ML21305A104

From kanterella
Jump to navigation Jump to search
Submittal of Updated Final Safety Analysis Report, Revision 26
ML21305A104
Person / Time
Site: Diablo Canyon  Pacific Gas & Electric icon.png
Issue date: 10/11/2021
From: Gerfen P
Pacific Gas & Electric Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML21306A142 List: ... further results
References
DCL-21-074
Download: ML21305A104 (15)


Text

Enclosure 3 contains Sensitive Information - Withhold Under 10 CFR 2.390 When separated from Enclosure 3, this cover letter is decontrolled.

Pacific Gas and Electric Company" Paula Gerten Diablo Canyon Power Plant Site Vice President Mail code 104/6/605 P.O. Box 56 Avila Beach, CA 93424 805.545.4596 Internal: 691.4596 Fax: 805.545.4234 PG&E Letter DCL-21-074 U.S. Nuclear Regulatory Commission 10 CFR 50.4 ATTN: Document Control Desk 10 CFR 50.54 Washington, DC 20555-0001 10 CFR 50.71 Docket No. 50-275, OL-DPR-80 Docket No. 50-323, OL-DPR-82 Diablo Canyon Power Plant Units 1 and 2 Submittal of Updated Final Safety Analysis Report, Revision 26

Dear Commissioners and Staff:

Pursuant to 10 CFR 50.71(e), 10 CFR 50.54(a)(3), and 10 CFR 50.4(b)(6), Pacific Gas ano Electric Company (PG&E) hereby submits Diablo Canyon Power Plant (DCPP) "Updated Final Safety Analysis Report" (UFSAR), Revision 26. contains a summary of changes to the UFSAR resulting from 10 CFR 50.59 evaluations. Enclosure 2 provides a list of license amendments that resulted in changes incorporated into Revision 26 of ~he DCPP UFSAR. contains the DCPP UFSAR, Revision 26, including the drawings listed on UFSAR Table 1.6-1, on one Digital Versatile Disc (DVD), labeled "Diablo Canyon Power Plant UFSAR,,Revision 26 (non-redacted), dated September 2021." The contents are in Adobe Acrobat portable document format. Enclosure 3 contains sensitive information and should be withheld from public disclosure in accordance with 10 CFR 2.390(d)(1). provides a list of the information that has been redacted in accordance with NRG Regulatory Issue Summary (RIS) 2015-17, "Review and Submission of Updates to Final Safety Analysis Reports, Emergency Preparedness Documents, and Fire Protection Documents." contains one DVD for DCPP UFSAR, Revision 26, with the redacted information identified in Enclosure 4 removed. This DVD is labeled, "Diablo Canyon Power Plant UFSAR, Revision 26 (redacted), dated S,eptember 2021."

A member of the STARS Alliance Callaway

  • Diablo Canyon
  • Palo Verde
  • Wolf Creek Enclosure 3 contains Sensitive Information - Withhold Under 10 CFR 2.390 When separated from Enclosure 3, this cover letter is decontrolled.

Enclosure 3 contains Sensitive Information - Withhold Under 10 CFR 2.390 When separated from Enclosure 3, this cover letter is decontrolled.

Document Control Desk PG&E Letter DCL--21-074 Page2 contains a description of the information that has been removed from the UFSAR in accordance with Appendix A of Nuclear Energy Institute (NEI)

Guideline 98-03, Revision 1, "Guidelines for Updating Final Safety Analysis .

Reports." Deletions and additions are identified by revision bars on the right side of the associated pages of the UFSAR.

PG&E makes no new or revised regulatory commitments (as defined by NEI 99-04) in this letter.

If you have any questions regarding this submittal, please contact Mr. Jim Morris at (805) 545-4609.

This certifies, to the best of my judgement and belief, that Revision 26 of the DCPP UFSAR accurately presents changes that were incorporated into the UFSAR as of May 2021.

