Kairos Power Fuel Qualification Supporting the Hermes Operating License Application ML23117A0482023-04-27027 April 2023 Presentation Materials for Kairos Power Briefing to the Advisory Committee on Reactor Safeguards on Hermes Preliminary Safety Analysis Report ML23118A3232023-04-27027 April 2023 Kairos Power LLC, Submittal of Safeguards Information Protection Plan ML23115A3942023-04-25025 April 2023 Kairos Power, LLC - Transmittal of Changes to Preliminary Safety Analysis Report ML23102A2392023-04-11011 April 2023 Kairos Power LLC, Presentation Materials for Briefing to the Advisory Committee on Reactor Safeguards, Kairos Power Subcommittee on Hermes Preliminary Safety Analysis Report Section 12.9 and Chapter 13 ML23089A3872023-03-30030 March 2023 Kairos Power LLC, Submittal of the Environmental Report for the Kairos Power Fluoride Salt-Cooled, High Temperature Non-Power Reactor (Hermes), Revision 1 ML23088A0682023-03-28028 March 2023 Kairos Power LLC, Transmitatl of Presentation Materials for Kairos Power Briefing to the Advisory Committee on Reactor Safeguards, Subcommittee on Hermes Preliminary Safety Analysis Report Chapters 5, 7, 8, and 11 ML23076A2182023-03-15015 March 2023 Kairos Power, LLC, Presentation Materials for Kairos Power Briefing to the Advisory Committee on Reactor Safeguards, Kairos Power Subcommittee on Hermes Preliminary Safety Analysis Report Chapters 1, 2, 3, 4, 6, and 9 ML23062A7342023-03-13013 March 2023 Transmittal Letter for Final Safety Evaluation of Graphite Material Qualification for the KP-FHR ML23062A7302023-03-13013 March 2023 Transmittal Letter for Final Safety Evaluation of Metallic Material Qualification for the KP-FHR 2023-09-25
[Table view] |
Text
KPNRC2210006 October 12, 2022 Docket No. 507513 US Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 205550001
Subject:
Kairos Power LLC Transmittal of Changes to Preliminary Safety Analysis Report Chapter 4
References:
- 1. Letter, Kairos Power LLC to Document Control Desk, Submittal of the Preliminary Safety Analysis Report for the Kairos Power Fluoride SaltCooled, High Temperature NonPower Reactor (Hermes), Revision 1, September 29, 2022 (ML22272A594)
- 2. Audit Plan, Nuclear Regulatory Commission, Kairos Power, LLC - Plan for a General Audit of The Hermes Construction Permit Application, February 10, 2022 (ML22039A336)
In September 2022, Kairos Power submitted Revision 1 of the Preliminary Safety Analysis Report (PSAR)
(Reference 1) as part of the Construction Permit Application (CPA) for the Hermes nonpower reactor.
This letter transmits changes to the pages of the PSAR to address NRC feedback received on Chapter 4 in the General Audit (Reference 2). Changes to the pages of the PSAR are provided in Enclosure 1. Kairos Power requests NRC review of these changes as part of the continued review of the Hermes CPA.
If you have any questions or need any additional information, please contact Nicole Schlichting at schlichting@kairospower.com or (980) 2159252, or Darrell Gardner at gardner@kairospower.com or (704) 7691226.
I declare under penalty of perjury that the foregoing is true and correct.
Executed on October 12, 2022 Sincerely, Peter Hastings, PE Vice President, Regulatory Affairs and Quality
Enclosures:
Changes to PSAR Chapter 4 Kairos Power LLC www.kairospower.com 707 W Tower Ave, Suite A 5201 Hawking Dr SE, Unit A 2115 Rexford Rd, Suite 325 Alameda, CA 94501 Albuquerque, NM 87106 Charlotte, NC 28211
KPNRC2210006 Page 2 xc (w/enclosure):
William Jessup, Chief, NRR Advanced Reactor Licensing Branch Benjamin Beasley, Project Manager, NRR Advanced Reactor Licensing Branch Edward Helvenston, Project Manager, NRR Advanced Reactor Licensing Branch Samuel Cuadrado de Jesus, Project Manager, NRR Advanced Reactor Licensing Branch Matthew Hiser, Project Manager, NRR Advanced Reactor Licensing Branch