MONTHYEARIR 05000282/20230042024-02-0101 February 2024 Integrated Inspection Report 05000282/2023004 and 05000306/2023004 ML23356A1232024-01-29029 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting) ML24024A0722024-01-24024 January 2024 Independent Spent Fuel Storage Installation, Onticello, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24017A0182024-01-19019 January 2024 Confirmation of Initial License Examination ML23356A0032024-01-17017 January 2024 Issuance of Amendments Revise Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) L-PI-23-034, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System,2024-01-0202 January 2024 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specification 3.7.8, Cooling Water (Cl) System, L-PI-23-035, Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report2023-12-20020 December 2023 Response to Request for Additional Information Regarding License Amendment Request to Revise Technical Specifications Section 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report IR 07200010/20234012023-12-20020 December 2023 Independent Spent Fuel Storage Installation Security Inspection Report 07200010/2023401 ML23349A0572023-12-15015 December 2023 and Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota ML23215A1672023-12-15015 December 2023 Acceptance of Requested Licensing Action Amendment Request to Revise Surveillance Requirement 3.8.1.2 Note 3 IR 05000282/20234012023-12-13013 December 2023 Security Baseline Inspection Report 05000282/2023401 and 05000306/2023401 L-PI-23-033, Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-12-0505 December 2023 Supplement to License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 ML23304A1632023-11-15015 November 2023 Supplemental Information Needed for Acceptance of Requested Licensing Action Amendment Request to Revise SR 3.8.1.2 Note 3 ML23319A3182023-11-15015 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation IR 05000282/20230032023-11-0808 November 2023 Integrated Inspection Report 05000282/2023003 and 05000306/2023003 ML23311A3572023-11-0707 November 2023 Core Operating Limits Report (COLR) for Prairie Island Nuclear Generating Plant (PINGP) Unit 2. Cycle 33. Revision 0 ML23285A3062023-10-12012 October 2023 Implementation of the Fleet Standard Emergency Plan for the Monticello Nuclear Generating Plant and the Prairie Island Nuclear Generating Plant ML23270B9022023-09-29029 September 2023 Review of Reactor Vessel Material Surveillance Program Capsule N Technical Report L-PI-23-025, License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 32023-09-28028 September 2023 License Amendment Request to Revise Technical Specification 3.8.1, Surveillance Requirement 3.8.1.2, Note 3 ML23265A2532023-09-26026 September 2023 Review of Reactor Vessel Material Surveillance Program Capsule N Technical Report ML23262B0372023-09-19019 September 2023 Response to NRC Request for Additional Information Regarding the 2023 Monticello and Prairie Island Plant Decommissioning Funding Status Reports ML23256A1682023-09-13013 September 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Voluntary Security Clearance Program 2023 Insider Threat Program Self-Inspection L-PI-23-023, Baffle Former Bolts Alternate Aging Management Strategy2023-09-11011 September 2023 Baffle Former Bolts Alternate Aging Management Strategy IR 05000282/20230052023-08-30030 August 2023 Updated Inspected Plan for Prairie Island Nuclear Generating Plant Report 05000282/2023005 and 05000306/2023005 IR 05000282/20230102023-08-17017 August 2023 NRC Inspection Report 05000282/2023010 and 05000306/2023010 ML23222A0122023-08-10010 August 2023 Independent Spent Fuel Storage Installation and Monticello Nuclear Generating Plant - Changes in Foreign Ownership, Control or Influence IR 05000282/20230022023-08-0303 August 2023 Integrated Inspection Report 05000282/2023002 and 05000306/2023002 ML23214A2032023-08-0202 August 2023 Request for Information for an NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000282/2024010; 05000306/2024010 ML23206A2342023-07-25025 July 2023 Independent Spent Fuel Storage Installation, and Monticello Nuclear Generating Plant, Changes in Foreign Ownership, Control or Influence ML23202A0032023-07-21021 July 2023 Independent Spent Fuel and Independent Spent Fuel Storage Installation, Monticello Nuclear Generating Plant, Submittal of Quality Assurance Topical Report (NSPM-1) ML23199A0922023-07-18018 July 2023 Notification of NRC Baseline Inspection and Request for Information; Inspection Report 05000306/2023004 ML23195A1732023-07-14014 July 2023 Revision of Standard Practice Procedures Plan L-PI-23-018, License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT2023-07-14014 July 2023 License Amendment Request to Revise ISFSI