ND-21-0551, ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332)

From kanterella
(Redirected from ML21155A031)
Jump to navigation Jump to search
ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 (Index Number 332)
ML21155A031
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 06/04/2021
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ITAAC 2.3.04.05, ND-21-0551
Download: ML21155A031 (7)


Text

Michael J. Vox 7825 River Road Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogfle 3 & 4 706-848-6459 tel JUN 0 h 2021 Docket No.: 52-025 ND-21-0551 10 CFR 52.99(c)(1)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 ITAAC Closure Notification on Completion of ITAAC 2.3.04.05 [Index Number 3321 Ladies and Gentlemen:

In accordance with 10 CFR 52.99(c)(1), the purpose of this letter is to notify the Nuclear Regulatory Commission (NRC) of the completion of Vogtle Electric Generating Plant(VEGP) Unit 3 Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.3.04.05 [Index Number 332].

This ITAAC confirms the retrievability of Fire Protection System pump displays in the Main Control Room. The closure process for this ITAAC is based on the guidance described in Nuclear Energy Institute (NEI) 08-01, "Industry Guideline for the ITAAC Closure Process under 10 CFR Part 52,"

which was endorsed by the NRC in Regulatory Guide 1.215.

This letter contains no new NRC regulatory commitments. Southern Nuclear Operating Company (SNC) requests NRC staff confirmation of this determination and publication of the required notice in the Federal Register per 10 CFR 52.99.

If there are any questions, please contact Kelli Roberts at 706-848-6991.

Respectfully submitted.

Michael J. Yo>

Regulatory Affairs Oirector Vogtle 3 & 4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of ITAAC 2.3.04.05 [Index Number 332]

MJY/RLB/sfr

U.S. Nuclear Regulatory Commission ND-21-0551 Enclosure Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III Mr. D. L. McKinney Mr. M. D. Meier Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. M. J. Vox Mr. A. S. Parton Ms. K. A. Roberts Mr. C. T. Defnall Mr. C. E. Morrow Mr. J. M. Fisher Mr. R. L. Beiike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reouiatorv Commission Ms. M. Bailey Mr. M. King Mr. G. Bowman Ms. A. Veil M C. P. Patel M G. J. Khouri M C. J. Even M B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. O. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. E. Davidson Mr. T. Fanelli Ms. K. McCurry Mr. J. Parent Mr. B. Griman

U.S. Nuclear Regulatory Commission ND-21-0551 Enclosure Page 3 of 3 Qqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Daiton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Orlani Mr. D. 0. Durham Mr. M. M. Corletti Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, Inc.

Mr. 8. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Balch BIngham

U.S. Nuclear Regulatory Commission ND-21-0551 Enclosure Page 1 of 4 Southern Nuclear Operating Company ND-21-0551 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 3 Completion of ITAAC 2.3.04.05[Index Number 332]

U.S. Nuclear Regulatory Commission ND-21-0551 Enclosure Page 2 of 4 ITAAC Statement Desian Commitment

5. Displays of the parameters identified in Table 2.3.4-1 can be retrieved in the MCR.

Inspections. Tests. Analvses Inspection will be performed for retrievability of the parameters in the MCR.

Acceptance Criteria The displays identified in Table 2.3.4-1 can be retrieved in the MCR.

ITAAC Determination Basis An inspection was performed to verify the retrievability of the Vogtle Electric Generating Plant (VEGP) Unit 3 Fire Protection System (FPS) plant parameters in the Main Control Room (MCR).

The inspection for retrievability confirmed that the displays of the parameters identified in Combined License (COL) Appendix C Table 2.3.4-1 (Attachment A)can be retrieved in the MCR.

The inspection was performed in accordance with the Unit 3 FPS component test work order (Reference 1)for FPS pump indication verifications, and visually confirmed that when each of the displays of parameters identified in Attachment A was summoned at a MCR workstation, the summoned plant parameter appeared on a display monitor at that MCR workstation. The results of the FPS component test work order are summarized in Reference 2.

The Unit 3 component test results are documented in References 1 and 2 and confirm that the VEGP Unit 3 plant parameter displays listed in Attachment A can be retrieved in the MCR.

References 1 and 2 are available for NRC inspection as part of Unit 3 ITAAC 2.3.04.05 Completion Package (Reference 3).

ITAAC Finding Review In accordance with plant procedures for ITAAC completion. Southern Nuclear Operating Company(SNC) performed a review of all ITAAC findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with the ITAAC. The ITAAC completion review is documented in the ITAAC Completion Package for ITAAC 2.3.04.05(Reference 3) and is available for NRC review.

ITAAC Completion Statement Based on the above information, SNC hereby notifies the NRC that ITAAC 2.3.04.05 was performed for VEGP Unit 3 and that the prescribed acceptance criteria are met.

Systems, structures, and components verified as part of this ITAAC are being maintained in their as-designed, ITAAC compliant condition in accordance with approved plant programs and procedures.

U.S. Nuclear Regulatory Commission ND-21-0551 Enciosure Page 3 of 4 References ^available for NRG inspection)

1. Work Order SNC921200, FPS Dispiays Retrievabiiity in MGR Verification Test - iTAAC:SV3-2.3.04.05, Revision 0
2. ITAAC Technicai Report SV3-FPS-ITR-800332, Unit 3 FPS Displays Retrievabiiity in MGR Verification Test: ITAAG 2.3.04.05, Revision 0
3. 2.3.04.05-U3-GP-Rev 0, iTAAG Completion Package

U.S. Nuclear Regulatory Commission ND-21-0551 Enclosure Page 4 of 4 Attachment A

'Excerpt from COL Appendix C Table 2.3.4-1

  • Table 2.3.4-1 "Equipment Name "Tag No. "Display Motor-driven Fire Pump FPS-MP-01A Yes(Run Status)

Diesel-driven Fire Pump FPS-MP-01B Yes(Run Status)

Jockey Pump FPS-MP-02 Yes(Run Status)