l March 27, 1989 Docket No. 50-368 Mr. T. Gene Campbell Vice President, Nuclear Operations Arkansas Power and Light Company Post Office Box 551 Little Rock, Arkansas 72203
Dear Mr. Campbell:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION - SIMULATOR CERTIFICATION FOR ARKANSAS NUCLEAR ONE, UNIT 2 (ANO-2) (TAC NO. 72192)
The staff has completed its review of your initial Simulator Certification submittal dated December 7, 1987. This review has identified several areas where additional information and data are needed to ensure complete docu-mentation of your certification. These areas are described in the enclosure.
We request that you provide the data and reply to the questions no later than May 31, 1989 so that this information may be promptly incorporated in the staff's records.
If you cannot meet this schedule, please contact me as soon as possible.
As indicated above, our review is only to ensure completeness of documentation.
The review does not, nor is it intended to, verify the accuracy 07 the data or statements made in the certification, nor provide NRC approval of the acceptability of a particular simulator for use in administering operating tests.
The reporting and/or recordkeeping requirements of this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely,
/s/
Chester Poslusny Jr., Project Manager Project Directorate - IV Division of Reactor Projects - III, IV, V and Special Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
/
See next page i
DISTRIBUTION:
l lj Docket File e NRC PDR Local PDR PD4 Reading
/
L. Rubenstein' J. Calvo P. Noonan C. Poslusny OGC-Rockville E. Jordan B. Grimes ACRS(10)
PD4 Plant File G. Holahan b
PD4/LA PD4/PM-OLB/
Q PD4/D /
PN00NA CPOSLUSNY:bj KP NS JCALVO 03%
03/$/89 03/M/89 03/47/89
[i 8904110472 890327 PDR ADOCK 05002368 P
yDC
v.
March 27, 1989 Docket No. 50-368
-Mr. T. Gene Campbell
.q Vice President, Nuclear j
Operations Arkansas Power and Light Company
- Post Office Box 551
)
Little Rock.- Artsnsas 72203
Dear Mr.' Campbell:
q
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION - SIMULATOR CERTIFICATION FOR ARKANSAS NUCLEAR ONE, UNIT 2 (ANO-2) (TAC NO. 72192)
The staff has completed its review of your initial Simulator Certification submittal dated December 7, 1987. This review has identified several areas q
where additional information and data are needed to ensure complete docu-mentation of your certification. These areas are described in the enclosure.
We request that you provide the data and reply to the questions no later than May 31, 1989 so that this information may be promptly incorporated in the staff's records.
If you cannot meet this schedule, please contact me as soon as possible.
As indicated above, our review is only to ensure completeness of documentation.
The review does not, nor is it intended to, verify the accuracy of the data or statements made in the certification, nor provide NRC approval of the acceptability of a particular simulator for use in administering operating tests.
The reporting and/or recordkeeping requirements of this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely,
/s/
Chester Poslusny Jr., Project Manager Project Directorate - IV Division of Reactor Projects - III, IV, Y and Special Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated i
cc w/ enclosure:
See next page 1
DISTRIBUTION:
Docket File NRC PDR Local PDR PD4 Reading L. Rubenstein J. Calvo P. Noonan C. Poslusny OGC-Rockville E. Jordan B. Grimes ACRS(10)
PD4 Plant File G. Holahan PD4/LA PD4/PM OLB/
Q PD4/D /
PN00NA CPOSLUSNY:bj KP INS JCALVO 03%
03/d/89 03/M/89 03/t7/89
1 1
/
o,,
UNITED STATES NUCLEAR REGULATORY COMMISSION
[
p,
- E WASHINGTON. D. C. 20666
- . '.. +
March 27,1989 Docket No. 50-368 Mr. T. Gene Campbell Vice President, Nuclear Operations Arkansas Power and Light Company Post Office Box 551 Little Rock, Arkansas 72203
Dear Mr. Campbell:
SUBJECT:
REQUEST FOR ADDITIONAL INFORMATION - SIMULATOR CERTIFICATION FOR ARKANSAS NUCLEAR ONE, UNIT 2 (ANO-2) (TAC NO. 72192)
The staff has completed its review of your initial Simulator Certification submittal dated December 7,1987. This review has identified several areas where additional information and data are needed to ensure comp'lete docu-mentation of your certification. These areas are described in the enclosure.
We request that you provide the data and reply to the questions no later than May 31, 1989 so that this infomation may be promptly incorporated in the staff's records.
If you cannot meet this schedule, please contact me as soon as possible.
As indicated above, our review is only to ensure completeness of documentation.
The review does not, nor is it intended to, verify the accuracy of the data or statements made in the certification, nor provide NRC approval of the acceptability of a particular simulator for use in administering operating tests.
The reporting and/or recordkeeping requirements.of this letter affect fewer than ten respondents; therefore, OMB clearance is not required under P.L.96-511.