Technical Specification 4.4 to Allow Use of a Code Alternative to ASME Code, NB-5130, Examination of Weld Edge Preparation Surfaces, for the TN-40HT ML23181A0192023-06-30030 June 2023 Independent Spent Fuel Storage Installation, Revision to Correspondence Service List for Northern States Power - Minnesota ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III L-PI-23-006, License Amendment Request to Revise Technical Specification 3.7.8 Required Actions2023-06-22022 June 2023 License Amendment Request to Revise Technical Specification 3.7.8 Required Actions L-PI-23-016, 2022 10 CFR 50.46 LOCA Annual Report2023-06-14014 June 2023 2022 10 CFR 50.46 LOCA Annual Report IR 05000282/20234202023-06-0101 June 2023 Security Baseline Inspection Report 05000282/2023420 and 05000306/2023420 ML23150A1722023-05-30030 May 2023 Preparation and Scheduling of Operator Licensing Examinations 2024-02-01
[Table view] Category:License-Operating (New/Renewal/Amendments) DKT 50
MONTHYEARML23356A0032024-01-17017 January 2024 Issuance of Amendments Revise Technical Specification 5.6.6, Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR) ML23115A4072023-04-26026 April 2023 Correction of License Amendment Nos. 226 and 214 Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B ML22357A1002023-03-31031 March 2023 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendments Standard Emergency Plan and Consolidated Emergency Operations Facility ML22300A2232022-11-0101 November 2022 Issuance of Amendments 241 and 229 TSTF-577 Revised Frequencies for Steam Generator Tube Inspections ML22181A0002022-08-17017 August 2022 Issuance of Amendments Reactor Trip System Power Range Instrumentation Channels ML22188A0852022-07-15015 July 2022 Correction Letter for Amendments 238 and 226 to Renewed Facility Operating Licenses ML22061A2062022-04-0101 April 2022 Issuance of Amendments TSTF-471, Rev. 1, TSTF-571-T, and Administrative Changes to Technical Specification Section 5.0 ML21312A0212021-11-23023 November 2021 Issuance of Amendment Nos. 237 and 225 Inoperable Cooling Water System Supply Header ML21008A0012021-03-19019 March 2021 Issuance of Amendment Nos. 236 and 224 Low Temperature Overpressure Protection ML20346A0202021-03-15015 March 2021 Issuance of Amendment Nos. 235 and 223, Adoption of Technical Specifications Task Force Traveler TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML20356A0022021-02-0505 February 2021 Issuance of Amendment Nos. 234 and 222, Revise Technical Specifications 3.2.1 and 5.6.5 Identified in Westinghouse Nuclear Safety Advisory Letters NSAL-09-05, Revision 1, and NSAL-15-1 ML20283A3422020-11-18018 November 2020 Issuance of Amendment Nos. 233 and 221 Adoption of Technical Specifications Task Force Traveler TSTF-547, Clarification of Rod Position Requirements ML20217L1852020-10-0202 October 2020 Issuance of Amendment Nos. 232 and 220 Increase the Integrated Leak Rate Test Program Type a and Type C Test Frequency ML20210M0142020-09-0808 September 2020 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendment Nos. 204, 231, and 219 TSTF-529 Clarify Use and Application Rules ML19276F6842019-11-12012 November 2019 Issuance of Amendments 230 and 218 Issuance of Amendments Adoption of 10 CFR 50.69 - Risk Informed Caterization and Treatment of Structure, Systems and Components of Nuclear Power Reactors ML19232A1512019-11-0707 November 2019 Issuance of Amendments Modifying the Design Basis for Quality Classification of Certain Fuel Handling Equipment ML19255H2012019-09-19019 September 2019 Correction Letter for Amendment Nos. 228 and 216 to Renewed Facility Operating License Nos. DPR-42 and DPR-60 ML19225D2172019-08-24024 August 2019 Correction Letter for Amendment Nos 228 and 216 to Renewed Facility Operating License Nos. DPR-42 and DPR-60 ML19140A4472019-07-30030 July 2019 Issuance of Amendments Revision to National Fire Protection Association (NFPA) Standard NFPA 805 Modifications ML19128A1332019-06-0606 June 2019 Issuance of Amendments TSTF-439 Eliminate Second Completion Times Limiting Time from Discovery of Failure to Meet an LCO ML19045A4802019-04-16016 April 2019 Issuance of Amendment Nos. 226 and 214 Adoption of TSTF-425, Revision 3, Relocate Surveillance Frequencies to Licensee Control - RITSTF Initiative 5B ML19029A0942019-01-29029 January 2019 Issuance of Amendment No. 213, One-Time Technical Specification Change to Extend Completion Time for EDGs D5 and D6 (Emergency Circumstances) ML18100A7882018-05-0101 May 2018 Issuance of Amendment Special Heavy Lifting Device Nondestructive Examination Frequency (CAC Nos. MG0072 and MG0073; EPID L-2017-LLA-0280) ML17346A3612018-03-0606 March 2018 Issuance of Amendment Nos. 224 and 211 to Adopt Changes to the Emergency Plan ML17362A2022018-03-0505 March 2018 