Submittal of Revision 22 to Updated Safety Analysis Report
ML21307A196
Person / Time
Site: Perry FirstEnergy icon.png
Issue date: 10/28/2021
From: Penfield R
Energy Harbor Nuclear Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML21307A174 List:
References
L-21-018
Download: ML21307A196 (8)


Text

I 1111B energy

~

harbor Rod L. Penfield Site Vice President, Perry Nuclear October 28, 2021 L-21-018 ATTN: Document Control Desk U.S. Nuclear Regulatory Commission Washington, DC 20555-001

SUBJECT:

Perry Nuclear Power Plant Docket No. 50-440, License No. NPF-58 Submittal of the Updated Safety Analysis Report, Revision 22 Perry Nuclear Power P/(,lnt IO Center Road.

P.O. Box 97 \\.

In accordance with the requirements of 10 CFR 50.71(e), Energy Harbor Nuclear Corporation (EHNC) is hereby submitting to the Nuclear Regulatory Commission (NRC) the Perry Nuclear Power Plant (PNPP) Updated Safety Analysis Report (USAR),

Revision 22, in CD-ROM format. This submittal reflects facility and procedure changes implemented between April 4, 2019 (the end of Refueling Outage 17), and April 8, 2021 (the end of Refueling Outage 18), along w_ith several changes implemented after Refueling Outage 18.

In accordance with 10 CFR 50.4(b)(6); Revision 22 of the PNPP USAR is submitted electronically on a total replacement basis. As required by NRC guidance for electronic submissions, Attachments 1 and 2 provide a listing of the document components that make up the two enclosed CD-ROMs. In addition to the USAR, the first enclosed CD-ROM includes the Technical Specification (TS) Bases, Revision 13, submitted to satisfy TS 5.5.11, "Technical Specifications (TSs) Bases Control Program," which requires submittal of TS Bases changes implemented without prior NRC approval.

The.second enclosed CD-ROM includes the PNPP USAR, and TS Bases with information identified in accordance with NRC Regulatory Issue Summary (RIS) 2015-17, "Review and Submission of Updates to Safety Analysis Reports, Emergency Preparedness Documents, and Fire Protection Documents," removed. includes a summary of information removed from the USAR in accordance with Appendix A to Nuclear Energy Institute (NEI) 98-03, "Guidelines for Updating Safety Analysis Reports," Revision 1.

J4-0 5 _3 (Vt~

Perry Nuclear Power Plant L-21-018 Page2 includes a summary of regulatory commitment changes to be submitted in accordance with NEI 99 04, "Guidelines for Managing NRC Commitment Changes,"

Revision 0, as endorsed by NRC RIS 2000-17, "Managing Regulatory Commitments Made by Power Reactor Licensees to the NRC Staff."

This certifies, to the best of my judgment and belief, that Revision 22 of the PNPP USAR accurately presents changes made since the previous submittal that are necessary to reflect information and analysis submitted to the Commission or pursuant to Commission requirements.

This submittal contains no new regulatory commitments. If you have any questions regarding this report, please contact Mr. Phil H. Lashley, Manager - Fleet Licensing, at (330) 696-7208.

Attachments:

1.

List of Document Components on CD-ROM 1

2.

List of Document Components on CD-ROM 2 (Information Identified Per RIS 2015-17 Removed)

3.

Information Removed from the PNPP USAR

4.

Commitment Change Summary Report

Enclosures:

A.

Perry Nuclear Power Plant USAR, and Technical Specification Bases

( on CD-ROM 1)

B.

