ML21244A497

From kanterella
Jump to navigation Jump to search
Response to Contested Violation and Final White Finding and Revised Notice of Violation Inspection Report 0500333/2021090
ML21244A497
Person / Time
Site: FitzPatrick Constellation icon.png
Issue date: 09/03/2021
From: David Lew
NRC Region 1
To: Rhoades D
Exelon Generation Co
Erin Carfang
Shared Package
ML21244A495 List:
References
EA-20-138 IR 2021090
Download: ML21244A497 (14)


See also: IR 05000333/2021090

Text

.

September 3, 2021

EA-20-138

Mr. David P. Rhoades

Senior Vice President

Exelon Generating Company LLC

President and Chief Nuclear Officer, Exelon Nuclear

4300 Winfield Road

Warrenville, IL 60555

SUBJECT:

JAMES A. FITZPATRICK NUCLEAR POWER PLANT - RESPONSE TO

CONTESTED VIOLATION AND FINAL WHITE FINDING AND REVISED

NOTICE OF VIOLATION - INSPECTION REPORT 0500333/2021090

Dear Mr. Rhoades:

This letter provides you the response to your letter dated June 3, 2021, contesting the

Notice of Violation (NOV) issued by Nuclear Regulatory Commission (NRC) letter dated April

20, 2021 (ML21105A543). In summary, Exelon Generation Company, LLC (ExGen) did not

agree that the violation constituted a Performance Deficiency as the staff at James A.

FitzPatrick Nuclear Power Plant (FitzPatrick) could not have reasonably been able to identify

and prevent a nonconforming component (pressure control valve) from being installed and

therefore, contested the characterization of the 10 CFR 50 Appendix B, Criterion VII and XV

violations. On June 25, 2021, the NRC acknowledged receipt of this letter (ADAMS Accession

ML 21176A005) and informed you that we would evaluate your response and provide the

results of our evaluation.

In your letter dated February 26, 2021 (ADAMS Accession ML 21057A190), ExGen

acknowledged that the failure to control a defective part and prevent its use occurred at the

Limerick Generating Station (LIM) in 2010; and, as a result the staff at LIM failed to

communicate the deficiency to Fitzpatrick prior to selling the defective part to FitzPatrick.

ExGen further acknowledged that the sale of the defective part from Limerick to FitzPatrick in

2017, and its subsequent installation, resulted in a failure of the FitzPatrick high pressure

coolant injection system (HPCI) in 2020.

The NRC conducted a detailed review of your response and the applicable regulatory

requirements, in accordance with Part I, Section 2.4.4, of the NRC Enforcement Manual. The

NRC team that performed the review were not involved with the original inspection effort.

Based on the totality of the information, including the inspection report with referenced

documents, your response to the apparent violation, and your response contesting the final

violation; the review team determined that the violations referencing 10 CFR 50, Appendix B

Criterion VII, Control of Purchased Material, Equipment and Services, and Criterion XV,

Nonconforming Materials, Parts or Components, were not sufficiently supported as stated in

D.P. Rhoades

- 2 -

the issued Notice. The Criterion VII violation has been withdrawn and the Criterion XV violation

has been revised.

The review team confirmed the validity of the issued Technical Specification violation and

recommended a revised performance deficiency concerning FitzPatrick staffs failure to

adequately follow its procurement and receipt procedures. The team determined that these

failures, which substantially contributed to the installation of a defective part into the high

pressure coolant injection system, was reasonably foreseeable and preventable. The

circumstances of the performance deficiency were determined to constitute violations of 10 CFR

50 Appendix B, Criterion V, Instructions, Procedures, and Drawings (hereafter referred to as

Criterion V) and Criterion XV. The noncompliance with Criterion V is newly identified, and the

noncompliance with Criterion XV, with changes, is confirmed. The bases for these

determinations, which include the withdrawal of the Criterion VII violation are detailed in the

enclosures to this letter. The enclosed Notice (i.e., revised) supersedes the Notice issued on

April 20, 2021. The revised Notice includes violations (i.e., Criterion V, Criterion XV and

Technical Specification 3.5.1) that are categorized collectively as a problem associated with a

finding.

Due to the change in the characterization of the performance deficiency, a review of the

previously issued risk assessment was also performed (Enclosure 2). This review concluded

that the underlying assumption and methodology were not altered by the revised performance

deficiency and that the performance deficiency supports a finding of White significance.

