ML21104A145

From kanterella
Jump to navigation Jump to search
Attachment - Rulemaking Activities, April 2021
ML21104A145
Person / Time
Issue date: 04/30/2021
From: Christopher Hanson
NRC/Chairman
To: Carper T, Feinstein D, Kaptur M, Markey E, Pallone F, Rush B, Tonko P
US HR (House of Representatives), US SEN (Senate)
Sara Mroz
Shared Package
ML21104A111 List:
References
CORR-21-0032
Download: ML21104A145 (10)


Text

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 1 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date1 Final Rule to Signature Authority2 Final Rule Publication Date3 1

Rulemaking Actions 2021 Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code High 3150-AK21 NRC-2018-0289 N/A 12/12/2018 N/A N/A N/A N/A N/A 2

Rulemaking Actions 2022 Edition of the American Society of Mechanical Engineers Operations and Maintenance Code High 3150-AK43 NRC-2020-0030 N/A 12/12/2019 N/A N/A N/A N/A N/A 3

Rulemaking Actions 2023 Edition of the American Society of Mechanical Engineers Boiler and Pressure Vessel Code High 3150-AK42 NRC-2020-0029 N/A 12/12/2019 N/A N/A N/A N/A N/A 4

Rulemaking Actions 2024 Edition of the American Society of Mechanical Engineers Operations and Maintenance Code High 3150-AK62 NRC-2021-0022 N/A 1/6/2021 N/A N/A N/A N/A N/A 5

Rulemaking Actions Advanced Boiling-Water Reactor (ABWR) Design Certification Renewal High 3150-AK04 NRC-2017-0090 N/A 3/30/2017 N/A 12/9/2020 8/18/2021 12/9/2020 8/18/2021 6

Rulemaking Actions Advanced Nuclear Reactor Generic Environmental Impact Statement High 3150-AK55 NRC-2020-0101 N/A 9/21/2020 N/A 11/30/2021 5/30/2022 5/1/2023 11/1/2023 7

Rulemaking Actions American Society of Mechanical Engineers 2019 - 2020 Code Editions High 3150-AK22 NRC-2018-0290 N/A 12/12/2018 N/A 3/3/2021 3/26/2021 2/24/2022 6/30/2022 8

Rulemaking Actions Approval of American Society of Mechanical Engineers Code Cases, Revision 39 High 3150-AJ94 NRC-2017-0025 N/A 5/1/2016 N/A 12/23/2020 2/2/2021 12/27/2021 3/23/2022 1 These dates are NRC staff estimates. The actual dates are subject to Commission action.

2 These dates are NRC staff estimates. The actual dates are subject to Commission action.

3 These dates are NRC staff estimates. The actual dates are subject to Commission action.

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 2 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 9

Rulemaking Actions Approval of American Society of Mechanical Engineers Code Cases, Revision 40 High 3150-AK23 NRC-2018-0291 N/A 12/12/2018 N/A N/A N/A N/A N/A 10 Rulemaking Actions Approval of American Society of Mechanical Engineers Code Cases, Revision 41 High 3150-AK61 NRC-2021-0023 N/A 1/6/2021 N/A N/A N/A N/A N/A 11 Rulemaking Actions Cyber Security for Fuel Facilities High 3150-AJ64 NRC-2015-0179 N/A 3/24/2015 4/12/2016 10/4/2017 9/15/2021 4/30/2022 10/14/2022 12 Rulemaking Actions Drug and Alcohol Testing:

Technical Issues and Editorial Changes High 3150-AJ15 NRC-2012-0079 PRM-26-4, PRM-26-7, PRM-26-8 N/A 1/1/2022 1/1/2023 4/1/2023 1/1/2024 4/1/2024 13 Rulemaking Actions

