  • Public Meeting Slides:

ML22067A067

  • Please log into both the webinar and the bridgeline. Visuals will be through TEAMS, and audio will be through the bridgeline.
  • Bridgeline: 888-566-5975 Passcode: 9449086 then #

MONTICELLO SUBSEQUENT LICENSE RENEWAL PUBLIC MEETING WILL BEGIN SHORTLY Technical contact:

glenna.lappert@nrc.gov 1

Monticello Nuclear Generating Plant Subsequent License Renewal Pre-Application Meeting March 15, 2022 Marieliz Johnson, Safety Project Manager Tam Tran, Environmental Project Manager 2

Meeting Logistics

  • Meeting visuals are through TEAMS
  • Meeting audio is through the bridgeline
  • Public participants are observers in listen-only mode until the public participation session toward the end of the meeting
  • No regulatory decisions will be made at todays meeting 3

Agenda Introduction and Purpose Subsequent License Renewal (SLR)

Overview Environmental Review Overview Environmental Review - Resource Areas Discussion and Question Public Participation 4

Introduction and Purpose

  • Marieliz Johnson, NRR Safety PM Mareiliz.Johnson@NRC.gov 301-415-5861
  • 10 CFR 51.40: (a) A prospective applicant is encouraged to confer with NRC staff as early as possible in its planning process before submitting environmental information or filing an environmental report.

5

NRCs Governing Statutes

- Atomic Energy Act

- National Environmental Policy Act (NEPA)

- Protect Public Health and Safety

- Promote Common Defense and Security

- Protect the Environment Subsequent License Renewal Overview 6

Subsequent License Renewal Overview Environmental Review (10 CFR Part 51)

NRC Renewal Decision (10 CFR 54.29)

Subsequent License Renewal Application (SLRA) Accepted Safety Review (10 CFR Part 54)

ACRS Recommendation (10 CFR 54.25)

Hearings*

10 CFR Part 2

  • If a Request for Hearing is Granted 7

Subsequent License Renewal Env. Review

Environmental Review Considers, evaluates, and discloses environmental impacts of continued plant operation and alternatives to subsequent license renewal Staff review is to determine if the environmental impacts of subsequent license renewal are so great that license renewal would be unreasonable 8

Staff Evaluates Impacts to Resources

- Wildlife and Fish

- Water and Air Resources

- Historical and Cultural Resources

- Taxes, Transportation, Environmental Justice

- Human Health

- Land Use Consultation Environmental Impact Statement 9

HR1

Environment Review Notice of Intent to Prepare EIS Record of Decision 10

11 Environmental Review -

Resource Areas Human Health Terrestrial Resources Air Quality Socioeconomics and Environmental Justice Land Use Historic and Cultural Resources Geologic Resources Aquatic Resources Water Resources

Role of Public Comments on Environmental Review Subsequent License Renewal Decision License Renewal Application Supplemental Environmental Impact Statement Safety Evaluation Report Hearing*

Discussion and Question 13

Public Participation

  • Please press *1 to get in queue to speak
  • State and spell your name and affiliation
  • Press # to return to the meeting
  • The operator will introduce you when it's your turn to speak 14