You are not required to respond to this letter. If you have additional information that you believe

the NRC should consider, you should follow the instructions in the Notice. The details of the

NRC's evaluation of a reply to the Notice of Violation, as well as the re-stated Notice, are

contained in the enclosures to this letter. In accordance with Title 10 of the Code of Federal

Regulations (10 CFR) 2.390, "Public inspections, exemptions, requests for withholding," a copy

of this letter and its enclosure will be made available electronically for public inspection in the

NRCs ADAMS, accessible from the NRC Web site http://www.nrc.gov/readinq-rm/adams.html.

Should you have any questions regarding this matter, please contact Ms. Erin E. Carfang, Chief,

Projects Branch 1, Division of Reactor Projects in Region I, at 610-337-5120.

Sincerely,

David C. Lew

Regional Administrator

Docket No. 50-333

License No. DPR-59

cc: Distribution via ListServ

David C. Lew

Digitally signed by David C. Lew

Date: 2021.09.03 08:37:46 -04'00'

ML21244A497

SUNSI Review

Non-Sensitive

Sensitive

Publicly Available

Non-Publicly Available

OFFICE

RI/DRSS

NRR

OE

RI/RA

NAME

CCahill

CMiller

MLombard

DLew

DATE

09/2 /21

09/ 2 /21

09/3 /21

09/ 3 /21

ENCLOSURE 1

NRC RESPONSE TO INFORMATION PROVIDED IN THE EXELON LETTER

DATED JUNE 3, 2021

As discussed below, the NRC Independent Review Team (IRT) reviewed the information

provided by Exelon Generation Company, LLC (ExGen) and determined that the characterization

of the finding remains of low-to-moderate safety significance (White). The IRT determined that

the violations of 10 CFR 50, Appendix B, Criterion VII, Control of Purchased Material,

Equipment and Services, and Criterion XV, Nonconforming Materials, Parts or Components,

were not sufficiently supported as written. As a result, the Criterion VII violation has been

withdrawn and the Criterion XV violation has been revised. The violation of TS 3.5.1 remains

unchanged. However, the IRT determined that a violation of 10 CFR Part 50 Appendix B,

Criterion V, is warranted.

Regarding the contested 10 CFR Part 50 Appendix B, Criteria VII and XV violations, the IRT

determined that neither 10 CFR Part 21, nor any associated NRC guidance, requires a

licensee to evaluate an incoming component for the existence of a Part 21 notification.

FitzPatrick, as required by 10 CFR 21.311, appropriately invoked the requirements of Part 21

by its inclusion in the purchase order. Part 21 does not represent a receipt inspection

characteristic for the procurement of a structure, system, component, or service. Rather, its

inclusion in the purchase order places the supplier on notice that the requirements of Part 21

must be met. Accordingly, given that no additional information was presented in the inspection

report regarding a failure to comply with procurement documents (i.e., the purchase order), the

IRT determined the assertion, that Fitzpatrick failed to ensure purchased material, equipment,

and services, whether purchased directly or through contractors and subcontractors, conform

to the procurement documents, was not supported as stated in the subject inspection report.

In reviewing the licensees response and the body of information available to support the

inspection outcome, the staff determined that FitzPatrick failed to comply with its procurement

and receipt procedures which resulted in ExGens failure to adequately identify and control

items to prevent the use of a defective item as specified in Section 6, Identification and Control

of Items, of FitzPatricks Quality Assurance Program Manual (QAPM). Thus, the staff

determined that FitzPatricks failure to accomplish procurement activities as prescribed by

ExGens quality assurance procedures resulted in a noncompliance with 10 CFR 50, Appendix

B, Criteria V and XV. The revised finding and Notice of Violation (NOV) are described in

Enclosures 2 and 3.

SUMMARY OF EXGEN COMMENT - Ability to Identify Part 21 Information

ExGen disputed NRCs basis for determining that the violations were reasonably foreseeable

and preventable because the act of clearing an unrelated shelf-life hold did not provide an

opportunity for either the Limerick Generation Station (Limerick) material handler, or the

FitzPatrick qualified receipt inspector (QRI), to identify the Part 21 information. The Part 21

information was documented in an Issue Report (IR) located in the component database and

was also documented in ExGens Corrective Action Program (CAP) database.