Sincerely, Paula Gerten Site Vice President armb/50943987-03 Enclosures cc: Diablo Distribution cc/enc: Samson S. Lee, NRG Project Manager Scott A. Morris, NRG Region IV Administrator Winston C. Smith, Acting NRG Senior Resident Inspector A member of the STARS Alliance Callaway o Diablo Canyon

  • Palo Verde
  • Wolf Creek Enclosure 3 contains Sensitive Information - Withhold Under 10 CFR 2.390 When separated from Enclosure 3, this cover letter is decontrolled.

Enclosure 1 PG&E Letter DCL-21-074 Changes Incorporated into the Diablo Canyon Power Plant Updated Final Safety Analysis Report, Revision 26 Resulting from 10 .CFR 50.59 Evaluations

Enclosure 1 PG&E Letter DCL-21-074 Changes Incorporated into the Diablo Canyon Power Plant Updated Final Safety Analysis Report, Revision 26 Resulting 1from 10 CFR 50.59 Evaluations LBIE Description Number1 1l

)

2020-013 Adoption of the Tornado Missile Risk Evaluator (TMRE) Methodology.

2021-002 Accept for use as-is nonconforming structural steel welds that were accepted usinq an alternate visual weld inspection criteria.

<1l 10 CFR 50.59 Licensing Basis Impact Evaluation Number Page 1 of 1

Enclosure 2 PG&E Letter DCL-21-074 License Amendments (LAs) that Resulted in Changes Incorporated into Revision 26 of the DCPP Updated Final Safety Analysis Report

Enclosure 2 PG&E Letter DCL-21-074 License Amendments (LAs) that Resulted in Changes Incorporated into Revision 26 of the DCPP Updated Final Safety Analysis Report Unit 1 Unit 2 Description LA LA 234 236 Incorporation of FULL SPECTRUM LOCA Methodology (EPID L-2018-LLA-0730) 235 237 Changes to the Intake Structure Physical Security Classification (EPID L-2019-LLA-0029) 237 239 Relocate Technical Specification 5.3, "Unit Staff Qualifications," to the Updated Final Safety Analysis Report (EPID L-2019-LLA-0268)

Page 1 of 1

Enclosure 3 contains Sensitive Information - Withhold Under 10 CFR 2.390 Enclosure 3 PG&E Letter DCL-21-074 The DVD in this enclosure contains the following files:

File Name File Size (Mb)

Chapter 1 3.96 Chapter 2 25.0 Chapter 3 30.3 Chapter 4 4.81 Chapter 5 3.38 Chapter 6 15.0 Chapter 7 1.91 2.65 _

Chapter 8 Chapter 9 7.20 Chapter 10 .944 Chapter 11 3.87 Chapter 12 3.52 Chapter 13 .516 Chapter 14 1.32 Chapter 15 16.8 Chapter 16 .100 Chapter 17 1.38 Table 1.6-1 Drawings 701 Enclosure 3 contains Sensitive Information - Withhold Under 10 CFR 2.390 Page 1 of 1

Enclosure 3 contains Sensitive Information - Withhold Under 10 CFR 2.390 Enclosure 3 PG&E Letter DCL-21-074 Digital Versatile Disc Diablo Canyon Power Plant Diablo Canyon Power Plant Updated Final Safety Analysis Report, Revision 26 (non-redacted), dated September 2021 Enclosure 3 contains Sensitive Information - Withhold Under 10 CFR 2.390

Enclosure 4 PG&E Letter DCL-21-074 List of Information Redacted from Updated Final Safety Analysis Report, Revision 26 in Accordance with RIS 2015-17

Enclosure 4 PG&E Letter DCL-21-074 List of Information Redacted from Updated Final Safety Analysis Report, Revision 26 in Accordance with RIS 2015-17 Information Withheld Description Figures 6.2-53, 6.2-54, 6.2-55, and 6.2-56 Containment subcompartment analyses drawings.

Figures 12.1-1, 12.1-2, 12.1-3, 12.1-4, 12.1- Radiation zone maps that contain 5, 12.1-6, 12.1-7, 12.1-8, 12.1-9, 12.1-10, general arrangement features.

12.1-11, 12.1-12 Drawings: Engineering drawings 57722-1, 57723-1, 57724-1, 57725-1, incorporated by reference.

