MONTHYEARML20363A1672020-12-18018 December 2020 Application for Certificate of Compliance for the Industrial Nuclear Company Raw Material Shipping Container, Revision 0, Docket 71-9387 Project stage: Request ML21029A0832021-02-12012 February 2021 Model No. Outer Pack-Raw Material Shipping Container, Revision 0 Application Acceptance Letter Project stage: Acceptance Review ML21147A1662021-06-10010 June 2021 Request for Additional Information for the Model No. Outer Pack-Raw Material Shipping Container, Revision 0 Project stage: RAI ML21216A1762021-08-0303 August 2021 Industrial Nuclear Co., Inc. Responses to Request for Additional Information for Outer Package-Raw Material Shipping Container Package Project stage: Response to RAI ML21323A0982021-11-16016 November 2021 Letter from C. Bollinger, Industrial Nuclear Company, Inc Rmsc SAR Review Delays, November 16, 2021, Docket 07109387 Project stage: Request ML21334A3552021-11-30030 November 2021 Safety Analysis Report Outer Package-Raw Material Shipping Container, Revision 4, November 2021, Docket 71-9387 Project stage: Request ML21348A1152021-12-16016 December 2021 Letter to C. Bollinger Delays in NRC Review of the Inc Outer Package-Raw Material Shipping Container (OP-RMSC) Package Review, Docket 71-9387 Project stage: Approval ML21347A3952022-01-18018 January 2022, 31 January 2022 Revision No. 0 of Certificate of Compliance No. 9387 for the Model No. OP-RMSC Transportation Package Project stage: Request ML21347A3972022-01-18018 January 2022 Letter to M. Rose Re Revision No. 0 of Certificate of Compliance No. 9387 for the Model No. OP-RMSC Transportation Package Project stage: Other 2021-12-16
[Table View] |
|
---|
Category:Letter
MONTHYEARML21347A3972022-01-18018 January 2022 Letter to M. Rose Re Revision No. 0 of Certificate of Compliance No. 9387 for the Model No. OP-RMSC Transportation Package ML21348A1152021-12-16016 December 2021 Letter to C. Bollinger Delays in NRC Review of the Inc Outer Package-Raw Material Shipping Container (OP-RMSC) Package Review, Docket 71-9387 ML21323A0982021-11-16016 November 2021 Letter from C. Bollinger, Industrial Nuclear Company, Inc Rmsc SAR Review Delays, November 16, 2021, Docket 07109387 ML21216A1762021-08-0303 August 2021 Industrial Nuclear Co., Inc. Responses to Request for Additional Information for Outer Package-Raw Material Shipping Container Package ML21216A1772021-08-0303 August 2021 Submittal of Application for Certificate of Compliance for the Inc Rmsc, Revision 1 ML21147A1662021-06-10010 June 2021 Request for Additional Information for the Model No. Outer Pack-Raw Material Shipping Container, Revision 0 ML21029A0832021-02-12012 February 2021 Model No. Outer Pack-Raw Material Shipping Container, Revision 0 Application Acceptance Letter ML20363A1672020-12-18018 December 2020 Application for Certificate of Compliance for the Industrial Nuclear Company Raw Material Shipping Container, Revision 0, Docket 71-9387 2022-01-18
[Table view] |
Text
December 16, 2021
Mr. Charles Bollinger Chief Operating Officer/RSO Industrial Nuclear Company, Inc.
14320 Wicks Blvd San Leandro, CA 94577
SUBJECT:
RE: DELAYS IN NRC REVIEW OF THE INC OUTER PACKAGE-RAW MATERIAL SHIPPING CONTAINER (OP-RMSC) PACKAGE REVIEW, DOCKET 71-9387
Dear Mr. Bollinger :
Your letter dated November 16, 2021 (Agencywide Documents Access and Management System Accession No. ML21334A355), requested the staff reconsider delaying the review of the Outer Pack-Raw Material Shipping Container (Model No. OP-RMSC) package. In your letter you state that as a result of a lack of shipment options, you may be forced out of business by the end of 2021 if the NRC review is delayed much longer. We understand your concerns and have coordinated internally and raised the priority of the review. We are currently in the process of finalizing the certificate and associated safety evaluation report and the current plan is to issue them by early January 2022. I communicated this revised schedule to your quality assurance manager, Mike Rose, by email on November 19, 2022.
If you have any questions regarding this matter, I may be contacted at (301) 415-5196.
Sincerely,
Nishka Devaser, Project Manager Storage and Transportation Licensing Branch Division of Fuel Management Office of Nuclear Material Safety and Safeguards
Docket No. 71-9387 EPID No. L-2020- NEW-0008
ML21348A115 OFFICE DFM DFM DFM NAME NDevaser SFigueroa YDiazSanabria DATE 12/15/ 2021 12/ 16/ 2021 12/ 16/ 2021