1 10 CFR 21.31, Procurement documents, states, Each individual, corporation, partnership, dedicating

entity, or other entity subject to the regulations in this part shall ensure that each procurement document

for a facility, or a basic component issued by him, her or it on or after January 6, 1978, specifies, when

applicable, that the provisions of 10 CFR Part 21 apply.

2

NRC RESPONSE

The IRT considered the violation in the context of 10 CFR 21 (i.e., Part 21) as used (or implied)

in the contrary to statements for the issued 10 CFR 50 Appendix B, Criterion VII and Criterion

XV violations. The IRT concluded that this aspect of the violations should be withdrawn.

SUMMARY OF EXGEN COMMENT - Archived, Descriptive and Readily Available

With respect to the shelf life hold, ExGen contends the NRC has mischaracterized this

archived and descriptive information as readily available to both the Limerick material

handler and the FitzPatrick quality receipt inspection quality receipt inspection.

NRC RESPONSE

As a point of clarification, the hold that was presented was a user-hold. In order to identify the

reason for a user-hold, the licensees staff would need to further review and disposition the

concern as appropriate. As described in ExGens June 3, 2021 response, the manipulation of

the Passport system requires some degree of user familiarity and skill of the craft. As the

licensee states in their response, descriptive information in the component tracking database

can be provided in several panels. After a review of the information and steps to manipulate the

Passport system, the NRC maintains that this information was readily available, and as a result

represented a reasonable opportunity to foresee and prevent the installation of the

nonconforming PCV.

SUMMARY OF EXGEN COMMENT- Requirements to Research

Although ExGen provided information in the response to the AV - demonstrating that there was

no regulatory requirement to research information unrelated to the shelf life hold, as well as

explaining why the non-conformance would not have reasonably been identified by the Exelon

Business Services Corporation (BSC) staff in 2017 - there is no indication in the issued NOV

that this information was considered.

NRC RESPONSE

The IRT assessed this information during its deliberations. This information, in part, is

addressed in the NRC Response to EXGEN Comments pertaining to10 CFR Part 50 Appendix

B, Criterion VII. The NRC agrees that there was no regulatory requirement to research

information unrelated to the user hold. Accordingly, the revised NOV does not cite a failure to

perform this level of research. Instead, the IRT recommended a performance deficiency (PD)

and violation associated with failures to follow ExGens procedural provisions and the availability

of the subject information. Ultimately, the staff determined that it was reasonable for ExGen to

foresee and prevent the installation of the nonconforming PCV during receipt inspection;

however, the failure of personnel to adhere to procedural requirements resulted in a failure to

identify that the diaphragm in the PCV required replacement.

SUMMARY OF EXGEN COMMENT- Limerick Criterion XV

The NRC staff acknowledged that the Criterion XV violation that occurred at Limerick in 2010

could not have been prevented by the ExGen staff in 2017. However, when recharacterizing the

3

Criterion XV violation as having occurred in 2017, the NRC did not explain how Criterion XV

was violated that year.

NRC RESPONSE

NRC staff identified that information about the Part 21 notification was readily available in the

database and could reasonably be identified by a qualified procurement engineer when

performing a review of available information to address the hold'. As determined by the IRT,

the basis for the issued Criterion XV violation was underpinned by the Criterion VII violation. As

described above, the IRT found Criterion VII to be unsupported. As a result of the IRT review of

this matter, NRC determined that the Criterion XV violation was not sufficiently supported as

stated in the issued Notice; the IRT documented a revised Criterion XV violation that was based

on a procedural deficiency in lieu of a Part 21 procurement deficiency.

SUMMARY OF EXGEN COMMENT- Clearing the User Hold

The licensee stated that the shelf-life hold was actually cleared by the Limerick MH after the

existence of the hold had been communicated to the FitzPatrick buyer; and, that the FitzPatrick

buyer engaged the FitzPatrick Procurement Engineer (PE) who appropriately reviewed the

original vendor documentation and determined that the shelf-life could be extended - which was

subsequently communicated to the FitzPatrick buyer and the FitzPatrick QRI. Per the licensee,

at no time did the FitzPatrick buyer, the FitzPatrick QRI, or the FitzPatrick PE have any reason -

nor was there any regulatory requirement - to access the component tracking database or the

ExGen CAP system to investigate the reason for the shelf-life hold. ExGen stated that clearing

the hold was the responsibility of the Limerick warehouse staff as the custodian of the

component.