Issuance of Amendment Concerning Revision to the Prairie Island Nuclear Generating Plant, Units 1 and 2 Emergency Plan (CAC Nos. MF9345 and MF9346; EPID L-2017-LLA-0175) ML17334A1782017-11-30030 November 2017 Issuance of Amendment Request Related to Spent Fuel Pool Criticality Technical Specification Changes (CAC Nos. MF7121 and MF7122, EPID L-2015-LLA-0002) Non-Proprietary ML17310B2392017-11-28028 November 2017 and Prairie Island Nuclear Generating Plant, Units 1 and 2 - Issuance of Amendment Unit Staff Qualifications (CAC Nos. MF9545, MF9546, and MF9547; EPID L-2017-LLA-0195) ML17163A0272017-08-0808 August 2017 Issuance of Amendments Transition to NFPA-805 Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants ML17130A7162017-06-20020 June 2017 Issuance of Amendments Technical Specification 3.8.7 Inverters-Operating ML16256A5142016-10-13013 October 2016 Issuance of Amendment One-Time Extension for Technical Specification Surveillance Requirement 3.8.4.3. DC Sources - Operating ML16133A4062016-06-16016 June 2016 Issuance of Amendment Nos. 217 and 205, Adoption of Technical Specifications Task Force TSTF-523, Revision 2, Generic Letter 2008-01, Managing Gas Accumulation (CAC Nos. MF6449 and MF6450) ML15264A2092015-11-30030 November 2015 Issuance of Amendment Nos. 216 and 204 Regarding Revisions to Technical Specification 3.3.3 and Renewed Facility Operating License ML15229A1762015-08-26026 August 2015 Issuance of Amendment Nos. 215 and 203 Regarding Revision to Licensing Basis Analysis for a Waste Gas Decay Tank Rupture ML15086A0462015-05-21021 May 2015 Issuance of Amendment Nos. 214 and 202 Regarding Revisions to Technical Specification 3.8.1, AC Sources - Operating ML15062A0132015-05-20020 May 2015 Issuance of Amendments 213 and 201 to Revise TS 3.5.3, ECCS - Shutdown ML14239A2572014-11-28028 November 2014 and Prairie Island Nuclear Generation Plant, Units 1 and 2 - Issuance of License Amendments Regarding Cyber Security Plan Implementation Schedule Milestones ML14296A6662014-11-19019 November 2014 Issuance of Amendments Regarding Nuclear Methodology References ML13270A2792014-01-25025 January 2014 Issuance of Amendments Emergency Plan Changes ML13175A2082013-09-11011 September 2013 Issuance of Amendment Exception to Technical Specification 5.5.14 Testing Requirements Associated with Steam Generator Replacement ML13241A3832013-08-29029 August 2013 Issuance of Amendments Spent Fuel Pool Criticality Changes ML13113A4002013-07-0202 July 2013 License Amendments TSTF-510 ML13093A3442013-05-0909 May 2013 License Amendments for Fuel Oil System and TSTF-501 ML1129011152011-12-0101 December 2011 Issuance of Amendments Revision of Technical Specifications 5.2.1, Onsite and Offsite Organizations and TS 5.3, Plant Staff Qualifications. ML1122008562011-10-27027 October 2011 Operating Plant, Units 1 and 2 - Issuance of Amendments Request to Exclude the Dynamic Effects Associated with Certain Postulated Pipe Ruptures from the Licensing Basis Based Upon Application of Leak-Before-Break Methodology ML1119904692011-08-16016 August 2011 Issuance of Amendments Changes to Security Plan ML11187A2312011-07-29029 July 2011 Issuance of Amendment Nos. 202 (for Unit 1) and 189 (for Unit 2) Regarding Cyber Security ML11147A1232011-06-27027 June 2011 Issuance of Renewed Facility Operating Licenses for Prairie Island Nuclear Generating Plant ML11147A1392011-06-27027 June 2011 Enclosure 2: Prairie Island Nuclear Generating Plant, Unit 2, Renewed Facility Operating License ML11147A1372011-06-27027 June 2011 Renewed Facility Operating License ML1034304982011-05-0404 May 2011 Generation Plant, Units 1 and 2 - Issuance of Amendments Use of Beacon Power Distribution Monitoring System (Tac Nos. ME4059 and ME4060) 2024-01-17
[Table view] |
Text
July 15, 2022 Mr. Christopher P. Domingos Site Vice President Prairie Island Nuclear Generating Plant Northern States Power Company Minnesota 1717 Wakonade Drive East Welch, MN 55089
SUBJECT:
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 -
CORRECTION LETTER FOR AMENDMENTS 238 AND 226 TO RENEWED FACILITY OPERATING LICENSES (EPID L-2021-LLA-0069)
Dear Mr. Domingos:
On April 1, 2022, the U.S. Nuclear Regulatory Commission (NRC or the Commission) issued Amendment No. 238 to Renewed Facility Operating License No. DPR-42 and Amendment No. 226 to Renewed Facility Operating License No. DPR-60 for the Prairie Island Nuclear Generating Plant, Units 1 and 2, respectively (Agencywide Documents Access and Management System (ADAMS) Accession No. ML22061A206). The amendments consisted of changes to the technical specification (TSs) regarding incorporation of Technical Specification Task Force (TSTF) travelers TSTF-471 and TSTF-571, as well as administrative changes to TSs Section 5.0 to remove unused pages.