Sincerely, to VV Chester Poslusny Jr.,
rejectManager Project Directorate - IV Division of Reactor Projects - III, IV, Y and Special Projects Office of Nuclear Reactor Regulation
Enclosure:
As stated cc w/ enclosure:
See next page
.t Mr. T. Gene Campbell Arkansas Power & Light Company Arkansas Nuclear One, Unit 2 cc:
Mr. Dan R. Howard, Manager Mr. Charles B. Brinkman, Manager Licensing Washington Nuclear Operations Arkansas Nuclear One Combustion Engineering, Inc.
P. O. Box 608 12300 Twinbrook Parkway, Suite 330 Russellville, Arkansas 72801 Rockville, Maryland 20852 Mr. James M. Levine, Executive Director Site Nuclear Operations Honorable William Abernathy Arkansas Nuclear One County Judge of Pope County P. O. Box 698 Pope County Courthouse Russellville, Arkansas 72801 Russellville, Arkansas 72801 Mr. Nicholas S. Reynolds Bishop, Cook, Perce11 & Reynolds 1400 L Street, N.W.
Washington, D.C.
20005-3502 f
Regional Administrator, Region IV U.S. Nuclear Regulatory Comission Office of Executive Director for Operations 611 Ryan Plaza Drive, Suite 1000 Arlington, Texas 76011 Senior Resident Inspector U.S. Nuclear Regulatory Comission 1 Nuclear Plant Road Russellville, Arkansas 72801 Ms. Greta Dieus, Director Division of Environmental Health Protection Arkansas Department of Health 4815 West Markam Street Little Rock, Arkansas 72201 Mr. Robert B. Borsum Babcock & Wilcox Nuclear Power Generation Division 1700 Rockville Pike, Suite 525 Rockville, Maryland 20852
____m_________-.___m_.____
(
ENCLOSURE I
l l
1.
The attachment, " Abstract: Performance Test Development, Conduct and i
Evaluation" and its subsequent attachments, submitted with Form 474 do J
not provide sufficient information regarding the results of the performance testing. For all tests performed for initial certification please provide documentation of the results including:
- Final Conditions
- Description of baseline data used to determine fidelity to the reference plant
- Deficiencies found as a result of the tests, corrective actions planned and dates by which corrections will be made.
If the baseline data used was the judgement of a panel of experts then documentation of their review, sufficient for a third party to evaluate the adequacy of the tests and results, should be included. Comparisons to the " Anticipated Plant Response" sheets including any differing professional opinions as to the outcome of the tests would be helpful.
2.
In Exception 2 of your submittal you state that you have identified no conditions which require " administrative controls or other means... to alert the instructor when certain parameters approach values indicative of events beyond the implemented model or known plant behavior."
NUREG-1258 explains that "it is essential, for the conduct of a licensing examination, that the simulation facility permit a candidate to mitigate the consequences of an event using the reference plant's Emergency Operating Procedures (EOPs)." E0Ps normally include operator actions for mitigating events which have progressed beyond plant design limits.
Furthermore, in Attachment 3, Simulator Fidelity Testing Guideline,"
items 6.1.3f and 6.3.3f state that reaching the simulator operating limits is one of the criteria for terminating a transient test. Please provide an explanation of this apparent conflict.
If you have identified simulator operating limits then test documentation must be provided verifying compliance to Section 4.3 of ANSI /ANS-3.5-1985 or additional justification for exception is required.
3.
In item I.B, " Transient Testing," of the abstract you state that
... selected transients were performed using plant response predicted in the Safety Analysis Report..." ANSI /ANS-3.5-1985 states in Appendix A, Section A.3.3(2) that FSAR transients may be inappropriate for real-time cynamic simulation comparisons. Please state which transients were compared to the plant response predicted in the Safety Analysis Report and provide a justification for making such a comparison.
The set of transients you list is not the same as those required in ANSI /ANS-3.5-1985, Appendix B, Section B.2.2.
Please provide justification for using the set of transients you list or provide performance test abstracts for the Appendix B transients.
4.
With regard to Attachment 3, " Simulator Fidelity Testing Guideline," Item 4.1.c.3 on page 11, it is not clear that the annual operability testing includes approximately 25% of the " Plant Malfunctions in ANSI /ANS-3.5-1985, Section 3.1.2.
Please confirm that such testing is included.
5.
Attachments 7, 8, and 9,* Simulator Modification Control Guidelines,"
" Simulator Design Control Guidelines," and " Simulator DCP Control Guideline," respectively, appear to be draft versions of these procedures.
Please send copies of signed, final versions.of these procedures and confirm that simulator modification and design control is performed in accordance with these procedures.
6.
An unsigned, incomplete copy of procedure ERC871030, " Simulator Operability Test", was included in your submittal. Were the tests described in this document performed for initial certification? If so, please send a copy of the completed version of this document including the test results.