NRC RESPONSE

The NRC recognizes that the specific facts of the procurement incident are impacted by the

amount of time that has elapsed since the 2017 transfer, personnel retirements, and the lack of

documentation. However, in response to the comments above, the NRC reviewed action

request (AR) 04348906 - originated on June 6, 2020, by FitzPatrick - to inform our decision on

the sequence of events and the actions of the involved individuals. Specifically, per the AR, (1)

the PCV was put on user hold at Limerick on October 20, 2017, due to the self-life expiring

within 5 days, (2) the valve was transferred to Fitzpatrick on December 15, 2017, with the shelf-

life indicating expired in Passport, and (3) the Fitzpatrick quality receipt package inspection

identified, reviewed and dispositioned the shelf-life issue with FitzPatricks Procurement

Engineering prior to releasing the PCV for installation in the HPCI system.

Procedure SM-AA-102, Warehouse Operations, Rev 23, Attachment 1, step 1.10.6, specifies, in

part, that for items on hold to be released to another facility, the receiving facility must create an

action item to track the resolution before the transfer occurs. FitzPatrick, the receiving facility,

did not create an action item to track the dispositioning of the hold which should have resulted in

the component being returned to user-hold status and tagged until dispositioning had occurred.

Based on the IRT assessment of the supporting information, the team concluded that there

were a number of procedural adherence issues at both the Limerick and FitzPatrick stations

with respect to procurement practices. Similar conclusions were arrived by ExGen as

documented in the Corrective Action Program Evaluation (CAPE) Charter for Condition Report

Number 04334315, dated June 24, 2020, when addressing both Limericks and FitzPatricks

shortcomings in the total chain of events.

4

SUMMARY OF EXGEN COMMENT- Clearing the User Hold

The licensee asserted that the NRC incorrectly stated that IR 1086768 had not been resolved at

the time the PCV was sold to, and accepted at, FitzPatrick. ExGen had previously explained in

their response to the AV, that all actions associated with IR 1086768 have been in

COMPLETE status since 2010. However, the NRC did not acknowledge this fact in the NOV

and inaccurately stated that the IR remained unresolved.

NRC RESPONSE

The NRC acknowledges that actions associated with IR 1086768 have been in COMPLETE

status since 2010. The actions of concern were taken to COMPLETE by generating M Codes

which directed the replacement of the diaphragm prior to installation. Specifically, in the

component identification (CID) facility-specific section in Passport Panel D202, it stated, Need

to replace diaphragm 116-0013 prior to use in the plant refer IR 1086768. The IRT determined

that if prescribed procedures were followed as described above, it would have been reasonable

for the FitzPatrick procurement staff to identify that the action to replace the diaphragm was not

completed. Furthermore, it was reasonable for procurement engineers to review Passport

Panel D202 during the receipt process regardless of whether a hold was placed on the

component.

SUMMARY OF EXGEN COMMENT- Unresolve Part 21s

ExGen specifically informed the NRC that there is no reference to the Part 21 in the component

tracking database. Furthermore, if a search of the referenced IR would have been required,

which ExGen continues to stress was NOT required, it would have indicated to the Limerick MH

and the FitzPatrick QRI that there were no open ATIs associated with that IR and therefore, they

would have concluded that the IR was dispositioned correctly and closed. In order for any BSC

or ExGen staff to identify that there was an unresolved Part 21 concern associated with the

PCV, the individual would have had to arbitrarily decide to audit the closures of each of the ATIs

associated with IR 1086768, despite having no cause or regulatory requirement to do so.

NRC RESPONSE

As stated above, Part 21 does not represent a receipt inspection characteristic for the

procurement of structures, systems and components (SSC).

SUMMARY OF EXGEN COMMENT- Part 21 and Closed Action Tracking Items (ATIs)

Assuming the BSC staff had reason to look for any open ATIs associated with older Part 21

notifications in 2017, which they did not, the BSC staff would have determined that appropriate

actions were put in place and subsequently completed to address the 2010 Part 21 notification.

