Letter Sequence Request |
---|
EPID:L-2022-LLA-0121, Updated Final Safety Analysis Report (Ufsar), Revision 16 and Fire Protection Report (Fpr), Revision 25 (Open) |
|
MONTHYEARML21298A2082021-10-21021 October 2021 Updated Final Safety Analysis Report (Ufsar), Revision 16 and Fire Protection Report (Fpr), Revision 25 Project stage: Request RS-22-005, Response to Request for Additional Information for the GNF3 Fuel Transition License Amendment Request2022-01-11011 January 2022 Response to Request for Additional Information for the GNF3 Fuel Transition License Amendment Request Project stage: Response to RAI RS-22-006, Request to Expand Applicability of Prime Methods to Evaluate Fuel Centerline Melt and Cladding Strain Compliance for Framatome Fuel2022-01-20020 January 2022 Request to Expand Applicability of Prime Methods to Evaluate Fuel Centerline Melt and Cladding Strain Compliance for Framatome Fuel Project stage: Request RS-22-028, Supplement to Request to Expand Applicability of Prime Methods to Evaluate Fuel Centerline Melt and Cladding Strain Compliance for Framatome Fuel at Quad Cities2022-03-16016 March 2022 Supplement to Request to Expand Applicability of Prime Methods to Evaluate Fuel Centerline Melt and Cladding Strain Compliance for Framatome Fuel at Quad Cities Project stage: Request RS-22-040, Response to Request for Additional Information Related to the License Amendment Request to Transition to GNF3 Fuel2022-04-11011 April 2022 Response to Request for Additional Information Related to the License Amendment Request to Transition to GNF3 Fuel Project stage: Response to RAI RS-22-065, License Amendment Request Regarding Transition to GNF3 Fuel2022-08-18018 August 2022 License Amendment Request Regarding Transition to GNF3 Fuel Project stage: Request ML22258A1872022-09-13013 September 2022 NRR E-mail Capture - NRC Acceptance Review Dresden, Units 2 and 3, Amendment Request - Transition to GNF3 Fuel Project stage: Acceptance Review ML22335A5652022-12-14014 December 2022 Audit Plan to Support the Review of Licensee'S Information Related to Equipment Qualification License Amendment Request for Transition to GNF3 Fuel Project stage: Other ML23019A0132023-01-12012 January 2023 NRR E-mail Capture - Final RAI Dresden 2 and 3 - License Amendment Pertaining to GNF3 Fuel Transition Project stage: RAI RS-23-004, Response to Request for Additional Information Regarding Transition to GNF3 Fuel License Amendment Request2023-01-23023 January 2023 Response to Request for Additional Information Regarding Transition to GNF3 Fuel License Amendment Request Project stage: Response to RAI ML23088A2242023-04-0505 April 2023 Regulatory Audit Report Regarding License Amendment Request to Transition to GNF3 Fuel Project stage: Other RS-23-057, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-04-17017 April 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel Project stage: Supplement RS-23-070, Supplement to License Amendment Request Regarding Transition to GNF3 Fuel2023-05-16016 May 2023 Supplement to License Amendment Request Regarding Transition to GNF3 Fuel Project stage: Supplement ML23144A3142023-07-0606 July 2023 Issuance of Amendment Nos. 281 and 274 Transition to GNF3 Fuel (EPID L-2022-LLA-0121) - Nonproprietary Project stage: Approval ML23192A6292023-07-11011 July 2023 Correction Letter - Issuance of Amendment Nos. 281 and 274 Regarding Transition to GNF3 Fuel (EPID L-2022-LLA-0121) (Non-Proprietary) Project stage: Approval 2022-09-13
[Table View] |
|
---|
Category:Fire Protection Plan
MONTHYEARML22042B3102021-10-21021 October 2021 4 to Fire Protection Report - Volume 2_Redacted ML22042B3052021-10-21021 October 2021 5 to Fire Protection Report - Volume 1 - Redacted ML21298A2082021-10-21021 October 2021 Updated Final Safety Analysis Report (Ufsar), Revision 16 and Fire Protection Report (Fpr), Revision 25 ML20015A4362020-01-15015 January 2020 Revision 24 to Fire Protection Report, Volume 2 - Redacted ML20015A4332020-01-15015 January 2020 Revision 24 to Fire Protection Report, Volume 1 - Redacted RS-19-098, Submittal of Revision 15 to Updated Final Safety Analysis Report, and Revision 24 to Fire Protection Report2019-10-21021 October 2019 Submittal of Revision 15 to Updated Final Safety Analysis Report, and Revision 24 to Fire Protection Report ML19241B3362019-08-29029 August 2019 Ltr. 08/29/19 Quad Cities Nuclear Power Station, Units 1 and 2 - Notification of NRC Triennial Fire Protection Baseline Inspection Request for Information 05000254/2019013; 05000265/2019013 (DRS-A.Dahbur) ML18012A6662017-10-19019 October 2017 Revision 23 to Fire Protection Report, Vol. 1 Redacted 2021-10-21
[Table view] Category:Letter
