Submittal of Braidwood Unit 2 - Pressure and Temperature Limits Report (PTLR) Revision 8
ML21300A075
Person / Time
Site: Braidwood Constellation icon.png
Issue date: 10/27/2021
From: Keenan J
Exelon Generation Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
Shared Package
ML21300A074 List:
References
BW210065
Download: ML21300A075 (1)


Text

Exelon Generation October 27, 2021 BW210065 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Braidwood Station, Unit 2 Renewed Facility Operating License No. NPF-77 NRC Docket No. 50-457

~~

>>IOP~~fjlJ.. ~&l

~.

II.. OOilW"1161fi

Subject:

Braidwood Unit 2 - Pressure and Temperature Limits Report (PTLR), Revision 8

Reference:

1) Letter from U.S. NRC to B.C. Hanson (Exelon Generation Company, LLC),

Braidwood Station, Units 1 and 2, and Byron Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 217, 217, 221, and 221 Regarding Reactor Coolant System Pressure and Temperature Limits Report Technical Specifications (EPID L-2019-LLA-0215)," dated September 18, 2020

2) Letter from U.S. NRC to B.C. Hanson (Exelon Generation Company, LLC),

"Braidwood Station, Units 1 and 2, and Byron Station, Unit Nos.1 and 2 Exemption from the Requirements of 10 CFR 50.61 and 10 CFR 50, Appendix G (EPID L-2019-LLE-0022)," dated August 31, 2020 The purpose of this letter is to transmit the Pressure and Temperature Limits Report (PTLR) for Braidwood Station, Unit 2 in accordance with Technical Specification (TS) 5.6.6, "Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)."

Braidwood Station, Unit 2 TS 5.6.6, "Reactor Coolant System (RCS) Pressure and Temperature Limits Report (PTLR)," was revised to allow the use of AREVA NP Topical Report BAW-2308, Revisions 1-A and 2-A, "Initial RT Nor of Linde 80 Weld Materials" for determining RCS pressure-temperature limits.

Please direct any questions you may have regarding this matter to Mr. Kevin Lueshen, Regulatory Assurance Manager, at (815) 417-2800.

Sincerely,

Keenan, John P.

John Keenan t Digitally signed by Keenan, John

,y.

/

,:QJ>l;,~=Keenan,John P.

l Dat~2021.1 0.24 07:58:45 -05'00' Site Vice President Braidwood Station

Attachment:

Braidwood Unit 2 Pressure and Temperature Limits Report (PTLR), Revision 8