NRC RESPONSE

As stated above, Part 21 does not represent a receipt inspection characteristic for the

procurement of a SSC.

5

SUMMARY OF EXGEN COMMENT - Descriptive Information

The issue report (IR) number associated with the 2010 Part 21 response was not documented

in the status field, but instead was documented in a hidden descriptive information field along

with 63 other line items of descriptive information.

NRC RESPONSE

The IRT disagreed with ExGens characterization that the relevant descriptive information

concerning the deficient PCV diaphragm was not readily available. Specifically, information was

clearly available in Passport panel D202. Procurement Engineers operate in accordance with

procedure SM-AA-300-1001, Procurement Engineering Process, and other procedures.

Section 4.29 describes how additional comments and basis for site applicability may be entered

using CID specific panel D202. The IRT determined that, when clearing the user-hold for the

PCV, it would have been reasonable for procurement engineers to access this descriptive

information, which was readily available and required no more than a few minutes to review.

From this descriptive information, it would have been reasonable for the licensee to identify that

the defective diaphragm in the PCV required replacement. Furthermore, it was reasonable for

procurement engineers to review Passport Panel D202 during the receipt process regardless of

whether a hold was placed on the component.

ENCLOSURE 2

REVISED FINDING IN RESPONSE TO CONTESTED VIOLATION

Defective Part Results in High Pressure Coolant Injection System Pressure Control Valve

Failure

Cornerstone

Significance

Cross-cutting

Aspect

Report

Section

Mitigating

Systems

White NOV 05000333/2020012-01

Open

EA-20-138

[H.1] -

Resources

71153

The inspectors documented a self-revealed White finding and related violation of FitzPatrick

Technical Specifications (TS 3.5.1). The finding included failures to comply with Title 10 of

the Code of Federal Regulations (10 CFR) Part 50, Appendix B, Criterion V, Instructions,

Procedures and Drawings and Criterion XV, Nonconforming Materials, Parts, or

Components. Exelon Generation, LLC (ExGen) did not adequately implement quality-related

procedures which contributed to FitzPatricks failure to identify a nonconforming component,

which was verified as acceptable for use. Subsequently, FitzPatricks maintenance staff

installed the nonconforming component which caused the inoperability of the HPCI system on

April 10, 2020.

Description:

The HPCI system at FitzPatrick provides an emergency source of water following a transient

or accident. This high pressure source of coolant is delivered from two water sources using

steam generated from the reactor to drive the associated turbine and pump. The HPCI

system pump can deliver up to 4,250 gallons per minute and may be operated across a wide

range of reactor pressures. The HPCI system pump and turbine are supported by an oil

system designed to lubricate bearings and provide adequate pressure to control the steam

turbine stop and control valves.

During a HPCI maintenance window in December 2017, an emergent need arose for a

replacement pressure control valve (PCV). ExGen did not have a replacement PCV on site at

the time, and subsequently located a replacement PCV at Limerick. On December 16, 2017,

ExGen issued purchase order (P.O.) 637326 to move the HPCI system PCV from the

Limerick warehouse to FitzPatrick during a planned HPCI system maintenance window. Due

to the emergent demand, the purchase order was issued in parallel with a document review

by FitzPatrick. Per issue report (IR) 04348906, originated on June 6, 2020, the PCV was put

on user hold at Limerick on October 20, 2017, due to the shelf-life expiring within 5 days.

This IR states the valve was transferred to FitzPatrick on December 15, 2017, with an expired

shelf-life annotated in Passport (the licensees component tracking database). Additionally,

the IR states that prior to releasing the PCV for installation, Fitzpatricks quality receipt

inspection identified, reviewed, and dispositioned the shelf-life issue with FitzPatrick

Procurement Engineering.

Procedure SM-AA-300-1001, Section 4.10.2, specified that when the requesting facility

(FitzPatrick) is not a specific user of the procured component that the existing Catalogue

Identification (CID) at the target site (Limerick) shall be reviewed by the requesting site. The

purpose of this review is to ensure that quality and technical requirements of the component

are adequate for the requesting facilitys need; and, that the review shall be performed by a

procurement engineer (PE) for a safety-related component. The CID was not in a ready state

Notice of Violation

2

at the time of request, as a user hold existed in Passport for a shelf-life concern. The

document package associated with P.O. No. 011466532 included electronic correspondence

documenting that appropriate Fitzpatrick staff reviewed the document package for P.O. No.

