MONTHYEARML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination ML22251A0192022-08-10010 August 2022 Form 5.1-1 Postexamination Check Sheet DC-Cook 2022 ML22251A0162022-08-10010 August 2022 Form 2.1-1 Examination Preparation Checklist DC-Cook 2022 ML22250A7202022-08-10010 August 2022 Form 1.3-1 Exam Security Agreement DC-Cook 2022 ML22251A0202022-08-0202 August 2022 Post Examination Submittal Letter DC-Cook 2022 ML22192A1192022-07-11011 July 2022 Operator Licensing Examination Approval ML22250A6912022-06-30030 June 2022 Form_2.3-4_Written_Exam_Quality_Checklist_DC-Cook_2022 ML22250A6902022-06-30030 June 2022 Form_2.3-2_Operating_Test_Quality_Checklist_DC-Cook_2022 ML22250A6652022-06-30030 June 2022 Form: 2.3-1 Examination Outline Quality Checklist DC-Cook - 2022 ML22250A6692022-06-30030 June 2022 Form 3.4.1 Events and Evolutions Checklist DC-Cook 2022 ML22250A6922022-05-12012 May 2022 Licensee_Iinitial_License_Exam_Submittal_Letter_DC-Cook_2022 AEP-NRC-2022-20, Response to NRC Regulatory Issue Summary 2022-01 Preparation and Scheduling of Operator Licensing Examinations2022-03-14014 March 2022 Response to NRC Regulatory Issue Summary 2022-01 Preparation and Scheduling of Operator Licensing Examinations ML22250A6712022-02-16016 February 2022 Outline Submittal Notification Email DC-Cook 2022 ML22032A0392022-02-0101 February 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21347A5742021-12-29029 December 2021 Confirmation of Initial License Examination ML21110A5272021-04-19019 April 2021 GFE Results, March 2021 IR 05000315/20203012020-10-19019 October 2020 NRC Initial License Examination Report 05000315/2020301; 05000316/2020301 ML20356A0912020-08-25025 August 2020 2020 DC Cook Ile Proposed Control Room and In-Plant Systems JPMs ML20356A0842020-08-25025 August 2020 2020 DC Cook Ile Simulator Scenario Quality Checklist ES-301-4 ML20356A1522020-08-25025 August 2020 2020 DC Cook Ile Written Exam Outlines ES-401-2 and ES-401-3 ML21006A2222020-08-25025 August 2020 2020 DC Cook Ile Operating Test Outline Submittal Letter ML20356A0332020-08-25025 August 2020 2020 DC Cook Ile Operating Test Competencies Checklist ES-301-6 ML20356A2592020-08-25025 August 2020 2020 DC Cook Ile As-Administered Control Room and In-Plant Systems JPMs ML21006A4402020-08-25025 August 2020 2020 DC Cook Ile Post Exam Package Submittal Letter and Comment Summary Rcvd 20200825 ML21006A4372020-08-25025 August 2020 2020 DC Cook Ile Exam Preparation Checklist ES-201-1 ML20356A0742020-08-25025 August 2020 2020 DC Cook Ile Operating Test Quality Checklist ES-301-3 ML21005A4312020-08-25025 August 2020 2020 DC Cook Ile As-Administered Simulator Scenarios ML21006A4292020-08-25025 August 2020 2020 DC Cook Ile Exam Security Checklists ES-201-3 ML20356A2652020-08-25025 August 2020 2020 DC Cook Ile As-Administered RO and SRO Admin JPMs ML21006A4102020-08-25025 August 2020 2020 DC Cook Ile Operating Test Review Worksheet ES-301-7 ML20356A0802020-08-25025 August 2020 2020 DC Cook Ile Proposed Exam Submittal Letter ML21006A4412020-08-25025 August 2020 2020 DC Cook Ile Written Exam Grading Quality Checklist ES-403-1 RO ML20356A1602020-08-25025 August 2020 2020 DC Cook Ile Exam Outline Quality Checklist ES-201-2 ML20356A0862020-08-25025 August 2020 2020 DC Cook Ile Written Examination Quality Checklist ES-401-6 