MONTHYEARIR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 ML24004A0052024-01-17017 January 2024 Exemption from Select Requirements of 10 CFR Part 73 (EPID L-2023-LLE-0042 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) RS-24-001, Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2024-01-0303 January 2024 Response to Request for Additional Information Regarding Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 ML23349A1622023-12-17017 December 2023 Issuance of Amendment Nos. 298 and 294 Increase Completion Time in Technical Specification 3.8.1.B.4 (Emergency Circumstances) RS-23-128, Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-15015 December 2023 Response to Request for Additional Information for the Emergency License Amendment Request Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days ML23305A1402023-12-13013 December 2023 Units 1 & 2; Nine Mile Point, Unit 2; Peach Bottom, Units 2 & 3; and Quad Cities, Units 1 and 2 - Issuance of Amendments to Adopt Traveler TSTF-580 RS-23-123, Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days2023-12-13013 December 2023 Emergency License Amendment Request - Increase Technical Specifications Completion Time in TS 3.8.1.B.4 from 7 Days to 30 Days ML23339A1762023-12-0505 December 2023 Notification of NRC Baseline Inspection and Request for Information (05000265/2024001) ML23319A3342023-11-20020 November 2023 Regulatory Audit in Support of License Amendment Requests to Adopt TSTF 505, Revision 2 and 10 CFR 50.69 RS-23-104, Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML23317A1192023-11-10010 November 2023 Constellation Energy Generation, LLC - 2023 Annual Report - Guarantees of Payment of Deferred Premiums IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 RS-23-113, Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 262023-10-20020 October 2023 Submittal of Updated Final Safety Analysis Report (Ufsar), Revision 17 and Fire Protection Report (Fpr), Revision 26 RS-23-097, Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans2023-10-12012 October 2023 Constellation Energy Generation, LLC, Advisement of Leadership Changes and Submittal of Updated Standard Practice Procedures Plans ML23206A0382023-09-21021 September 2023 Proposed Alternative to the Requirements of the ASME Code IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 RS-23-089, Sixth Ten-Year Interval Inservice Testing Program2023-09-0505 September 2023 Sixth Ten-Year Interval Inservice Testing Program RS-23-080, Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs2023-08-30030 August 2023 Constellation Energy Generation, LLC, Application to Revise Technical Specifications to Adopt TSTF-264-A, Revision 0, 3.3.9 and 3.3.10 - Delete Flux Monitors Specific Overlap Requirement SRs RS-23-086, Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval2023-08-28028 August 2023 Relief Request I5R-26, Inservice Inspection Program Relief Request Regarding Examination Coverage for the Fifth Inservice Inspection Interval SVP-23-038, Owner'S Activity Report Submittal Fifth 10-Year Interval 2023 Refueling Outage Activities2023-08-14014 August 2023 Owner'S Activity Report Submittal Fifth 10-Year Interval 2023 Refueling Outage Activities IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 ML23178A0742023-08-0707 August 2023 Issuance of Amendment Nos. 296 and 292 Adoption of TSTF-416 Low Pressure Coolant Injection (LPCI) Valve Alignment Verification Note Location ML23216A0362023-08-0707 August 2023 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and RFI ML23216A0562023-08-0404 August 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 SVP-23-031, Regulatory Commitment Change Summary Report2023-07-14014 July 2023 Regulatory Commitment Change Summary Report ML23181A1062023-06-30030 June 2023 Postponement- Information Meeting (Open House) with a Question-And-Answer Session to Discuss NRC 2022 End-Of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station ML23178A2422023-06-28028 June 2023 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief in the Division of Operating Reactor Licensing for Plant Licensing Branch III ML23179A1932023-06-28028 June 2023 07122023 Letter-Significant Public Meeting to Discuss NRC End-of-Cycle Performance Assessment of Quad Cities Nuclear Plant for Performance for 2022 Calendar Year IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter RS-23-077, Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations2023-06-16016 June 2023 Response to NRC Regulatory Issue Summary 2023-01, Preparation and Scheduling of Operator Licensing Examinations ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter RS-23-060, Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors2023-06-0808 June 2023 Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors RS-23-059, License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b2023-06-0808 June 2023 License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion Times - RITSTF Initiative 