0011466532 and found it to be acceptable. FitzPatricks review did not identify discrepant

information located within Exelons equipment database (e.g., the CID facility-specific section

in Passport panel D202).

The FitzPatrick procurement staff authorized Limerick to transfer a component in hold status

in the Passport system without initiating a new hold upon receipt of the component at the

destination site (FitzPatrick). These actions were not in accordance with the requirements of

procedure SM-AA-102, Warehouse Operations, Rev. 23. Procedure SM-AA-102, specified

that items released on hold shall be tracked by a respective Action Request (AR) assignment,

Work Order task or Issue report with respective assignments to track the released material.

Specifically, the licensee failed to ensure that a component released on hold was adequately

tracked by a respective AR assignment, work order task or issue report with respective

assignments to ensure requisite component quality, and the Catalogue ID (CID) for this

component was set to READY. Additionally, a hold tag was required to be attached to the

component upon receipt of the transfer at the receiving site and entered into the sites hold

tag log. These actions were not performed. The failure to initiate a hold upon receipt of the

PCV or initiate tracking documents resulted in opportunities for FitzPatrick to identify the

discrepant information located within the equipment database. The formal actions to

disposition the hold, as required per SM-AA-102, provided a reasonable opportunity, under

these specific circumstances, for FitzPatrick to identify that the PCV was nonconforming.

Descriptive information relating to the nonconforming condition was readily available in

several panels in the licensees component tracking data base. For example, panel D202

included a readily available note which stated need to replace diaphragm 116-00134 prior to

use in plant.

The review of P.O. No. 011466532 did not identify the discrepant information located within

the CID facility specific section in Passport panel D202. The document package associated

with the P.O. included electronic correspondence (i.e., a one-line email) documenting that a

senior procurement engineer reviewed the document package for the P.O. and found it to be

acceptable. The use of panel D202 is described in Section 4.29 of SM-AA-300-1001,

Procurement Engineering Process and Responsibility, Rev 24. Specifically, the procedure

states Additional comments and the basis for site applicability may be added under the CID

facility specific section in Passport panel D202, AAA route list, D201 panel OLE field, or BOM

NOTES, as appropriate. The guidance in Procedure SM-AA-300-1001, combined with the

failures to follow procedural requirements for applying hold tags and initiating tracking

documentation further inform the agencys conclusion that reasonable opportunities existed to

foresee and prevent the installation of the nonconforming PCV.

Consequently, without identifying adverse information concerning the PCV, procurement staff

verified a nonconforming component as acceptable for use. As a result of the nonconforming

part installation, on April 10, 2020, at 1:15 AM, while conducting monthly technical

specification surveillance testing of the HPCI auxiliary oil system, operators identified an oil

leak on 23PCV-12 as a result of a tear in the subject diaphragm. Ultimately, the HPCI system

was declared inoperable and placed the station into a higher licensee-established risk

category (Yellow). ExGen notified the NRC of the inoperability per 10 CFR Part

50.72(b)(3)(v)(D) via Event Notification 54647. The 23PCV-12 valve was replaced and the

HPCI system restored to operable status on April 10, 2020, at 8:02 PM.

Notice of Violation

3

Corrective Actions: ExGen performed immediate corrective actions to replace the

nonconforming HPCI system PCV. ExGen also performed a fleet-wide stand down for

procurement staff to conduct additional training. Additionally, ExGen created a separate

action for each ExGen site to validate that a similar condition does not exist regarding other of

nonconforming materials, parts, or components within their inventory tracking database.

Furthermore, ExGen revised its warehouse and procurement procedures, adding steps

pertaining to items subject to 10 CFR Part 21 notifications and items with holds.

Corrective Action References: IR 4334315, IR 4348906

Performance Assessment:

Performance Deficiency: The inspectors determined that FitzPatricks did not comply with the

requirements and guidance of quality-related procurement procedures, which contributed to

ExGens failure to adequately identify and control a nonconforming item.

Procedure SM-AA-102, Warehouse Operations, Rev 23, states items that are on hold at one

site can be released to another site while on hold only if an action item is created at the

receiving site to track resolution of the item before the transfer occurs, and the item is added

to the receiving sites hold tag log. Additionally, a hold tag shall be attached to the item upon

receipt of the transfer at the receiving site.