Perry Nuclear Power Plant USAR With Information Identified Per RIS 2015-17 Removed, and Technical Specification Bases (on CD-ROM 2) cc:

NRC Region Ill Administrator (without Enclosure B)

NRC Resident Inspector (without Enclosure B)

NRC Project Manager (without Enclosure B)

L-21-018 List of Document Components on CD-ROM 1 Page 1 of 2 File Name 001 LIST EFF Rev 22.pdf 002 Chapter 00.pdf 003 Chapter 01.pdf 004 Chapter 02.0 to 02.4.pdf 005 Chapter 02.5 to 02E.pdf 006 Chapter 03.pdf 007 Chapter 04.pdf 008 Chapter 05.pdf 009 Chapter 06.pdf 010 Chapter 07.pdf 011 Chapter 08.pdf 012 Chapter 09.pdf 013 Chapter 1 0.pdf 014 Chapter 11.pdf 015 Chapter 12.pdf 016 Chapter 13.pdf 017 Chapter 14.pdf 018 Chapter 15.pdf 019 Chapter 16.pdf 020 Chapter 17.pdf 021 FIG_LIST Rev 22.pdf 022 Figures Section 01.pdf 023 Figures Section 02 (2.1-1 to 2.5-46).pdf 024 Figures Section 02 (2.5-47 to 2.5-49).pdf 025 Figures Section 02 (2.5-50 to 2.5-215).pdf 026 Figures Section 02D-1 to 02D-2.pdf 027 Figures Section 02D-3 to 02E-1.pdf Size 146 KB 856 KB 14,156 KB 14,129 KB 38,219 KB 15,665 KB 13,526 KB 13,848 KB 14,278 KB 13,909 KB 13,660 KB 15,450 KB 13,523 KB 13,800 KB 13,771 KB 13,386 KB 13,763 KB 14,723 KB 57 KB 72 KB 211 KB 17,285 KB 28,300 KB 20,215 KB 26,172 KB 19,648 KB 32,280 KB L-21-018 Page 2 of 2 File Name 028 Figures Section 03.pdf 029 Figures Section 04.pdf 030 Figures Section 05.pdf 031 Figures Section 06.pdf 032 Figures Section 07.pdf 033 Figures Section 08.pdf 034 Figures Section 09 (9.1-1 to 9.4-29).pdf 035 Figures Section 09 (9.5-1 to 9.5-26).pdf 036 Figures Section 09 (9A-1 to 9A-34).pdf 037 Figures Section 1 0.pdf 038 Figures Section 11.pdf 039 Figures Section 12.pdf 040 Figures Section 13.pdf 041 Figures Section 14.pdf 042 Figures Section 15.pdf 043 PNPP TS Bases Rev 13.pdf Size 39,005 KB 1,560 KB 4,989 KB 7,730 KB 10,280 KB 3,142 KB 19,597 KB 4,324 KB 9,790 KB 16,875 KB 2,660 KB 18,237 KB 145 KB 241 KB 5,587 KB 955 KB L-21-018 List of Document Components on CD-ROM 2 (Information Identified Per RIS 2015-17 Removed)

File Name 001 LIST _EFF Rev 22.pdf 002 Chapter 00.pdf 003 Chapter 01.pdf 004 Chapter 02.0 to 02.4.pdf 005 Chapter 02.5 to 02E.pdf 006 Chapter 03.pdf 007 Chapter 04.pdf 008 Chapter 05.pdf 009 Chapter 06.pdf 010 Chapter 07.pdf 011 Chapter 08.pdf 012 Chapter 09.pdf 013 Chapter 1 0.pdf 014 Chapter 11.pdf 015 Chapter 12.pdf 016 Chapter 13.pdf 017 Chapter 14.pdf 018 Chapter 15.pdf 019 Chapter 16.pdf 020 Chapter 17.pdf 021 FIG_LIST Rev 22.pdf 022 Figures Section 01.pdf Page 1 of 2 023 Figures Section 02 (2.1-1 to 2.5-46).pdf 024 Figures Section 02 (2.5-47 to 2.5-49).pdf 025 Figures Section 02 (2.5-50 to 2.5-215).pdf 026 Figures Section 02D-1 to 02D-2.pdf 027 Figures Section 02D-3 to 02E-1.pdf Size 121 KB 1,008 KB 14,156 KB 14,129 KB 38,219 KB 15,665 KB 13,526 KB 13,848 KB 14,278 KB 13,909 KB 13,660 KB