ML20356A1572020-08-25025 August 2020 2020 DC Cook Ile Transient and Event Checklists ES-301-5 ML20356A2572020-08-25025 August 2020 2020 DC Cook Ile As-Administered RO SRO Written Examination ML20356A1012020-08-25025 August 2020 2020 DC Cook Ile Proposed Simulator Scenarios ML20356A1412020-08-25025 August 2020 2020 DC Cook Ile Operating Test JPM Outlines ES-301-1 and ES-301-2 ML20356A1492020-08-25025 August 2020 2020 DC Cook Ile Operating Test Scenario Outlines ES-D-1 ML20356A0992020-08-25025 August 2020 2020 DC Cook Ile Proposed Ro_Sro Written Examination ML21006A4182020-08-25025 August 2020 2020 DC Cook Ile Record of Rejected KAs ES-401-4 ML21006A4202020-08-25025 August 2020 2020 DC Cook Ile Written Exam Review Worksheet ES-401-9 ML20356A0952020-08-25025 August 2020 2020 DC Cook Ile Proposed RO and SRO Admin JPMs ML21006A4442020-08-25025 August 2020 2020 DC Cook Ile Written Exam Grading Quality Checklist ES-403-1 SRO ML20364A2132020-08-13013 August 2020 2018 Donald C. Cook Nuclear Power Plant Exam Administered Scenarios ML20210M4202020-07-29029 July 2020 Operator Licensing Examination Approval ML19353A0252019-12-18018 December 2019 Confirmation of Initial License Examination AEP-NRC-2019-26, Response to RIS 2019-022019-05-30030 May 2019 Response to RIS 2019-02 ML19106A0162019-04-15015 April 2019 GFE Results, March 2019 ML19045A3722019-02-12012 February 2019 March 2019 GFE Cover Letter Riii 2023-12-05
[Table view] Category:Part 55 Examination Related Material
MONTHYEARML23338A2642023-12-0505 December 2023 Confirmation of Initial License Examination ML22251A0162022-08-10010 August 2022 Form 2.1-1 Examination Preparation Checklist DC-Cook 2022 ML22251A0192022-08-10010 August 2022 Form 5.1-1 Postexamination Check Sheet DC-Cook 2022 ML22250A7202022-08-10010 August 2022 Form 1.3-1 Exam Security Agreement DC-Cook 2022 ML22251A0202022-08-0202 August 2022 Post Examination Submittal Letter DC-Cook 2022 ML22192A1192022-07-11011 July 2022 Operator Licensing Examination Approval ML22250A6692022-06-30030 June 2022 Form 3.4.1 Events and Evolutions Checklist DC-Cook 2022 ML22250A6902022-06-30030 June 2022 Form_2.3-2_Operating_Test_Quality_Checklist_DC-Cook_2022 ML22250A6912022-06-30030 June 2022 Form_2.3-4_Written_Exam_Quality_Checklist_DC-Cook_2022 ML22250A6652022-06-30030 June 2022 Form: 2.3-1 Examination Outline Quality Checklist DC-Cook - 2022 ML22250A6922022-05-12012 May 2022 Licensee_Iinitial_License_Exam_Submittal_Letter_DC-Cook_2022 AEP-NRC-2022-20, Response to NRC Regulatory Issue Summary 2022-01 Preparation and Scheduling of Operator Licensing Examinations2022-03-14014 March 2022 Response to NRC Regulatory Issue Summary 2022-01 Preparation and Scheduling of Operator Licensing Examinations ML22250A6712022-02-16016 February 2022 Outline Submittal Notification Email DC-Cook 2022 ML22032A0392022-02-0101 February 2022 Notification of an NRC Biennial Licensed Operator Requalification Program Inspection and Request for Information ML21347A5742021-12-29029 December 2021 Confirmation of Initial License Examination IR 05000315/20203012020-10-19019 October 2020 NRC Initial License Examination Report 05000315/2020301; 05000316/2020301 ML21006A4202020-08-25025 August 2020 2020 DC Cook Ile Written Exam Review Worksheet ES-401-9 ML20356A1012020-08-25025 August 2020 2020 DC Cook Ile Proposed Simulator