On December 16, 2017, FitzPatrick failed to follow SM-AA-102. Adherence to the

requirements of this procedure, as well as using guidance provided in SM-AA-300-1001,

would have presented a reasonable opportunity for FitzPatrick to identify and assess readily

available information that was within the licensees Catalogue ID database and also linked to

the ExGen corrective action program. Consequently, without reviewing readily available

adverse information concerning the PCV, procurement staff verified a nonconforming

component as acceptable for use. Subsequently, FitzPatricks maintenance staff installed the

nonconforming component which caused the inoperability of the HPCI system.

Screening: The inspectors determined the performance deficiency was more than minor

because it was associated with the Equipment Performance attribute of the Mitigating

Systems cornerstone and adversely affected the cornerstone objective to ensure the

availability, reliability, and capability of systems that respond to initiating events to prevent

undesirable consequences. Specifically, the HPCI system was unavailable to perform its

safety function as a result of the failed PCV.

Significance: The performance deficiency was assessed by a Region I Senior Reactor

Analyst (SRA) and NRR Senior Risk Analysis and determined that prior risk assessment was

still valid for the failed HPCI system. The finding was determined to be of low to moderate

safety significance (White). The risk important core damage sequences were dominated by

internal events, primarily loss of condenser heat sink and loss of main feedwater. The

dominant core damage sequence is loss of condenser heat sink, failure of high-pressure

injection (HPI), and failure to manually depressurize the reactor. See Enclosure 1 to this final

determination report and the Attachment, HPCI Oil PCV Failure Detailed Risk Evaluation, to

the preliminary determination report (ADAMS Accession Number: ML21020A108) for a

detailed review of the quantitative and qualitative criteria considered in the final risk

determination.

Notice of Violation

4

The inspectors assessed the significance of the finding using Appendix A, The Significance

Determination Process (SDP) for Findings At-Power. The inspectors reviewed Inspection

Manual Chapter (IMC) 0609, Attachment 4, Initial Characterization of Findings, and

determined the finding affects the mitigating system cornerstone. The inspectors evaluated

the significance of this finding using Inspection Manual Chapter (IMC) 0609, Appendix A, The

Significance Determination Process (SDP) for Findings at Power, Exhibit 2 - Mitigating

Systems Screening Questions. The inspectors determined that the finding represented a loss

of the PRA function of a single train, the HPCI system, for greater than its technical

specification (TS) allowed outage time and required a detailed risk evaluation (DRE).

A Region I Senior Reactor Analyst (SRA) performed a detailed risk evaluation. The finding

was determined to be of low to moderate safety significance (White). The risk important core

damage sequences were dominated by internal events, primarily loss of condenser heat sink

and loss of main feedwater. The dominant core damage sequence is loss of condenser heat

sink, failure of high-pressure injection (HPI), and failure to manually depressurize the reactor.

This final determination report and the Attachment, HPCI Oil PCV Failure Detailed Risk

Evaluation, to the preliminary determination report provide a detailed review of the

quantitative and qualitative criteria considered in the final risk determination (ADAMS

Accession Number: ML21020A108).

Cross-Cutting Aspect: H.1 - Resources: Leaders ensure that personnel, equipment,

procedures, and other resources are available and adequate to support nuclear safety. The

cause of the finding was determined to be associated with a cross-cutting aspect of

Resources in the Human Performance area because ExGen staff failed to identify and

address a nonconformance during verification of the quality of the HPCI system PCV.

Specifically, the inspectors determined there were multiple ways for ExGen to reasonably

identify a nonconformance associated with the PCV diaphragm which had not been

addressed. Furthermore, procurement implementing procedures did not provide adequate

guidance to ensure that procedure users would identify and resolve this issue. Having

comprehensive steps within the relevant procedure would likely have prevented installation of

the defective part at FitzPatrick.