. 15,450 KB 13,523 KB 13,800 KB 13,771 KB 13,386 KB 13,763 KB 14,723 KB 57 KB 72 KB 211 KB 5,433 KB 28,300 KB 20,215 KB 26,171 KB 19,648 KB 32,280 KB L-21-018 Page 2 of 2 File Name 028 Figures Section 03.pdf 029 Figures Section 04.pdf 030 Figures Section 05.pdf 031 Figures Section 06.pdf 032 Figures Section 07.pdf 033 Figures Section 08.pdf 034 Figures Section 09 (9.1-1 to 9.4-29).pdf 035 Figures Section 09 (9.5-1 to 9.5-26).pdf 036 Figures Section 09 (9A-1 to 9A-34).pdf 037 Figures Section 1 0.pdf 038 Figures Section 11.pdf 039 Figures Section 12.pdf 040 Figures Section 13.pdf 041 Figures Section 14.pdf 042 Figures Section 15.pdf 043 PNPP TS Bases Rev 13.pdf Size 27,846 KB 1,560 KB 4,989 KB 7,540 KB 10,280 KB 2,746 KB 18,370 KB 4,324 KB 616 KB 16,875 KB 2,660 KB 1,968 KB 145 KB 241 KB 5,587 KB 955 KB L-21-018 Information Removed from the PNPP USAR Page 1 of 1 In accordance with Nuclear Energy Institute (NEI) 98-03, Revision 1, "Guidelines for Updating Safety Analysis Reports," licensees periodically report a brief description of information removed from the Updated Safety Analysis Report (USAR) and the basis for its removal. The following provides a summary of the information removed from the PNPP USAR and the basis for removal.

1. The acronym "FENOC" was removed throughout the USAR for occasions that referred to the FENOC Quality Assurance Program Manual (QAPM) or other
  • programs such as the corrective action program. These programs are company programs required by regulations. Rewording from "FENOC" to "company" is simply rewording text without changing the scope, meaning, or level of detail.

Letters, programs, and manuals that previously included FENOC are now referred to as "company." Where appropriate, when referring to the specific name, "FENOC" was replaced with "Energy Harbor Nuclear Corp." and "FirstEnergy" was replaced with "Energy Harbor Corp." Section 4.5.1.4.1 contained information relative to General Electric engineering representation that is beyond the level of necessary detail and is not important to providing and understanding the plant's design and operation from either a general or system functional perspective.

2. Removed obsolete information from Section 13.1.1.2, Table 13.1-1, and Figure 13.1-2 related to the Perry Engineering Organization. The Manager, Technical Services Engineering, and Manager, Plant Engineering, are obsolete position titles that no longer reflect the current organization. These positions have been consolidated into one position, Manager, Strategic Engineering. The responsibilities assigned to the engineering organization have not changed but have been rearranged to reflect the current organizational structure. Section 13.1.1.2 contained descriptive information that is not important to providing and understanding the plant's design and operation from either a general or system functional perspective.

COMMITMENT NUMBER/SOURCE/DATE PY-L02090 PY-CEI/NRR-1861 L, 9/20/1994 NRG BL 90-01, Supplement 1, 12/22/1992 List of Abbreviations Used:

BL Bulletin L-21-018 Commitment Change Summary Report Page 1 of 1 COMMITMENT DESCRIPTION A current special pressure transient check, which would identify transmitter failure due to loss of sensor fill-oil, will remain in calibration procedures after the enhanced 24 month monitoring program is completed.

CHANGE Closed.

NRG Nuclear Regulatory Commission REASON FOR CHANGE The subject transmitters associated with this commitment have been replaced with those that are not susceptible to the failure mechanism (loss of fill-oil) identified in NRG BL 90-01, Supplement 1. As replacement of the transmitters with a non-susceptible transmitter was the alternative to maintaining an enhanced surveillance program per BL 90-01, Supplement 1, the commitment is no longer applicable.