The amendments did not revise any wording in TSs Section 5.0; however, in the course of issuing the revised TS pages, the word year was inadvertently removed from the last sentence in TS 5.5.6, Reactor Coolant Pump Flywheel Inspection Program, on page 5.5-5: of exposed surfaces of the removed flywheels may be conducted at 20 year intervals.
This letter corrects Amendment Nos. 238 and 226 to restore TS 5.5.6 to the wording as approved in Amendment Nos. 170 and 160 when the inspection interval for TS 5.5.6, Reactor Coolant Pump Flywheel Inspection Program, was increased from 10 years to 20 years (ML051510045).
The NRC staff concludes that the error was introduced during the preparation of the license amendments and is entirely editorial in nature. The proposed correction does not change any of the conclusions in the safety evaluation associated with the amendments referenced above and does not affect the associated notices to the public. Enclosed, please find the corrected replacement page.
C. Domingos If you have any questions regarding this matter, please call me at (301) 415-3733.
Sincerely,
/RA/
Robert F. Kuntz, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos. 50-282 and 50-306
Enclosure:
Corrected Page to Amendment No. 238 to DPR-42 and Amendment No. 226 to DPR-60 cc: Listserv
ENCLOSURE PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 DOCKET NOS. 50-282 AND 50-306 CORRECTED PAGE TO LICENSE AMENDMENT NOS. 238 AND 226 RENEWED FACILITY OPERATING LICENSE NO. DPR-42 RENEWED FACILITY OPERATING LICENSE NO. DPR-60
Programs and Manuals 5.5 5.5 Programs and Manuals 5.5.4 Radioactive Effluent Controls Program (continued)
- j. Limitations on the annual dose or dose commitment to any member of the public, beyond the site boundary, due to releases of radioactivity and to radiation from uranium fuel cycle sources, conforming to 40 CFR 190.
The provisions of SR 3.0.2 and SR 3.0.3 are applicable to the Radioactive Effluent Controls Program surveillance frequency.
5.5.5 Component Cyclic or Transient Limit This program provides controls to track the USAR, Section 4.1.4, cyclic and transient occurrences to ensure that components are maintained within the design limits.
5.5.6 Reactor Coolant Pump Flywheel Inspection Program This program shall provide for the inspection of each reactor coolant pump flywheel per the recommendations of Regulatory Position C.4.b of Regulatory Guide 1.14, Revision 1, August 1975. In lieu of Position C.4.b(1) and C.4.b(2), a qualified in-place UT examination over the volume from the inner bore of the flywheel to the circle one-half of the outer radius or a surface examination (MT or PT) of exposed surfaces of the removed flywheels may be conducted at 20 year intervals.
5.5.7 Inservice Testing Program This program provides controls for inservice testing of ASME Code Class 1, 2, and 3 components. The program shall include the following:
Prairie Island Unit 1 - Amendment No. 238 Units 1 and 2 5.5-5 Unit 2 - Amendment No. 226
ML22188A085 OFFICE DORL/LPL3/PM DORL/LPL3/LA DORL/LPL3/BC DORL/LPL3/PM NSalgado NAME RKuntz SRohrer RKuntz (SWall for)
DATE 07/6/2022 07/11/2022 07/15/2022 07/15/2022