  • Enhanced Security for Special Nuclear Material High 3150-AJ41 NRC-2014-0118 N/A 2/8/2006 N/A 8/2/2021 2/2/2022 9/20/2022 2/20/2023 14 Rulemaking Actions Enhanced Weapons for Spent Fuel Storage Installations and TransportationSection 161A Authority High 3150-AJ55 NRC-2015-0018 N/A 8/15/2008 N/A 9/27/2021 12/27/2021 3/25/2022 7/25/2022 15 Rulemaking Actions Enhanced Weapons, Firearms Background Checks, and Security Event Notifications High 3150-AI49 NRC-2011-0018 N/A 8/8/2005 N/A 3/16/2015 9/22/2015 5/21/2018 9/30/2021 16 Rulemaking Actions Fitness-for-Duty Drug Testing Program Requirements High 3150-AI67 NRC-2009-0225 N/A 9/1/2012 7/1/2013 2/22/2017 9/16/2019 9/15/2021 12/15/2021 17 Rulemaking Actions Greater-Than-Class-C and Transuranic Waste High 3150-AK00 NRC-2017-0081 N/A 12/22/2015 7/22/2019 N/A N/A N/A N/A 18 Rulemaking Actions
  • Independent Spent Fuel Storage Installation Security Requirements High 3150-AI78 NRC-2009-0558 PRM-72-6 N/A N/A 8/2/2021 2/2/2022 9/30/2022 2/28/2023

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 3 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 19 Rulemaking Actions Integrated Radioactive Source Security and Accountability High N/A NRC-2015-0094 PRM-37-1 N/A N/A N/A N/A N/A N/A 20 Rulemaking Actions List of Approved Spent Fuel Storage Casks [This is a placeholder for several annually recurring rules.]

High N/A N/A N/A N/A N/A N/A N/A N/A N/A 21 Rulemaking Actions List of Approved Spent Fuel Storage Casks:

Standardized NUHOMS System, Certificate of Compliance No. 1004, Amendment No. 17 High 3150-AK57 NRC-2020-0274 N/A 12/6/2020 N/A 3/12/2021 3/24/2021 3/12/2021 3/24/2021 22 Rulemaking Actions List of Approved Spent Fuel Storage Casks:

Holtec International HI-STORM 100 Cask System, Certificate of Compliance No. 1014, Amendment No. 15 High 3150-AK53 NRC-2020-0257 N/A 11/8/2020 N/A 3/1/2021 4/9/2021 3/1/2021 4/9/2021 23 Rulemaking Actions List of Approved Spent Fuel Storage Casks: NAC-UMS, Certificate of Compliance No. 1015, Amendment No. 8 High 3150-AK63 NRC-2021-0052 N/A 2/22/2021 N/A 4/13/2021 5/11/2021 4/13/2021 5/11/2021 24 Rulemaking Actions Low-Level Radioactive Waste Disposal High 3150-AI92 NRC-2011-0012 N/A 3/18/2009 N/A 7/18/2013 3/26/2015 5/31/2022 11/30/2022 25 Rulemaking Actions NuScale Small Modular Reactor Design Certification High 3150-AJ98 NRC-2017-0029 N/A 3/23/2017 N/A 1/14/2021 7/2/2021 1/6/2022 3/22/2022 26 Rulemaking Actions Performance-Based Emergency Core Cooling System Acceptance Criteria High 3150-AH42 NRC-2008-0332 PRM-50-71, PRM-50-84 3/31/2003 7/31/2008 3/1/2012 3/24/2014 3/16/2016 12/31/2021

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 4 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 27 Rulemaking Actions Reactor Vessel Material Surveillance Testing During Period of Extended Operation High N/A NRC-2018-0295 N/A N/A N/A N/A N/A N/A N/A 28 Rulemaking Actions Regulatory Improvements for Production and Utilization Facilities Transitioning to Decommissioning High 3150-AJ59 NRC-2015-0070 N/A 12/30/2014 11/27/2017 5/7/2018 6/30/2021 8/31/2022 3/15/2023 29 Rulemaking Actions Release of Veterinary Animals Containing Byproduct Materials High N/A NRC-2021-0027 N/A N/A N/A N/A N/A N/A N/A 30 Rulemaking Actions Renewing Nuclear Power Plant Operating Licenses -