4b ML23144A3632023-05-26026 May 2023 Information Meeting (Open House) with a Question and Answer Session to Discuss NRC 2022 End-of-Cycle Plant Performance Assessment of Quad Cities Nuclear Power Station, Units 1 and 2 RS-23-042, Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling2023-05-25025 May 2023 Application to Revise Technical Specifications to Adopt TSTF-580, Provide Exception from Entering Mode 4 with No Operable RHR Shutdown Cooling ML23033A4042023-05-15015 May 2023 Exemption from the Requirements of 10 CFR Part 2, Section 2.109(B) Related to Submission of Subsequent License Renewal Application Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 ML23132A2022023-05-12012 May 2023 Annual Radiological Environmental Operating Report ML23125A0612023-05-0808 May 2023 Proposed Alternative to the Requirements of the ASME Code IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 RS-22-067, 10 CFR 50.46 Annual Report2023-05-0404 May 2023 10 CFR 50.46 Annual Report ML23118A3472023-05-0101 May 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Correction of Amendment No. 193 Adoption of TSTF-306, Revision 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration EPID L-2022-LLA-0143 RS-23-068, Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell2023-04-28028 April 2023 Response to Request for Additional Information for Quad Cities Relief Request I6R-11, Proposed Alternatives for a Temper Bead Weld Repair of the Mating Surfaces of the Reactor Pressure Vessel Head and Shell SVP-23-018, Radioactive Effluent Release Report for 20222023-04-28028 April 2023 Radioactive Effluent Release Report for 2022 ML23114A2522023-04-28028 April 2023 Request to Use a Provision of a Later Edition of the ASME Boiler & Pressure Vessel Code, Section XI ML23110A0622023-04-25025 April 2023 Transmittal of Final Quad Cities Nuclear Power Plant, Unit 1 Accident Sequence Precursor Report (Licensee Event Report 254-2022-001) ML23081A0382023-04-25025 April 2023 County, 1 & 2; Nine Mile Point, 2; and Quad Cities, 1 & 2 - Issuance of Amendments to Adopt TSTF-306, Rev. 2, Add Action to LCO 3.3.6.1 to Give Option to Isolate the Penetration 2024-02-05
[Table view] Category:Updated Final Safety Analysis Report (UFSAR)
MONTHYEARML21300A2722021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 07 - Instrumentation and Controls ML21300A2682021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 01 - Introduction and General Description of Plant ML22042B3082021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 13 - Conduct of Operations-Redacted ML22042B3052021-10-21021 October 2021 5 to Fire Protection Report - Volume 1 - Redacted ML21300A2742021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 11 - Radioactive Waste Management ML21300A2652021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 17 - Quality Assurance ML21300A2662021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 08 - Electric Power ML21300A2692021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, List of Affected Pages ML22042B3062021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 02 - Site Characteristics - Redacted ML21300A2642021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 14 - Initial Test Program ML21300A2552021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 05 - Reactor Coolant System and Connected Systems ML21300A2582021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 09 - Auxiliary Systems ML21298A2082021-10-21021 October 2021 Updated Final Safety Analysis Report (Ufsar), Revision 16 and Fire Protection Report (Fpr), Revision 25 ML21300A2602021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 15 - Accident and Transient Analyses ML21300A2622021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 04 - Reactor ML22041A8442021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 06 - Engineered Safety Features-Redacted ML22042B3072021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 03 - Design of Structures, Components, Equipment and Systems-Redacted ML21300A2612021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 16 - Technical Specifications ML22042B3102021-10-21021 October 2021 4 to Fire Protection Report - Volume 2_Redacted ML21300A2702021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 10 - Steam and Power Conversion System ML21300A2562021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Chapter 12 - Radiation Protection ML21300A2632021-10-21021 October 2021 6 to Updated Final Safety Analysis Report, Appendix a ML21196A0082021-07-15015 July 2021 Redacted - Dresden, Updated Final Safety Analysis Report, Chapter 2, Site Characteristics ML20015A4292020-01-15015 January 2020 UFSAR Revision 15 Chapter 6 Engineered Safety Features - Redacted ML20015A4262020-01-15015 January 2020 UFSAR Revision 15 Chapter 3 Design of