ENCLOSURE 3

NOTICE OF VIOLATION

Exelon Generation Company, LLC Docket No. 50-333

James A. FitzPatrick Nuclear Power Plant License No. DPR-59 EA-20-138

During an NRC review in response to a contested violation conducted from June 3, 2021,

through September 3, 2021, violations of NRC requirements were identified. In accordance with

the NRC Enforcement Policy, the violations are listed below:

Title 10 CFR Part 50, Appendix B, Criterion V, Instructions, Procedures, and Drawings, states,

in part, that activities affecting quality shall be prescribed by documented instructions,

procedures, or drawings, of a type appropriate to the circumstances and shall be accomplished

in accordance with these instructions, procedures, or drawings.

Title 10 CFR Part 50, Appendix B, Criterion XV, Nonconforming Materials, Parts, or

Components, states, in part, that measures shall be established to control materials, parts, or

components which do not conform to requirements in order to prevent their inadvertent use or

installation. These measures shall include, as appropriate, procedures for identification,

documentation, segregation, disposition, and notification to affected organizations.

Exelon Procedure SM-AA-102, Warehouse Operations, Revision 23, prescribes activities

affecting quality and measures to control nonconforming components. Procedure SM-AA-102,

Attachment 1, step 1.10.6, states Items that are on hold at one site can be released to another

site while on hold only if an action item is created at the receiving site to track resolution of the

item before the transfer occurs, and the item is added to the receiving sites hold tag log. A hold

tag shall be attached to the item upon receipt of the transfer at the receiving site.

FitzPatrick Technical Specification (TS 3.5.1) requires, in part, that the HPCI system be

operable in Modes 1, 2 and 3 with reactor steam dome pressure >150 psig. If the HPCI system

is determined to be inoperable, it shall be returned to an operable status within 14 days. If not

restored to an operable status, the unit shall be shut down and in Mode 3 within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />.

Contrary to the above, from December 16, 2017, to April 10, 2020, activities affecting quality

were not accomplished in accordance with procedures for controlling a nonconforming

component and a nonconforming component was not controlled in accordance with documented

procedures. Specifically, Exelon failed to initiate an action item at FitzPatrick to track resolution

of a nonconforming Pressure Control Valve (PCV) before its transfer occurred, did not add it to

the receiving sites hold tag log, and did not attach a hold tag upon receipt. As a result, on

December 16, 2017, Exelon did not identify that the PCVs diaphragm required replacement and

installed the nonconforming PCV in the High Pressure Coolant Injection (HPCI) system.

Consequently, the HPCI system was rendered inoperable prior to April 10, 2020, for a period

longer than its TS allowed outage time, and the unit was not shut down and placed in Mode 3

within 12 hours1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br /> in accordance with requirements.

These violations are categorized collectively as a problem and are associated with a White

Significance Determination Process finding.

Notice of Violation

2

No response to this Notice of Violation is required since the NRC previously received adequate

responses as documented in a letter dated February 26, 2021 (ML21057A190). If you wish to

provide additional information for the NRC to consider, you should notify the Region I Regional

Administrator verbally within 10 days of receipt of this Notice of Violation, followed by a written

response submitted within 30 days of the date of the verbal notification to the U.S. Nuclear

Regulatory Commission, ATTN: Document Control Desk, Washington, DC 20555-0001, with a

copy to the Regional Administrator, Region I, and a copy to the NRC Resident Inspector at the

facility that is the subject of this Notice. This reply should be clearly marked as a "Reply to a

Notice of Violation; EA-20-138".

Your response, if made, will be made available electronically for public inspection in the NRC

Public Document Room or from the NRCs document system (ADAMS), accessible from the

NRC Web site at http://www.nrc.gov/reading-rm/adams.html, to the extent possible, it should not

include any personal privacy, proprietary, or safeguards information so that it can be made

available to the public without redaction. If personal privacy or proprietary information is

necessary to provide an acceptable response, then please provide a bracketed copy of your

response that identifies the information that should be protected and a redacted copy of your

response that deletes such information. If you request withholding of such material, you must

specifically identify the portions of your response that you seek to have withheld and provide in

detail the bases for your claim of withholding (e.g., explain why the disclosure of information will

create an unwarranted invasion of personal privacy or provide the information required by

10 CFR 2.390(b) to support a request for withholding confidential commercial or financial

information). If safeguards information is necessary to provide an acceptable response, please

provide the level of protection described in 10 CFR 73.21.

In accordance with 10 CFR 19.11, the licensee may be required to post this Notice within two

working days of receipt.

Dated this 3rd day of September 2021.