Environmental Review High 3150-AK32 NRC-2018-0296 N/A N/A N/A N/A N/A N/A N/A 31 Rulemaking Actions Revise Enrichment Limits to Support Licensing New Fuel Designs High N/A NRC-2020-0034 N/A N/A N/A N/A N/A N/A N/A 32 Rulemaking Actions Revision of Fee Schedules: Fee Recovery for FY 2021 High 3150-AK24 NRC-2018-0292 N/A 11/1/2018 N/A 1/29/2021 2/22/2021 5/12/2021 5/30/2021 33 Rulemaking Actions Revision of Fee Schedules: Fee Recovery for FY 2022 High 3150-AK44 NRC-2020-0031 N/A 1/15/2020 N/A 1/12/2022 1/25/2022 5/12/2022 5/30/2022 34 Rulemaking Actions Revision of Fee Schedules: Fee Recovery for FY 2023 High 3150-AK58 NRC-2021-0024 N/A 1/6/2021 N/A 1/12/2023 1/25/2023 5/12/2023 5/25/2023 35 Rulemaking Actions Risk-Informed, Technology Inclusive Regulatory Framework for Advanced Reactors High 3150-AK31 NRC-2019-0062 N/A 10/2/2020 N/A 5/31/2022 10/31/2022 3/29/2024 10/31/2024 36 Rulemaking Actions U.S. Advanced Pressurized Water Reactor (US-APWR)

Design Certification High 3150-AI83 NRC-2010-0133 N/A 2/29/2008 N/A N/A N/A N/A N/A

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 5 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 37 Rulemaking Actions Updates for Emerging Medical Technologies High N/A NRC-2018-0297 N/A N/A N/A N/A N/A N/A N/A 38 Rulemaking Actions Adjustment of Civil Penalties for Inflation for Fiscal Year 2022 Medium 3150-AK45 NRC-2020-0032 N/A 1/22/2020 N/A N/A N/A 12/16/2021 1/14/2022 39 Rulemaking Actions Adjustment of Civil Penalties for Inflation for Fiscal Year 2023 Medium 3150-AK59 NRC-2021-0025 N/A 1/6/2021 N/A N/A N/A 1/3/2023 1/16/2023 40 Rulemaking Actions Alignment of Licensing Processes and Lessons Learned from New Reactor Licensing Medium 3150-AI66 NRC-2009-0196 N/A 9/22/2015 1/29/2021 5/26/2022 8/23/2022 3/14/2024 6/19/2024 41 Rulemaking Actions Alternative Physical Security Requirements for Advanced Reactors Medium 3150-AK19 NRC-2017-0227 N/A 11/19/2018 7/16/2019 9/27/2021 12/27/2021 1/17/2023 4/17/2023 42 Rulemaking Actions Amendment to Access Authorization Fees Medium 3150-AK49 NRC-2020-0133 N/A 4/1/2020 N/A 5/31/2021 8/30/2021 5/31/2021 8/30/2021 43 Rulemaking Actions Categorical Exclusions from Environmental Review Medium 3150-AK54 NRC-2018-0300 N/A 11/30/2020 N/A 9/16/2022 3/31/2023 5/10/2024 11/29/2024 44 Rulemaking Actions Controlled Unclassified Information Medium 3150-AK30 NRC-2019-0060 N/A 1/18/2019 N/A N/A N/A 5/31/2022 8/31/2022 45 Rulemaking Actions Decommissioning Financial Assurance for Sealed and Unsealed Radioactive Materials Medium 3150-AK52 NRC-2017-0031 PRM-30-66 10/13/2020 12/6/2021 2/17/2023 8/17/2023 5/31/2024 11/29/2024 46 Rulemaking Actions Definition of Utilization Facility for Medical Radioisotope Facilities Medium N/A NRC-2018-0299 N/A N/A N/A N/A N/A N/A N/A 47 Rulemaking Actions Emergency Preparedness Requirements for Small Modular Reactors and Other New Technologies Medium 3150-AJ68 NRC-2015-0225 N/A 6/22/2016 11/15/2017 10/12/2018 5/12/2020 9/30/2021 3/31/2022

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 6 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 48 Rulemaking Actions Exempt Quantities and Concentrations Medium N/A NRC-2021-0077 N/A N/A N/A N/A N/A N/A N/A 49 Rulemaking Actions Extending the Duration of the AP1000 Design Certification Medium 3150-AK56 NRC-2020-0269 N/A 11/17/2020 N/A 8/19/2021 9/16/2021 8/19/2021 9/16/2021 50 Rulemaking Actions Financial Qualifications Requirements for Reactor Licensing Medium 3150-AJ43 NRC-2014-0161 N/A 4/24/2014 N/A 2/28/2018 6/29/2021 8/25/2021 2/25/2022 51 Rulemaking Actions