Structures, Components, Equipment and Systems - Redacted ML20015A4232020-01-15015 January 2020 UFSAR Revision 15 Chapter 2 Site Characteristics - Redacted ML20015A4132020-01-15015 January 2020 UFSAR Revision 15 Chapter 13 Conduct of Operations - Redacted RS-19-109, Submittal of Amended Update to Quad Cities Nuclear Power Station Updated Final Safety Analysis Report (Ufsar), Revision 152019-11-13013 November 2019 Submittal of Amended Update to Quad Cities Nuclear Power Station Updated Final Safety Analysis Report (Ufsar), Revision 15 RS-19-098, Submittal of Revision 15 to Updated Final Safety Analysis Report, and Revision 24 to Fire Protection Report2019-10-21021 October 2019 Submittal of Revision 15 to Updated Final Safety Analysis Report, and Revision 24 to Fire Protection Report ML17298A3612017-10-19019 October 2017 Revision 14 to Updated Final Safety Analysis Report, Chapter 16, Technical Specifications RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 8, Electric Power2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 8, Electric Power RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 7, Instrumentation and Controls2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 7, Instrumentation and Controls RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 5, Reactor Coolant System and Connected Systems2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 5, Reactor Coolant System and Connected Systems RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 4, Reactor2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 4, Reactor RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 1, Introduction and General Description of Plant2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 1, Introduction and General Description of Plant RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, List of Effective Pages2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, List of Effective Pages RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Submittal of Rev. 14 to Updated Final Safety Analysis Report and Rev. 23 to Fire Protection Report2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Submittal of Rev. 14 to Updated Final Safety Analysis Report and Rev. 23 to Fire Protection Report RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 10, Steam and Power Conversion System ML17298A3632017-10-19019 October 2017 Revision 14 to Updated Final Safety Analysis Report, Chapter 17, Quality Assurance ML18012A6772017-10-19019 October 2017 Revision 14 to Updated Final Safety Analysis Report, Chapter 2, Site Characteristics Redacted ML18012A6892017-10-19019 October 2017 Revision 14 to Updated Final Safety Analysis Report, Fire Protection Report Vol. 2 Redacted ML18016A2542017-10-19019 October 2017 UFSAR - 6.0 Safety Features Table of Contents Redacted ML18016A2792017-10-19019 October 2017 UFSAR - 13.0 Conduct of Operations Table of Contents Redacted RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 9, Auxiliary Systems RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 11, Radioactive Waste Management2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 11, Radioactive Waste Management RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 12, Radiation Protection2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 12, Radiation Protection ML17298A3582017-10-19019 October 2017 Revision 14 to Updated Final Safety Analysis Report, Chapter 14, Initial Test Program ML17298A3532017-10-19019 October 2017 Revision 14 to Updated Final Safety Analysis Report, Chapter 12, Radiation Protection RS-17-126, Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 16, Technical Specifications2017-10-19019 October 2017 Quad Cities Nuclear Power Station, Units 1 & 2, Revision 14 to Updated Final Safety Analysis Report, Chapter 16, Technical Specifications ML17298A3512017-10-19019 October 2017 Revision 14 to Updated Final Safety Analysis Report, Chapter 11, Radioactive Waste Management 2021-07-15
[Table view] |
Text
4300 Winfield Road Warrenville, IL 60555 630 657 2000 Office RS-21-107 10 CFR 50.71(e) 10 CFR 54.37(b)
October 21, 2021 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265
Subject:
Quad Cities Updated Final Safety Analysis Report (UFSAR), Revision 16 and Fire Protection Report (FPR), Revision 25 In accordance with the requirements of 10 CFR 50.71, "Maintenance of records, making of reports," paragraph (e)(4), Exelon Generation Company (EGC), LLC submits Revision 16 to the Updated Final Safety Analysis Report (UFSAR) for Quad Cities Nuclear Power Station, Revision 25 to the Fire Protection Report (FPR), and a summary of evaluations conducted pursuant to 10 CFR 54.37(b), "Additional records and recordkeeping requirements." Summary of evaluations conducted pursuant to 10 CFR 50.59 "Changes, tests, and experiments," are submitted under separate cover.