57726-1, 57727-1, 57728-1, 500966-1, I 500971-1, 500977-1, 515939-1, 515940-1, 515941-1, 515942-1, 515947-1, 521123-1, 521124-1, 500968-1, 57721-1, 57720-1, 57719-1, 57718-1, 500967-1, 500965-1, 500964-1, 57729-1 , 57730-1 , 57731-: 1, 57732-1, 57733-1, 57734-1; 500969-1, 500972-1, 500973-1, 500974-1, 500976-1, 102023-6, 108023-6, 102023-8, 108023-8, 102023-9, 108023-9, 102023-11, 108023-11, 102023-12, 108023-12, 102023-16, 102023-17C, 102023-17, 102023-18, 108023-18, 515943-1, 515944-1, 515945-1, 515946-1, 515948-1, 515949-1, 438431-1, 438432-1, 439533-1 , 438449-1 , 438445-1 ,

507613-1, 521120-1, 521130-1, 521121-1, 521131-1, 521122-1, 521132-1, 521133-1, 521134-1, 521125-1, 521135-1, 508845-1, 500002-1, 500852-1,498992-1,498993-1, 500003-1, 500853-1, 663082-2, 502699-1 Proprietary Drawings: Engineering d_rawings 6006510-7, 6006510-14, 6006510-21, incorporated by reference.

6006510-22, 6006510-23, 6006510-61, 6006510-156, 6006510-132, 6006510-133, 6006510-155, 6006510-134(2 of 3),

6006510-134(3 of 3), 6006510-65, 6006510-135, 6023231-1, 6021770-30, 6021770-22, 6021770-19,6021770-5 Page 1 of 1

Enclosure 5 PG&E Letter DCL-21-074 The DVD in this enclosure contains the following files:

File Name File Size (Mb) 3.96 Chapter 1 25.0 Chapter 2 30.3 Chapter 3 Chapter 4 4.81 3.38 Chapter 5 14.0 Chapter 6 1.91 Chapter 7 2.65 Chapter 8 7.20 Chapter 9

.944 Chapter 10 3.87 Chapter 11 1.13 Chapter 12

.516 Chapter 13 1.32 Chapter 14 16.8 Chapter 15 Chapter 16 .100 1.38 Chapter 17 602 Table 1.6-1 DrawinQs Page 1 of 1

Enclosure 6 PG&E Letter DCL-21-074 Description of Information Removed from Revision 26 of the Updated Final Safety Analysis Report

Enclosure 6 PG&E Letter DCL-21-074 Description of Information Removed from Revision 26 of the Updated Final Safety Analysis Report Chapter 15 Section Description of Change Tables 15.3-1 15.3-2 15.4.1-1A 15.4.1-1B 15.4.1-2A 15.4.1-2B Tables removed due to the adoption of the Tornado Missile Risk 15.4.1-3A Evaluator Methodology.

15.4.1-3B 15.4.1-4A 15.4.1-4B 15.4.1-5A 15.4.1-5B 15.4.1-?A 15.4.1-7B Figures removed due to the adoption of the Tornado Missile Risk Evaluator Methodology.

Figures 15.1-6 15.3-1 15"3-2 15.3-3 15.3-4 15.3-8 15.3-9 15.3-11 15.3-13 15"3-33 15.3-34 15.3-35 15.3-36 15.3-37 15.3-38 15.3-39 15.3-40 15.3-41 Page 1 of 2

Enclosure 6 PG&E Letter DCL-21-074 Figures (continued) 15.4.1-1A 15.4.1-18 15.4.1-2A Figures removed due to the adoption of the Tornado Missile Risk ,

15.4.1-28 Evaluator Methodology.

15.4.1-3A 15.4.1-38 15.4.1-4A 15.4.1-48 15.4.1-5A 15.4.1-58 15.4.1-6A 15.4.1-68 15.4.1-7A 15.4.1-78 15.4.1-SA 15.4.1-88 15.4.1-9A 15.4.1-98 15.4.1-10A 15.4.1-108 15.4.1-11A 15.4.1-118 15.4.1-12A 15.4.1-128 15.4.1-13A 15.4.1-138 15.4.1-14A 15.4.1-148 15.4.1-15A 15.4.1-158 Page 2 of 2