Page 1 of 1 DRAFT OUTLINE COMMENTS Facility: BRAIDWOOD STATION Exam Date: JUNE 1 - JUNE 9, 2020 Written Exam Outline (Prepared by NRC)
Comment Resolution G
Two KAs needed to be replaced due to inapplicability and/or inability to write an operationally valid question at the appropriate license level.
Replacement KAs were randomly selected within the applicable category and approved by the Chief Examiner.
G Ensure ES-401-4 has been updated.
Replacement KAs were properly documented on the ES-401-4 form.
Administrative JPM Outline (12/20/2019)
Comment Resolution 1
Ensure RO EP is Significantly modified from the Bank JPM R-406.
This is a new Job Task for newly qualified RO operators. Significantly modified.
2 Ensure SRO EP is Significantly modified from the Bank JPM S-410.
This JPM has been significantly modified from previous JPM.
Control Room / In-Plant System JPM Outline (12/20/2019)
Comment Resolution G No comments.
JPMs significantly different from the written exam admin topics.
Simulator Scenario Outline Comments (12/20/2019)
Comment Resolution G
Per ES-301 D.5.b, To maintain test integrity, every scenario shall be new or significantly modified to ensure that the applicant has not had the opportunity to rehearse or practice the scenario. A significant modification means that, for each scenario, at least two events have not been used on the previous two NRC initial licensing operating exams.
How is it determined that each scenario is new or significantly modified?
The licensee has a database spreadsheet to flag repetitive events from the last two NRC Exams administered, which precludes not having at least 2 new events in each scenario.