The UFSAR is being submitted on Optical Storage Media (OSM) in its entirety, including documents incorporated by reference (Technical Requirements Manual, Technical Specifications Bases, and the FPR). UFSAR pages changed as a result of this update are delineated with "Revision 16, October 2021" in the page footer.
Attachment A provides a brief summary of the changes incorporated into UFSAR Revision 16.
Attachment B provides a brief summary of the changes incorporated into FPR Revision 25.
Attachment C provides the summary report pursuant to 10 CFR 54.37(b).
Attachment D contains the directory path, filename, and size of each individual file included on the OSM.
October 21, 2021 U. S. Nuclear Regulatory Commission Page 2 One (1) OSM is enclosed in this submission. The OSM labeled, "Exelon Generation - Quad Cities Nuclear Power Station - UFSAR Revision 16 - FPR Revision 25 - October 2021, contains the following components:
001 QDC UFSAR Rev 16.pdf, 55.4 MegaBytes (MB) 002 QDC FPR Rev 25.pdf, 4.12 MB 003 QDC TRM.pdf, 2.98 MB 004 QDC Tech Spec Bases.pdf, 2.37 MB As required by 10 CFR 50.71(e)(2)(i), I certify that to the best of my knowledge, the information contained in the Enclosure and attachments to this letter accurately reflect information and analyses submitted to the NRC or prepared pursuant to NRC requirements, and changes made under the provisions of 10 CFR 50.59.
There are no new commitments made in this document. Should you have any questions concerning this letter, please contact:
Amy Hambly Exelon Generation 4300 Winfield Road Warrenville, IL 60555 Phone: (630) 657-2808 amy.hambly@exeloncorp.com Respectfully, Gullott, Digitally signed by Gullott, David M.
David M. Date: 2021.10.21 11:20:49 -05'00' David M. Gullott Director - Licensing
Enclosure:
OSM - Exelon Generation - Quad Cities Nuclear Power Station - UFSAR Revision 16 -
FPR Revision 25 - October 2021 Attachments:
Attachment A - Updated Final Safety Analysis Report (UFSAR) - Revision 16 Change Summary Report Attachment B - Fire Protection Report (FPR) - Revision 25 Change Summary Report Attachment C - 10 CFR 54.37(b) Aging Management Review Summary Attachment D - OSM Directory Structure cc: Regional Administrator - NRC Region III NRC Senior Resident Inspector - Quad Cities Nuclear Power Station NRC Project Manager, NRR - Quad Cities Nuclear Power Station
QUAD CITIES STATION Attachment A Updated Final Safety Analysis Report (UFSAR)
Revision 16 Change Summary Report 19-R16-002, Revision to UFSAR Section 7.3 Revised to add information regarding the installation of 4 keylock switches to defeat the Primary Containment Isolation System (PCIS) Group I signal prior to reaching -59 reactor water level.
19-R16-003, Revision to UFSAR Sections 6.0, 6.2, 6.3, 13.3, & 15.6. Also revises Tables 15.6-5b, 15.6-7, 15.6-8a, 15.6-9 and Figure 15.6-7 Revised to add information about the increased MSIV leakage limits and separates total containment leakage allowable from MSIV leakage as related to the Appendix J testing.
19-R16-004, Revision to UFSAR Section 9.1 Revised to update the discussion of nucleate boing to align with the Extended Power Upgrade (EPU) GE spent fuel analysis.
19-R16-005, Revision to UFSAR Sections 9.1 and 12.3 Revised to utilize 10CFR50.68 in lieu of exemption from 10CFR70.24.
19-R16-006, Revision to UFSAR Section 9.4 Revised to remove excessive detail in the system description of computer room ventilation.
19-R16-007, Revision to UFSAR Section 11.5 and Figure 11.5-1 Revised to change the Off Gas Isolation Valve (holdup valve) from fail-closed to fail-open. It also shows that the valve does not have redundant instrument air solenoid valve.