Scenarios ML20356A0862020-08-25025 August 2020 2020 DC Cook Ile Written Examination Quality Checklist ES-401-6 ML20356A1412020-08-25025 August 2020 2020 DC Cook Ile Operating Test JPM Outlines ES-301-1 and ES-301-2 ML20356A0742020-08-25025 August 2020 2020 DC Cook Ile Operating Test Quality Checklist ES-301-3 ML21006A4372020-08-25025 August 2020 2020 DC Cook Ile Exam Preparation Checklist ES-201-1 ML20356A0332020-08-25025 August 2020 2020 DC Cook Ile Operating Test Competencies Checklist ES-301-6 ML21006A2222020-08-25025 August 2020 2020 DC Cook Ile Operating Test Outline Submittal Letter ML20356A1602020-08-25025 August 2020 2020 DC Cook Ile Exam Outline Quality Checklist ES-201-2 ML20356A0842020-08-25025 August 2020 2020 DC Cook Ile Simulator Scenario Quality Checklist ES-301-4 ML21006A4442020-08-25025 August 2020 2020 DC Cook Ile Written Exam Grading Quality Checklist ES-403-1 SRO ML20356A2652020-08-25025 August 2020 2020 DC Cook Ile As-Administered RO and SRO Admin JPMs ML20356A0802020-08-25025 August 2020 2020 DC Cook Ile Proposed Exam Submittal Letter ML20356A1522020-08-25025 August 2020 2020 DC Cook Ile Written Exam Outlines ES-401-2 and ES-401-3 ML20356A1492020-08-25025 August 2020 2020 DC Cook Ile Operating Test Scenario Outlines ES-D-1 ML21006A4182020-08-25025 August 2020 2020 DC Cook Ile Record of Rejected KAs ES-401-4 ML20356A0992020-08-25025 August 2020 2020 DC Cook Ile Proposed Ro_Sro Written Examination ML21005A4312020-08-25025 August 2020 2020 DC Cook Ile As-Administered Simulator Scenarios ML21006A4412020-08-25025 August 2020 2020 DC Cook Ile Written Exam Grading Quality Checklist ES-403-1 RO ML20356A0952020-08-25025 August 2020 2020 DC Cook Ile Proposed RO and SRO Admin JPMs ML21006A4102020-08-25025 August 2020 2020 DC Cook Ile Operating Test Review Worksheet ES-301-7 ML20356A1572020-08-25025 August 2020 2020 DC Cook Ile Transient and Event Checklists ES-301-5 ML21006A4292020-08-25025 August 2020 2020 DC Cook Ile Exam Security Checklists ES-201-3 ML20356A2572020-08-25025 August 2020 2020 DC Cook Ile As-Administered RO SRO Written Examination ML21006A4402020-08-25025 August 2020 2020 DC Cook Ile Post Exam Package Submittal Letter and Comment Summary Rcvd 20200825 ML20356A2592020-08-25025 August 2020 2020 DC Cook Ile As-Administered Control Room and In-Plant Systems JPMs ML20356A0912020-08-25025 August 2020 2020 DC Cook Ile Proposed Control Room and In-Plant Systems JPMs ML20364A2132020-08-13013 August 2020 2018 Donald C. Cook Nuclear Power Plant Exam Administered Scenarios ML20210M4202020-07-29029 July 2020 Operator Licensing Examination Approval ML19353A0252019-12-18018 December 2019 Confirmation of Initial License Examination AEP-NRC-2019-26, Response to RIS 2019-022019-05-30030 May 2019 Response to RIS 2019-02 ML20365A0662018-08-13013 August 2018 2018 Donald C. Cook Nuclear Power Plant Exam Form ES-201-1 ML20363A0982018-08-13013 August 2018 2018 Donald C. Cook Nuclear Power Plant Exam Form ES-401-6 ML20363A1042018-08-13013 August 2018 2018 Donald C. Cook Nuclear Power Plant Exam Proposed JPMs 2023-12-05
[Table view] |
Text
ES-401 Generic Knowledge and Abilities Outline (Tier 3) Form ES-401-3 Facility: D.C. Cook Date of Exam: 06/18/2018 Category K/A # Topic RO SRO-only IR # IR #
Knowledge of shift or short-term relief turnover 2.1.3 3.7 66 practices.
