ND-21-0288, ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.v.a (Index Number 809)

From kanterella
(Redirected from ML21291A250)
Jump to navigation Jump to search
ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.v.a (Index Number 809)
ML21291A250
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 10/18/2021
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ITAAC 3.3.00.07d.v.a, ND-21-0288
Download: ML21291A250 (6)


Text

<< Michael J. Vox 7825 River Road Qr>>l lfl-i£iKn Ml Regulatory Affairs Director Waynesboro, GA 30830 DUULIICrn INULICdr Vogtie3&4 706-848-6459 tel OCT 1 8 2021 Docket No.: 52-025 ND-21-0288 10 CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.v.a [Index Number 8091 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant(VEGP)

Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 3.3.00.07d.v.a [Index Number 809]. This ITAAC verified for areas inside containment that non-Class IE wiring which is not separated from Class 1E or associated wiring by the minimum separation distance or by a barrier or analyzed is treated as Class 1E wiring.

The closure process for this ITAAC is based on the guidance described in NEI-08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52" which is endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company(SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli Roberts at 706-848-6991.

Respectfully submitted.

Michael J. Vox Regulatory Affairs Director Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of ITAAC 3.3.00.07d.v.a [Index Number 809]

MJY/CMK/sfr

U.S. Nuclear Regulatory Commission ND-21-0288 Enclosure Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III Mr. D. L. McKlnney Mr. H. Nieh Mr. M. D. Meier Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. M. J. Vox Mr. A. S. Parton Ms. K. A. Roberts Ms. J.M. Coleman Mr. C. T. Defnall Mr. C. E. Morrow Mr. K. J. Drudy Mr. J. M. Fisher Mr. R. L. Belike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 Nuclear Regulatory Commission Ms. M. Bailey M M. King M G. Bowman Ms. A. Veil M C. P. Patel M G. J. Khourl M C. J. Even M B. J. Kemker Ms. N. C. Coovert M C. Welch M . J. Gaslevic M . O. Lopez-Santiago M . G. Armstrong M . M. Webb M . T. Fredette M . C. Santos M . B. Davis M . J. Vasquez M . J. Eargle M . E. Davidson M . T. Fanelll Ms. K. McCurry Mr. J. Parent Mr. B. Griman

U.S. Nuclear Regulatory Commission ND-21-0288 Enclosure Page 3 of 3 Mr. V. Hall Oqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Orlani Mr. D. 0. Durham Mr. M. M. Corletti Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., CDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Batch Bingham

U.S. Nuclear Regulatory Commission ND-21-0288 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-21-0288 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 ITAAC Closure Notification on Completion of ITAAC 3.3.00.07d.v.a [Index Number 809]

U.S. Nuclear Regulatory Commission ND-21-0288 Enclosure Page 2 of 3 ITAAC Statement Desion Commitment 7.d) Physical separation is maintained between Class 1E divisions and between Class 1E divisions and non-Class 1E cables.

Inspections. Tests. Analvses Inspections of the as-built raceways that route Class 1E cables will be performed to confirm that the separation between raceways that route Class 1E cables of different divisions, and between raceways that route Class 1E cables and raceways that route non-Class1 E cables is consistent with the following:

v) Non-Class 1E wiring that is not separated from Class 1E or associated wiring by the minimum separation distance or by a barrier or analyzed is considered as associated circuits and subject to Class 1E requirements.

Acceptance Criteria Results of the inspection will confirm that the separation between raceways that route Class 1E cables of different divisions, and between raceways that route Class 1E cables and raceways that route non-Class 1E cables is consistent with the following:

v.a) For areas inside containment, non-Class 1E wiring that is not separated from Class 1E or associated wiring by the minimum separation distance or by a barrier or analyzed is treated as Class 1E wiring.

ITAAC Determination Basis Multiple ITAAC are performed to ensure that physical separation is maintained between Class 1E divisions and between Class 1E divisions and non-Class 1E cables. In accordance with this ITAAC, non-Class 1E wiring that is not separated from Class 1E or associated wiring by the minimum separation distance and for which no barrier or analysis is provided is considered as associated circuits and subject to Class 1E requirements. The subject ITAAC requires inspections of the Class 1E and non-Class 1E raceways inside containment to confirm that non-Class 1E wiring that is not separated from Class 1E or associated wiring by the minimum separation distance or by a barrier or analyzed is considered as associated circuits and subject to Class 1E requirements. The Class 1E cables and raceways and non-Class1E cables inside containment are designed to be appropriately separated in accordance with APP-GW-E1-001 (Reference 1). Installation specifications provided to the constructor identify separation criteria, consistent with the ITAAC commitment.

Class 1E electrical cables and raceways are required to be installed in accordance with design drawings, installation specifications issued for construction, and work package requirements.

Completed raceway installation, in-progress and completed cable installation, and completed cable terminations are inspected to ensure the separation installation specifications are satisfied. Inspections are performed in accordance with the Construction Quality Verification Program 26139-000-4MP-T81C-N7101 (Reference 2). ITAAC 3.3.00.07d.ii.a [Index 800] will confirm that inspection records are completed to document the satisfactory separation between

U.S. Nuclear Regulatory Commission ND-21-0288 Enclosure Page 3 of 3 raceways that route Class 1E cables of different divisions, and between raceways that route Class 1E cables and raceways that route non-Class 1E cables.

Cable Separation Report for Associated Circuits (Reference 3)confirmed that the separation between raceways that route Class 1E cables of different divisions, and between raceways that route Class 1E cables and raceways that route non-Class 1E cables is consistent with the following:

For areas inside containment, non-Class 1E wiring that is not separated from Class 1E or associated wiring by the minimum separation distance or by a barrier or analyzed is considered as associated circuits and subject to Class 1E requirements.

There are associated circuits in containment at the Incore Instrument Thimble Assembly at the Class 1E Core Exit Thermocouple from the Non-Class 1E Signal Processing System (Reference 4).

The Cable Separation Report for Associated Circuits (Reference 3) is available for NRC inspection as part of the Unit 3 ITAAC 3.3.00.OTd.v.a Completion Packages (Reference 5).

ITAAC Finding Review In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company(SNC) performed a review of all ITAAC findings and associated corrective actions.

This review found no relevant ITAAC findings associated with this ITAAC.

ITAAC Compietion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 3.3.00.07d.v.a was performed for VEGP Unit 3 and that the prescribed acceptance criteria are met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

References favaiiabie for NRC inspection)

1. APP-GW-E1-001, "Electrical Systems Design Criteria"
2. 26139-000-4MP-T81C-N7101,"Bechtel Construction Quality Verification Program"
3. SV3-CSR-ITR-800809 Rev 0,"Unit 3 Cable Separation Report for Associated Circuits"
4. APP-GW-EOR-006,"IEEE 384 Design Compliance Description"
5. 3.3.00.07d.v.a-U3-CP-Rev0, ITAAC Completion Package