19-R16-009, Revision to UFSAR Section 8.2 and Table 8.3-1 Revised to add information on the new Unit 2 Unit aux transformer.
19-R16-010, Revision to UFSAR Section 3.5 Revised to add a new section 3.5.4.1, Missile Impact Evaluation for additional discussion/clarification on impact of missiles on exterior walls. Also added new section 3.5.4.2, Tornado Missile Protection that includes discussion on applicable reviews associated with tornado protection.
19-R16-011, Revision to UFSAR Table 1.2-3 Revised to remove lift station from the balance of plant batteries.
19-R16-012, Revision to UFSAR Section 6.2 and 9.3, Tables 1.8-1 and 6.2-7, and Appendix A Revised to add reference to NEI 94-01 and adds a notation to several valves in Table 6.2-7. In Section 9.3 removed sentence regarding LLRT of two containment isolation check valves. Also removed Reg Guide 1.163 requirement from Table 1.8-1 and Appendix A.
19-R16-013, Revision to UFSAR Section 8.3 Revised to address the change in open phase detection relay configuration per a plant modification.
19-R16-014, Revision to UFSAR Table 6.2-7 Revised to update primary containment isolation valve information.
1 of 2
QUAD CITIES STATION Attachment A Updated Final Safety Analysis Report (UFSAR)
Revision 16 Change Summary Report 19-R16-015, Revision to UFSAR Sections 6.3 and 15.0 and Tables 6.3-3E, 6.3-12E, 6.3-14D, 6.3-19D Revised to update the new LOCA and MAPLHGR analysis performed for the Unit 2 Cycle 26 nuclear fuel reload. Section 15.0 was updated to support use of the infrequent event categorization for lost parts capable for causing high percentage of flow orifice blockage and other editorials changes.
19-R16-016, Revision to UFSAR Section 7.6 Revised to add calibration intervals controlled by the Surveillance Frequency Control Program (SFCP).
19-R16-017, Revision to UFSAR Section 6.3 and Figure 6.3-41A Revised the wetwell pressure in the figure and other administrative changes to align the UFSAR with the approved peak primary containment internal pressure and the max allowable containment leakage rate.
19-R16-018, Revision to UFSAR Section 13.1 & 13.2 Revised to change standard ANSI N18.1-1971 to ANSI/ANS 3.1-2014 revision and associated dates and document title 19-R16-019, Revision to UFSAR Table 8.3-1 Revised to change from SF6 to vacuum for Bus 13 breakers.
19-R16-020, Revision to UFSAR Table 6.2-7 Revised to table to add notation to the test class column and various notes for various types of testing for different valves. In addition, editorial changes to fields and column names were made.
19-R16-021, Revision to UFSAR Sections 1.2 and 11.4 Revised the description of solid wastes stored at the Interim Spent Fuel Storage Installation (ISFSI).
19-R16-023, Revision to UFSAR Section 8.3 and Table 8.3-1 Revised to add additional EDG overload ratings.
19-R16-025, Revision to UFSAR Sections 4.1, 4.2, 4.3, 4.4, 5.2, 6.3, 15.4, 15.8 and Tables 4.1-1, 5.1-1, 6.3-3E, 6.3012E, 6.3-14D, and 6.3-19D Revised to update the new LOCA and MAPLHGR analysis for the Unit 1 fuel cycle.
19-R16-026, Revision to UFSAR Section 8.3 Revised to add a 120/240 VAC output transformer and discussion on the UPS system arrangement.
19-R16-027, Revision to UFSAR Section 7.7 and Figure 4.3-9 Revised to correct references to the Reactor Recirculation MG sets which were replaced with Adjustable Speed Drives (ASD) several years ago.
19-R16-028, Revision to UFSAR Section 2.2 Revised to remove reference to the sulfuric acid tank and sodium hydroxide tank that were once located in the turbine building trackway.
19-R16-029, Revision to UFSAR Appendix A Revised to add newly identified EQ components to the License Renewal section.
19-R16-030, Revision to UFSAR Table 6.2-7 Revised to add notes regarding the Reactor Building to Suppression Chamber vacuum breakers 2 of 2
QUAD CITIES STATION Attachment B Fire Protection Report (FPR)
Revision 25 Change Summary Report Revision Summary:
Fire Protection Report Change Packages25-001, 25-003,25-004.