(CFR: 41.10 / 45.13)
Knowledge of individual licensed operator 2.1.4 3.8 94 responsibilities related to shift staffing, such as medical requirements, no-solo operation, maintenance of active license status, 10CFR55, etc.
(CFR: 41.10 / 43.2)
- 1. Conduct of Ability to use plant computers to evaluate system or 2.1.19 3.9 67 Operations component status.
(CFR: 41.10 / 45.12)
Ability to interpret reference materials, such as graphs, 2.1.25 3.9 68 curves, tables, etc.
(CFR: 41.10 / 43.5 / 45.2, 45.6)
Knowledge of primary and secondary plant chemistry 2.1.34 3.5 95 limits (CFR: 41.10 / 43.5 / 45.12)
Subtotal 3 2 Ability to perform pre-startup procedures for the facility, 2.2.1 4.5 69 including operating those controls associated with plant equipment that could affect reactivity.
(CFR: 41.5, 41.10 / 43.5, 43.6 / 45.1)
Knowledge of the process for making design or 2.2.5 3.2 96 operating changes to the facility.
- 2. Equipment (CFR: 41.10 / 43.3 / 45.13)
Control Ability to determine Technical Specification Mode of 2.2.35 3.6 70 Operation (CFR: 41.7, 41.10 / 43.2 / 45.13)
Knowledge of conditions and limitations in the facility 2.2.38 4.5 97 license.
(CFR: 41.7 / 43.5 / 45.12)
Subtotal 2 2 Knowledge of radiation exposure limits under normal 2.3.4 3.2 71 and emergency conditions.
(CFR: 41.12 / 43.4 / 45.10)
Ability to approve release permits 2.3.5 3.8 98 (CFR: 41.11, 41.12 / 43.4 / 45.9)
- 3. Radiation Knowledge of radiological safety procedures pertaining 2.3.13 3.4 72 Control to licensed operator duties, such as response to radiation monitor alarms, containment entry requirements, fuel handling responsibilities, access to locked high-radiation areas, filters, etc.
(CFR: 41.12 / 43.4 / 45.9, 45.10)
Subtotal 2 1 Knowledge of system set points, interlocks and 2.4.2 4.5 73 automatic actions associated with EOP entry conditions (CFR: 41.7 / 43.5 / 45.13)
Knowledge of EOP mitigation strategies.
- 4. Emergency 2.4.6 3.7 74 (CFR: 41.10 / 43.5 / 45.13)
Procedures/Plan Knowledge of the specific bases for EOPs 2.4.18 4.0 99 (CFR: 41.10 / 43.1 / 45.13)
Knowledge of the emergency plan 2.4.29 4.4 100 (CFR: 41.10 / 43.5 / 45.13)
ES-401 Generic Knowledge and Abilities Outline (Tier 3) Form ES-401-3 Knowledge of operator response to loss of all 2.4.32 3.6 75 annunciators (CFR: 41.10 / 43.5 / 45.13)
Subtotal 3 2 Tier 3 Point Total 10 7