  • Geologic Repository Operations Area (GROA)

Fitness-For-Duty Requirements Medium 3150-AI38 NRC-2009-0089 N/A N/A 9/17/2040 3/17/2042 9/17/2042 9/17/2043 3/17/2044 52 Rulemaking Actions

  • Geologic Repository Operations Area Security and Material Control and Accounting Requirements Medium 3150-AI06 NRC-2007-0670 N/A N/A 3/16/2040 9/16/2041 3/16/2042 3/16/2043 7/15/2043 53 Rulemaking Actions Groundwater Protection at Uranium In Situ Recovery Facilities Medium 3150-AI40 NRC-2008-0421 N/A 3/24/2006 N/A 7/22/2021 1/21/2022 9/22/2022 3/30/2023 54 Rulemaking Actions Harmonization of Transportation Safety Requirements with IAEA Standards Medium 3150-AJ85 NRC-2016-0179 N/A 8/19/2016 4/12/2019 10/30/2020 9/2/2021 1/28/2022 5/27/2022 55 Rulemaking Actions Industrial Radiographic Operations and Training Medium N/A NRC-2017-0022 PRM-34-6 N/A N/A N/A N/A N/A N/A 56 Rulemaking Actions Items Containing Byproduct Material Incidental to Production Medium 3150-AJ54 NRC-2015-0017 PRM-30-65 8/13/2012 2/2/2021 1/19/2022 4/19/2022 12/21/2022 3/30/2023

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 7 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 57 Rulemaking Actions Miscellaneous Administrative Rulemaking [This is a placeholder for one or more rules making administrative or corrective changes to the CFR]

Medium N/A N/A N/A N/A N/A N/A N/A N/A N/A 58 Rulemaking Actions Modification of Administrative Requirements Medium N/A NRC-2018-0298 N/A N/A N/A N/A N/A N/A N/A 59 Rulemaking Actions Non-power Production or Utilization Facility License Renewal Medium 3150-AI96 NRC-2011-0087 N/A 8/26/2009 10/2/2012 4/7/2016 3/30/2017 6/17/2019 7/8/2021 60 Rulemaking Actions Nuclear Suppliers Group Revisions for Exports Medium 3150-AK60 NRC-2021-0026 N/A 1/6/2021 N/A N/A N/A N/A N/A 61 Rulemaking Actions Receipts-Based Small Business Size Standards Medium 3150-AJ51 NRC-2014-0264 N/A 1/29/2021 N/A 6/1/2021 7/30/2021 12/1/2021 2/28/2022 62 Rulemaking Actions Relaxation of Testing and Inspection Program Updates Required in 10 CFR 50.55a Medium N/A NRC-2021-0028 N/A N/A N/A N/A N/A N/A N/A 63 Rulemaking Actions Reporting Requirements for Non-Emergency Events at Nuclear Power Plants Medium N/A NRC-2020-0036 N/A N/A N/A N/A N/A N/A N/A 64 Rulemaking Actions Revision to the NRC's Acquisition Regulation (NRCAR)

Medium 3150-AJ36 NRC-2014-0033 N/A 6/1/2014 N/A N/A N/A N/A N/A 65 Rulemaking Actions

  • Spent Fuel Reprocessing Medium 3150-AJ53 NRC-2015-0016 N/A N/A 7/26/2021 7/26/2022 10/26/2023 7/26/2023 10/26/2024

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 8 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 66 Rulemaking Actions Training and Experience Requirements for Unsealed Byproduct Materials Medium N/A NRC-2020-0035 N/A N/A N/A N/A N/A N/A N/A 67 Rulemaking Actions Transforming the NRCs Environmental Review Process Medium N/A NRC-2021-0029 N/A N/A N/A N/A N/A N/A N/A 68 Rulemaking Actions Updates on the Export of Deuterium Medium 3150-AJ45 NRC-2014-0201 N/A 9/1/2014 N/A N/A N/A 2/28/2021 6/11/2021 69 Rulemaking Actions Alternatives to the Use of Credit Ratings Low 3150-AJ92 NRC-2017-0021 N/A 9/1/2014 N/A 4/29/2022 10/31/2022 7/31/2023 1/30/2024 70 Rulemaking Actions Cost Recovery Criteria for Research and Development Utilization Facilities Low N/A NRC-2020-0071 N/A N/A 1/31/2022 1/31/2023 4/30/2023 4/30/2024 8/30/2024 71 Petition Actions Access to the Decommissioning Trust Fund for the Disposal of Large Components N/A N/A NRC-2019-0083 PRM-50-119 N/A N/A N/A N/A N/A N/A 72 Petition Actions Accident Source Term Methodologies and Corresponding Release Fractions N/A N/A NRC-2020-0150 PRM-50-122 N/A N/A N/A N/A N/A N/A 73 Petition Actions Advance Tribal Notification of Certain Radioactive Material Shipments N/A N/A NRC-2021-0051 PRM-37-2 N/A N/A N/A N/A N/A N/A 74 Petition Actions Alternative Method for Calculating Embrittlement for Steel Reactor Vessels N/A N/A NRC-2019-0180 PRM-50-120 N/A N/A N/A N/A N/A N/A

