ES-301 Administrative Topics Outline Form ES-301-1 Facility: DC COOK Date of Examination: 7-23-2018 Examination Level: RO SRO Operating Test Number: __________

Administrative Topic (see Note) Type Code* Describe activity to be performed R-D Perform a Thermal Power Calculation KA SYS 015 Conduct of Operations A1.01 3.5/3.8, 2.1.19, 2.1.45 Conduct of Operations Determine Clearance Boundaries for Safety Injection Equipment Control System Leak R-N KA 2.2.13 3.6/3.8 Perform Monthly Rad Liquid And Gaseous Monitor Radiation Control Source Checks per 2-OHP-4030-214-057 S-N Attachment 2 K/A 2.3.5 2.9/2.9, K/A 073 A4.03 4.3/4.0 Complete EMD-32A Nuclear Plant Event Emergency Plan Notification Form per PMP-2080-EPP-107. K/A R-D 2.4.39 3.9/3.8 P 2016 NOTE: All items (five total) are required for SROs. RO applicants require only four items unless they are retaking only the administrative topics (which would require all five items).

  • Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)

(N)ew or (M)odified from bank ( 1)

(P)revious 2 exams ( 1; randomly selected)

ES-301 Administrative Topics Outline Form ES-301-1 Facility: DC COOK Date of Examination: 7-23-2018 Examination Level: RO SRO Operating Test Number: __________

Administrative Topic (see Note) Type Describe activity to be performed Code*

R-D Review a Thermal Power Calculation Conduct of Operations KA SYS 015 A1.01 3.5/3.8, 2.1.19, 2.1.45 Determine if Core Alterations may Continue Conduct of Operations (Review 2-OHP-4939-227-037 Data Sheet 3)

R-N KA 2.1.40 (3.9)

Verify Clearance Boundaries for Safety Injection Equipment Control system Leak and determine the required Technical R-N Specifications KA 2.2.13 3.6/3.8 Review Liquid Release (Alternate Path)

Radiation Control R-D K/A 2.3.6 (3.1)

Perform an Emergency Plan Classification with PAR Emergency Plan per PMP-2080-EPP-101.

R-M KA 2.4.44 (4.0)

NOTE: All items (five total) are required for SROs. RO applicants require only four items unless they are retaking only the administrative topics (which would require all five items).

  • Type Codes & Criteria: (C)ontrol room, (S)imulator, or Class(R)oom (D)irect from bank ( 3 for ROs; 4 for SROs & RO retakes)