Volume 1 (Fire Hazards Analysis):
- 1. Change 25-001: EC 629295 Editing the fire zone sizes in the plant to more accurately account for total area of each fire zone.
Many changes were made throughout section 4.3.
- 2. Change 25-002: Intentionally left blank
- 3. Change 25-003: No EC Editing to remove the electrical supervision requirements from the FHA. Changes made on section 2.1-11 and 5.5-7.
- 4. Change 25-004: EC 618590 Editing to incorporate Trackway 2 expansion structure into FHA. Table 3.3-1 and 3.3-2 as well as sections 4.2 and 4.3 were updated to account for these changes.
Volume 2 (Safe Shutdown Report):
- 1. No changes were made to the SSA.
1 of 1
QUAD CITIES STATION Attachment C 10 CFR 54.37(b) Aging Management Review Summary In accordance with 10 CFR 54.37(b) and the guidance specified in Regulatory Issue Summary 2007-16, Revision 1, Implementation of the Requirements of the 10 CFR 54.37(b) for Holders of Renewed Licenses, the UFSAR update required by 10 CFR 50.71 must include any Structures, Systems or Components (SSCs) newly identified that would have been subject to an aging management review or evaluation of time-limited aging analyses in accordance with 10 CFR 54.21. This UFSAR update must describe how the effects of aging will be managed such that the intended function(s) in 10 CFR 54.4(b) will be effectively maintained during the period of extended operation.
The 10 CFR 54.37(b) review of changes to the plant Current Licensing Basis covered the period of August 2, 2019 to August 17, 2021. The review included:
- Engineering Changes that were installed or completed since the last UFSAR update,
- UFSAR pending change descriptions and revised text, and
No newly identified SSCs were identified that require aging management or evaluation of TLAAs in accordance with the License Renewal Rule. Therefore, there are no associated updates required to the Quad Cities UFSAR described Aging Management Programs.
1 of 1
QUAD CITIES STATION Attachment D OSM Directory Structure Directory Path File Name Size 001 QDC UFSAR Rev 16 000 List of Effective Pages.pdf 203 KB 001 QDC UFSAR Rev 16 001 Chap 01 Introduction.pdf 386 KB 001 QDC UFSAR Rev 16 002 Chap 02 Site Characteristics.pdf 1337 KB 001 QDC UFSAR Rev 16 003 Chap 03 Design of Structs, Compnts, Equip.pdf 9065 KB 001 QDC UFSAR Rev 16 004 Chap 04 Reactor.pdf 6997 KB 001 QDC UFSAR Rev 16 005 Chap 05 Reactor Coolant Sys.pdf 2489 KB 001 QDC UFSAR Rev 16 006 Chap 06 Engineered Safety Features.pdf 13989 KB 001 QDC UFSAR Rev 16 007 Chap 07 Instrumentation and Controls.pdf 3528 KB 001 QDC UFSAR Rev 16 008 Chap 08 Electric Power.pdf 795 KB 001 QDC UFSAR Rev 16 009 Chap 09 Auxiliary Systems.pdf 9095 KB 001 QDC UFSAR Rev 16 010 Chap 10 Steam and Power Conversion.pdf 571 KB 001 QDC UFSAR Rev 16 011 Chap 11 Radioactive Waste Mgmt.pdf 2697 KB 001 QDC UFSAR Rev 16 012 Chap 12 Radiation Protection.pdf 425 KB 001 QDC UFSAR Rev 16 013 Chap 13 Conduct of Operations.pdf 716 KB 001 QDC UFSAR Rev 16 014 Chap 14 Initial Test Program.pdf 1164 KB 001 QDC UFSAR Rev 16 015 Chap 15 Accident and Transient Analyses.pdf 2888 KB 001 QDC UFSAR Rev 16 016 Chap 16 Technical Specifications.pdf 36 KB 001 QDC UFSAR Rev 16 017 Chap 17 Quality Assurance.pdf 49 KB 001 QDC UFSAR Rev 16 018 Appendix A.pdf 292 KB 002 QDC FPR Rev 25 001 QDC FPR VOL 1.pdf 3215 KB 002 QDC FPR Rev 25 002 QDC FPR VOL 2.pdf 1003 KB 003 QDC TRM 001 QDC TRM.pdf 3053 KB 004 QDC Tech Spec Bases 001 QDC Tech Spec Bases.pdf 2431 KB 1 of 1