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 9 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 75 Petition Actions Criteria to Return Retired Nuclear Power Reactors to Operations N/A N/A NRC-2019-0063 PRM-50-117 N/A N/A N/A N/A N/A N/A 76 Petition Actions Determining Which Structures, Systems, and Components and Functions Are Important to Safety N/A N/A NRC-2015-0213 PRM-50-112 N/A N/A N/A N/A N/A N/A 77 Petition Actions Elimination of Immediate Notification Requirements for Non-Emergency Events N/A N/A NRC-2018-0201 PRM-50-116 N/A N/A N/A N/A N/A N/A 78 Petition Actions Linear No-Threshold Model and Standards for Protection against Radiation N/A N/A NRC-2015-0057 PRM-20-28 N/A N/A N/A N/A N/A N/A 79 Petition Actions Linear No-Threshold Model and Standards for Protection against Radiation N/A N/A NRC-2015-0057 PRM-20-29 N/A N/A N/A N/A N/A N/A 80 Petition Actions Linear No-Threshold Model and Standards for Protection against Radiation N/A N/A NRC-2015-0057 PRM-20-30 N/A N/A N/A N/A N/A N/A 81 Petition Actions Protection of Digital Computer and Communication Systems and Networks N/A N/A NRC-2014-0165 PRM-73-18 N/A N/A N/A N/A N/A N/A 82 Petition Actions Public Protective Actions During a General Emergency N/A N/A NRC-2020-0155 PRM-50-123 N/A N/A N/A N/A N/A N/A

xx U.S. Nuclear Regulatory Commission Rulemaking Activities Planned (As of April 2, 2021) 10 Attachment Item Category Title CPR Priority RIN Docket ID Associated PRM Numbers Rulemaking Initiation Date Regulatory Basis Publication Date Proposed Rule to Signature Authority Proposed Rule Publication Date Final Rule to Signature Authority Final Rule Publication Date 83 Petition Actions Reporting Nuclear Medicine Injection Extravasations as Medical Events N/A N/A NRC-2020-0141 PRM-35-22 N/A N/A N/A N/A N/A N/A 84 Petition Actions Voluntary Adoption of Revised Design Basis Accident Dose Criteria N/A N/A NRC-2020-0055 PRM-50-121 N/A N/A N/A N/A N/A N/A Line 13 = The NRC staff, after reconsidering the need for additional requirements, provided options and recommendations to the Commission on October 1, 2019.

Line 18 = The NRC staff, after reconsidering the need for additional requirements, provided options and recommendations to the Commission on October 9, 2019.

Line 51 = This rulemaking activity is currently on hold. The dates listed are temporary placeholders pending the scheduling of an adjudicatory hearing on the DOE license application, which must be completed before the Commission decides whether to authorize construction of a geologic repository for high-level nuclear waste at Yucca Mountain, NV. The NRC will initiate requisite rulemaking activities pending the outcome of the licensing decision.

Line 52 = This rulemaking activity is currently on hold. The dates listed are temporary placeholders pending the scheduling of an adjudicatory hearing on the DOE license application, which must be completed before the Commission decides whether to authorize construction of a geologic repository for high-level nuclear waste at Yucca Mountain, NV. The NRC will initiate requisite rulemaking activities pending the outcome of the licensing decision.

Line 65 = The NRC staff, after reconsidering the need for additional requirements provided a recommendation to the Commission on March 5, 2021.