Status of NRCs Review of the Westinghouse Columbia Fuel Fabrication Facility License Renewal Application NRC Public Meeting February 4, 2021 2:00pm - 3:00pm ET David Tiktinsky Diana Diaz-Toro Senior Project Manager Project Manager
AGENDA Welcome and Introductions Westinghouses CFFF Environmental Improvements Presentation NRCs Status Update of the License Renewal Review: Safety & Environmental Reviews Public Questions Adjourn
NEPA Environmental Review Status Diana Diaz-Toro Project Manager
NEPA Environmental Review July 2014
- Westinghouse re-submitted its license renewal application to the NRC requesting to renew its operating license for an additional 40 years June 2018
- NRC staff published a final environmental assessment (EA) and Finding of No Significant Impact (FONSI) (83 FR 28014)
October 2019
- NRC staff re-opened its environmental review and published a draft EA for public review and comment (84 FR 57777)
June 2020
- NRC staff decides to prepare an environmental impact statement (85 FR 46193)
Environmental Impact Statement (EIS)
July 2020 Notice of Intent to Prepare an EIS & Begin Scoping Process August 2020 End of Scoping Comment Period November 2020 Issuance of Requests for Additional Information (RAIs)
December 2020 Responses to the RAIs June 2021 Publication of the Draft EIS for Public Review and Comment January 2022 Publication of the Final EIS February 2022 Publication of the Record of Decision
Safety Review Status David Tiktinsky Senior Project Manager
Safety Review July 2014
- Westinghouse re-submitted its license renewal application to the NRC requesting to renew its operating license for an additional 40 years July 2020
- NRC completed its safety review with the exception of environmental impacts and decommissioning. These portions will be completed after the EIS is developed February 2022
- NRC makes licensing decision and issues its record of decision (including the safety evaluation report)
FOR MORE INFORMATION Visit the NRCs Website at https://www.nrc.gov/info-finder/fc/westinghouse-fuel-fab-fac-sc-lc.html Visit Find documents online in the Agencywide Documents Access and Management System (ADAMS) at: