MONTHYEARML20363A1672020-12-18018 December 2020 Application for Certificate of Compliance for the Industrial Nuclear Company Raw Material Shipping Container, Revision 0, Docket 71-9387 Project stage: Request ML21029A0832021-02-12012 February 2021 Model No. Outer Pack-Raw Material Shipping Container, Revision 0 Application Acceptance Letter Project stage: Acceptance Review ML21147A1662021-06-10010 June 2021 Request for Additional Information for the Model No. Outer Pack-Raw Material Shipping Container, Revision 0 Project stage: RAI ML21216A1762021-08-0303 August 2021 Industrial Nuclear Co., Inc. Responses to Request for Additional Information for Outer Package-Raw Material Shipping Container Package Project stage: Response to RAI ML21323A0982021-11-16016 November 2021 Letter from C. Bollinger, Industrial Nuclear Company, Inc Rmsc SAR Review Delays, November 16, 2021, Docket 07109387 Project stage: Request ML21334A3552021-11-30030 November 2021 Safety Analysis Report Outer Package-Raw Material Shipping Container, Revision 4, November 2021, Docket 71-9387 Project stage: Request ML21348A1152021-12-16016 December 2021 Letter to C. Bollinger Delays in NRC Review of the Inc Outer Package-Raw Material Shipping Container (OP-RMSC) Package Review, Docket 71-9387 Project stage: Approval ML21347A3952022-01-18018 January 2022, 31 January 2022 Revision No. 0 of Certificate of Compliance No. 9387 for the Model No. OP-RMSC Transportation Package Project stage: Request ML21347A3972022-01-18018 January 2022 Letter to M. Rose Re Revision No. 0 of Certificate of Compliance No. 9387 for the Model No. OP-RMSC Transportation Package Project stage: Other 2021-12-16
[Table View] |
|
---|
Category:Letter
MONTHYEARML21347A3972022-01-18018 January 2022 Letter to M. Rose Re Revision No. 0 of Certificate of Compliance No. 9387 for the Model No. OP-RMSC Transportation Package ML21348A1152021-12-16016 December 2021 Letter to C. Bollinger Delays in NRC Review of the Inc Outer Package-Raw Material Shipping Container (OP-RMSC) Package Review, Docket 71-9387 ML21323A0982021-11-16016 November 2021 Letter from C. Bollinger, Industrial Nuclear Company, Inc Rmsc SAR Review Delays, November 16, 2021, Docket 07109387 ML21216A1762021-08-0303 August 2021 Industrial Nuclear Co., Inc. Responses to Request for Additional Information for Outer Package-Raw Material Shipping Container Package ML21216A1772021-08-0303 August 2021 Submittal of Application for Certificate of Compliance for the Inc Rmsc, Revision 1 ML21147A1662021-06-10010 June 2021 Request for Additional Information for the Model No. Outer Pack-Raw Material Shipping Container, Revision 0 ML21029A0832021-02-12012 February 2021 Model No. Outer Pack-Raw Material Shipping Container, Revision 0 Application Acceptance Letter ML20363A1672020-12-18018 December 2020 Application for Certificate of Compliance for the Industrial Nuclear Company Raw Material Shipping Container, Revision 0, Docket 71-9387 2022-01-18
[Table view] |
Text
November 16, 2021
Nishka Devaser NRC Project Manager NMSS/DSFM/SFLB Office: (301) 415-5196
We have received notice that the RMSC SAR review will be delayed for possibly a minimum of 3 months. As you know, the RMSC was developed to replace the Croft container which we have used for years to transport bulk source material from reactors to our facilities to manufacture encapsulated sources for our customers. Providing radiographic sources to our customers is our primary source of income. INC has been unable to ship material from the reactors since the Croft container became unavailable, until one of our competitors recently loaned us two transport containers. Aside from this instance of kindness from a competitor, there is no other bulk transport container available that we can use. The lack of available bulk material drums has affected our material supply and our business has come to a halt. If the review is not completed, Industrial Nuclear Company may be forced out of business and the doors will likely close by the end of the 2021. I find it a problem that HISTORE CISF is getting a high priority while a small business is getting pushed back.The SAR review has cost our company over $130,000 so far. If we are delayed any longer, the cost to Industrial Nuclear Company could be over $180,000 for material we are required to pay for that the reactor will not be able to ship to us.This will likely result in INCs closing. We are asking for you to please reconsider delaying our review and making it a priority so we can keep Industrial Nuclear company operational.
We are grateful for your immediate consideration of this request and for your agreement to this request.
Respectfully submitted,
Charles Bollinger Chief Operating Officer/RSO Industrial Nuclear Company 510- 352-6767 charlesb@ir100.com