Summary of June 24, 2022, Public Observation Meeting with Constellation Energy Generation, LLC Proposed License Amendment Request to Modify 10 CFR 50.69 License Conditions
ML22227A111
Person / Time
Site: Limerick  Constellation icon.png
Issue date: 08/25/2022
From: Audrey Klett
Plant Licensing Branch 1
To: Rhoades D
Constellation Energy Generation, Constellation Nuclear
Klett A
References
EPID L-2021-LLA-0042
Download: ML22227A111 (5)


Text

August 25, 2022 Mr. David P. Rhoades Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer Constellation Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

LIMERICK GENERATING STATION, UNITS 1 AND 2 -

SUMMARY

OF JUNE 24, 2022, PUBLIC OBSERVATION MEETING WITH CONSTELLATION ENERGY GENERATION, LLC RE: PROPOSED LICENSE AMENDMENT REQUEST TO MODIFY 10 CFR 50.69 LICENSE CONDITIONS (EPID L-2021-LLA-0042)

Dear Mr. Rhoades:

On June 24, 2022, the U.S. Nuclear Regulatory Commission (NRC) staff held a virtual public meeting with representatives from Constellation Energy Generation, LLC.1 The purpose of the meeting was to discuss Constellations planned response to NRCs request for additional information (RAI) 2 relating to Constellations license amendment request (LAR) 3 for Limerick Generating Station, Units 1 and 2. Constellation requested in its LAR to modify the existing Limerick license conditions for Title 10 of the Code of Federal Regulations, Section 50.69 (10 CFR 50.69), Risk-informed categorization and treatment of structures, systems and components for nuclear power reactors. The amendments would allow Constellation to use alternative defense-in-depth (DID), pressure boundary, and seismic categorization processes for treatment of systems, structures, and components per 10 CFR 50.69. The enclosure to this summary contains a list of attendees.

The licensee discussed its proposed responses to RAIs 9, 10, and 11, and 12 pertaining to its DID categorization process. As part of its response to RAI-9.A, the licensee informed the NRC staff that it is now using PWROG-20015-NP, Revision 3 in lieu of Revision 3B, which was posted earlier to the audit portal. In RAI-9.D, the licensee stated that it is using RG 1.200, Revision 2.

The licensee discussed its intent to withdraw the containment (large early release frequency) portion of the proposed DID categorization process via its response to RAI-12 and to continue using NEI 00-04 4 for its containment approach.

1 The meeting notice and agenda, dated June 22, 2022, are available in Agencywide Documents Access and Management System (ADAMS) under Accession No. ML22175A098.

2 The RAI, dated April 19, 2022, is available in ADAMS under ML22103A254.

3 ML21070A412, dated March 11, 2021 4

NEI 00-04, 10 CFR 50.69 SSC Categorization Guideline, Revision 0, July 2005 (ML052910035)

D. Rhoades 2

Regarding the NRC staffs questions on the role of the integrated decisionmaking panel (IDP) in the overall 10 CFR 50.69 categorization process (e.g., increased number of structures, systems, and components (SSCs) that would be categorized as low safety significant per the proposed alternative DID categorization process, apparent increased reliance on the IDP), the licensee stated that the IDP would require reviews from its engineering organization. In response to the staff concerns on over-reliance of the IDP, the licensee introduced a review by the engineering team as an additional step in the process.

The NRC staff did not make any regulatory decisions or commitments at the meeting. The enclosure to this summary lists members from the public that attended the meeting. The NRC staff did not receive any public meeting feedback forms. Please direct any inquiries to me at 301-415-0489 or by e-mail to Audrey.Klett@nrc.gov.

Sincerely,

/RA/

Audrey L. Klett, Senior Project Manager Plant Licensing Branch I Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-352 and 50-353

Enclosure:

List of Attendees cc: Listserv

Enclosure List of Attendees

LIST OF ATTENDEES JUNE 24, 2022, VIRTUAL PUBLIC MEETING WITH CONSTELLATION ENERGY GENERATION, LLC LIMERICK GENERATING STATION, UNITS 1 AND 2 U.S. Nuclear Regulatory Commission Constellation Energy Generation, LLC Mihaela Biro, NRR1/DRA2/APLA3 Stephen Flickinger Jeff Circle, NRR/DRA/APLA Roy R. Linthicum Jim Danna, NRR/DORL4/LPL15 Suzanne Loyd Audrey Klett, NRR/DORL/LPL1 Ashley Rickey Ed Miller, NRR/DORL/LPL2-16 Jeffrey Stone Bob Pascarelli, NRR/DRA/APLA V Sreenivas, NRR/DORL/LPL1 Jensen Hughes Shilp Vasavada, NRR/DRA/APLC7 Brian Nolan Steve Short, PNNL8 David Passehl Mark Wilk, PNNL Charles Young Members of the Public Westinghouse Bradley Dolan, Tennessee Valley Authority Richard W. Rolland, III Alfred Hyde, Dominion Contractor Mary Miller, Dominion Contractor Electric Power Research Institute Doug Kull Patrick ORegan 1 Office of Nuclear Reactor Regulation 2 Division of Risk Assessment 3 Probabilistic Risk Assessment Branch A 4 Division of Operating Reactor Licensing 5 Plant Licensing Branch I 6 Plant Licensing Branch II-1 7 Probabilistic Risk Assessment Branch C 8 Pacific Northwest National Laboratory (NRC contractor)

ML22227A111 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LPL1/LA NRR/DRA/APLA/BC NAME AKlett KZelenock RPascarelli DATE 08/15/2022 08/16/2022 08/15/2022 OFFICE NRR/DORL/LPL1/BC DORL/LPL1/PM NAME HGonzalez AKlett DATE 08/22/2022 08/25/2022